QUALITY PLAN : 0 PEKERJAAN FIRE FIGHTING : …………2012 : 2 / 6 DIAGRAM ALUR PROSES PELAKSANAAN PEKERJAAN PROSES INSPEKSI & PENGETESAN ALUR A URAIAN PEKERJAAN NOMOR PERSYARATAN MUTU NOMOR WAKTU / FORMULIR PARAMETER SYARAT MUTU FORMULIR FREKUENSI PERALATAN UTAMA I.K YANG DIPERIKSA DITERIMA CEK LIST PEMERIKSAAN Menerima pengiriman material d PM-WS-01 Inspeksi material Peralatan ut PM-WS-01 Merk, type, spek peralatan, Pada saat kualitas bahan, surat jalan Pemasangan peralatan utama pada dudukan: - Pompa Fire IK.M.30 Inspeksi Pemasangan peralatan utama : Posisi unit