TIME SCHEDULE PEMBANGUNAN GEDUNG KULIAH UNIVERSITAS BANDAR LAMPUNGLOKASI : GEDUNG MENENG, BANDAR LAMPUNG TAHUN ANGGARAN : 2010TAHUN 2010 NO URAIAN PEKERJAAN BOBOT NOPEMBER6/11 13/11 20/11 27/11 4/12

TAHUN 2011 DESESEMBER11/12 18/12 25/12 1/1 8/1

JANUARI15/1 22/1 29/1 5/2

PEBRUARI12/2 19/2 26/2 5/3

MARET12/3 19/3 26/3 2/4 9/4

APRIL16/4 23/4 30/4 7/5 14/5

MEI21/5 28/5 4/6

JUNI11/6 18/6 25/6 2/7 9/7

JULI16/7 23/7 30/7

AGUSTUS6/8 13/8 20/8

KET

1 A B I II III IV V VI C PEKERJAAN PENDAHULUAN PEKERJAAN STRUKTUR BASEMENT LANTAI I LANTAI II LANTAI III LANTAI IV LANTAI DAK PEKERJAAN RANGKA DAN ATAP 100.00 SCHEDULE ACUMULATIVE SCHEDULE ACTUAL ACUMULATIVE ACTUAL DEVIASI0.90 -

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

0.022

-

-

1

0.40 1.31 0.95 1.50 0.19

0.21 1.52 0.30 1.80 0.28

3.71 5.23 0.02 1.83 -3.40

3.71 8.94 -0.01 1.82 -7.12

0.02 8.95 0.00 1.82 -7.14

0.28 9.24 0.00 1.82 -7.42

6.57 15.81 0.00 1.82 -13.99

3.51 19.32 29.50 31.31 11.99

1.44 20.76 0.00 31.31 10.56

1.44 22.19 1.84 33.15 10.96

1.44 23.63 2.00 35.16 11.53

7.46 31.09 0.09 35.25 4.15

1.66 32.75 0.00 35.25 2.50

1.66 34.40 0.00 35.25 0.84

2.05 36.45 1.76 37.01 0.56

2.05 38.50 5.40 42.41 3.91

8.30 46.81 2.41 44.82 -1.99

3.38 50.19 0.00 44.82 -5.37

2.09 52.28 0.00 44.82 -7.46

2.09 54.37 4.04 48.86 -5.51

9.38 63.75 1.60 50.46 -13.29

3.59 67.34 1.48 51.94 -15.40

2.38 69.72 1.20 53.15 -16.58

2.47 72.20 0.36 53.51 -18.69

10.59 82.79 10.01 63.52 -19.27

3.55 86.34 1.58 65.09 -21.24

1.52 87.86 3.09 68.18 -19.68

1.43 89.29 1.95 70.13 -19.15

3.81 93.10 3.67 73.80 -19.30

1.72 94.82 7.79 81.59 -13.23

1.75 96.57 1.64 83.23 -13.34

1.62 98.18 1.64 84.86 -13.32

1.82 100.00 2.93 87.79 -12.21 100.00 4.67 92.45 -7.55 100.00 0.38 92.83 -7.17 100.00 1.02 93.85 -6.15 100.00 1.45 95.30 -4.70 100.00 0.30 95.60 -4.40 100.00 0.26 95.86 -4.14 100.00 1.45 97.31 -2.69 100.00 2.69 100.00 0.00

-

0.90 0.55 0.55 -0.35

9 8 7 6 5 4 3 2 1 0

: ACTUAL : SCHEDULE Bandar Lampung, 20 Agustus 2011

MENYETUJUI

DI AJUKAN OLEH

DR. IR. HERY RIYANTO. MT

IR. LILYANA

TIME SCHEDULE PEMBANGUNAN GEDUNG KULIAH UNIVERSITAS BANDAR LAMPUNGLOKASI : GEDUNG MENENG, BANDAR LAMPUNG TAHUN ANGGARAN : 2010TAHUN 2010 NO URAIAN PEKERJAAN BOBOT NOPEMBER6/11 13/11 20/11 27/11 4/12

TAHUN 2011 DESESEMBER11/12 18/12 25/12 1/1 8/1

JANUARI15/1 22/1 29/1 5/2

PEBRUARI12/2 19/2 26/2 5/3

MARET12/3 19/3 26/3 2/4 9/4

APRIL16/4 23/4 30/4 7/5 14/5

MEI21/5 28/5 4/5

JUNI11/5 18/5 25/5

1 A B I II III IV V VI C PEKERJAAN PENDAHULUAN PEKERJAAN STRUKTUR BASEMENT LANTAI I LANTAI II LANTAI III LANTAI IV LANTAI DAK PEKERJAAN RANGKA DAN ATAP 100.00 SCHEDULE ACUMULATIVE SCHEDULE ACTUAL ACUMULATIVE ACTUAL DEVIASI0.90 -

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

0.022

-

-

0.40 1.31 0.95 1.50 0.19

0.21 1.52 0.30 1.80 0.28

3.71 5.23 0.02 1.83 -3.40

3.71 8.94 -0.01 1.82 -7.12

0.02 8.95 0.00 1.82 -7.14

0.28 9.24 0.00 1.82 -7.42

6.57 15.81 0.00 1.82 -13.99

3.51 19.32 29.50 31.31 11.99

1.44 20.76 0.00 31.31 10.56

1.44 22.19 1.84 33.15 10.96

1.44 23.63 2.00 35.16 11.53

7.46 31.09 0.09 35.25 4.15

1.66 32.75 0.00 35.25 2.50

1.66 34.40 0.00 35.25 0.84

2.05 36.45 1.76 37.01 0.56

2.05 38.50 5.40 42.41 3.91

8.30 46.81 2.41 44.82 -1.99

3.38 50.19 0.00 44.82 -5.37

2.09 52.28 0.00 44.82 -7.46

2.09 54.37 4.04 48.86 -5.51

9.38 63.75 1.60 50.46 -13.29

3.59 67.34 1.48 51.94 -15.40

2.38 69.72 1.20 53.15 -16.58

2.47 72.20 0.36 53.51 -18.69

10.59 82.79 10.01 63.52 -19.27

3.55 86.34 1.58 65.09 -21.24

1.52 87.86 3.09 68.18 -19.68

1.43 89.29 1.95 70.13 -19.15

3.81 93.10 3.67 73.80 -19.30

1.72 94.82 7.79 81.59 -13.23

1.75 96.57 1.64 83.23 -13.34

1.62 98.18 1.64 84.86 -13.32

1.82 100.00 2.93 87.79 -12.21

-

0.90 0.55 0.55 -0.35

: ACTUAL : SCHEDULEBandar Lampung, 25 Juni 2011 DI AJUKAN OLEH

MENYETUJUI

DR. IR. HERY RIYANTO. MT

IR. LILYANA

IME SCHEDULE ULIAH UNIVERSITAS BANDAR LAMPUNG

NG MENENG, BANDAR LAMPUNG UN ANGGARAN : 2010

KET

1

9 8 7 6 5 4 3 2 1 0

TIME SCHEDULE PEMBANGUNAN GEDUNG KULIAH UNIVERSITAS BANDAR LAMPUNGLOKASI : GEDUNG MENENG, BANDAR LAMPUNG TAHUN ANGGARAN : 2010TAHUN 2010 NO URAIAN PEKERJAAN VOLUME SATUAN BOBOT NOPEMBER6/11 13/11 20/11 27/11 4/12

TAHUN 2011 DESESEMBER11/12 18/12 25/12 1/1 8/1

JANUARI15/1 22/1 29/1 5/2

PEBRUARI12/2 19/2 26/2 5/3

MARET12/3 19/3 26/3 2/4 9/4

APRIL16/4 23/4 30/4 7/5 14/5

MEI21/5 28/5 7/5

JUNO14/5 21/5 28/5

KET

1 A 1 2 3 4 5 $ 6 7 B I 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 II 1 2 3 4 5 6 7 8 PEKERJAAN PENDAHULUAN Pembersihan lokasi Direksikeet dan Gudang Penyediaan obat-obatan ( P3K ) Penyediaan Air Kerja,listrik kerja dll Pemindahan Tiang Listrik Pemindahan Paving Blok Area Parkir Pemasangan Bouwplank PEKERJAAN STRUKTUR BASEMENT Galian tanah utk pondasi Urugan tanah ex. Galian Galian tanah level Basement Urugan pasir bawah pondasi Urugan pasir bawah lantai Lantai Kerja Pas. Beton Foot Plat Pas. Beton Pondasi Tangga K 250 Pas. Beton Tangga K 250 Pas. Pedestal uk.40/40 K 250 Pas. Pedestal uk.40/50 K 250 Pas. Pedestal uk.40/60 K 250 Pas. Pedestal uk.15/40 K 250 Pas. Beton Sloof uk. 15/20 K 250 Pas. Beton Sloof uk. 25/50 K 250 Pas. Beton Sloof uk. 20/40 K 250 Pas. Beton Sloof uk. 20/30 K 250 Pas. Beton Kolom uk. 40/40 ( K4 ) K 250 Pas. Beton Kolom uk. 40/50 ( K3 ) K 250 Pas. Beton Kolom uk. 40/60 ( K1 ) K 250 Pas. Beton Kolom uk. 15/40 ( K5 ) K 250 Pas. Beton Kolom praktis 11/11 ( KP ) K 250 Dinding Penahan Tanah Batu Putih LANTAI I Pas. Tangga Beton K 250 Pas. Beton Kolom uk. 40/40 ( K4 ) K 250 Pas. Beton Kolom uk. 40/50 ( K3 ) K 250 Pas. Beton Kolom uk. 40/60 ( K1 ) K 250 Pas. Beton Kolom uk. 15/40 ( K5 ) K 250 Pas. Beton Kolom praktis 11/11 ( KP ) K 250 Pas. Beton Balok uk. 30/60 ( B1 ) K 250 Pas. Beton Balok uk. 25/60 ( B2 ) K 250

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

100

2,000.00 30.00 1.00 1.00 1.00 800.00 160.00

m2 m2 Ls Ls Ls m2 m'

0.2000 0.2250

0.200 0.100 0.100 0.112 0.112 0.112 0.037 0.112 -

0.0375 0.0525 0.1250-

0.052

0.125 0.075 -

0.1500 0.0220

0.075

0.022 0.022 -

420.00 320.00 800.00 12.00 83.85 8.05 71.78 3.83 4.41 1.78 2.92 30.66 7.08 2.40 20.56 48.24 0.35 2.11 3.52 36.96 1.72 1.02 150.00 4.41 1.92 3.00 33.60 1.56 1.02 2.39 36.69

m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3

0.3307 0.1260

0.083

0.083 0.066

0.083 0.066

0.083 0.198 0.126

0.025

0.025

0.076

0.6300 0.0375

0.630 0.189 0.441 0.019 0.019 0.004 0.262 0.018 1.819 1.819 0.026 0.018 0.018 0.018 -

90

0.2620 0.1107 3.6374 0.3016 0.3476 0.1376 0.2263 2.3761 0.5488 0.2207 1.8889 4.4317 0.0320 0.1637 0.2728 2.8643 0.1330 0.0788 1.4250 0.3650 0.1547 0.2417 2.7068 0.1257 0.0819 0.1845 3.90040.069 0.069 0.018 0.018 -

0.151

0.151

0.087

0.087

0.087

0.087

0.113

0.113

1.188

1.188

0.274

0.274

0.221

1.889

80

4.432

0.032

0.164

0.273

2.864

0.133

0.079

0.285

0.285

0.285

0.285

0.285

0.091

0.091

0.091

0.091

0.077

0.077

0.121

0.121

70

1.353

1.353

0.063

0.063

0.041

0.041

0.046

0.046

0.046

0.046

0.975

0.975

0.975

0.975

9 10 11 12 13 14 15 III 1 2 3 4 5 6 7 8 9 10 11 12 13 14 IV 1 2 3 4 5 6 7 8 9 10 11 12 13 14 V 1 2 3 4 5 6 7 8 9 10

Pas. Beton Balok uk. 20/40 ( B3 ) K 250 Pas Beton Balok uk. 20/30 ( B4 ) K 250 Pas. Beton Balok uk. 15/30 ( B5 ) K 250 Pas. Beton Balok uk. 15/20 ( B6 ) K 250 Pas. Beton Balok uk. 10/20 ( B7 ) K 250 Pas. Beton Plat t.12 cm K 250 Pas. Plat bondek LANTAI II Pas Beton Tangga K 250 Pas Beton Kolom uk. 40/40 ( K4 ) K 250 Pas Beton Kolom uk. 40/60 ( K2 ) K 250 Pas Beton Kolom uk. 15/40 ( K5 ) K 250 Pas Beton Kolom praktis 11/11 ( KP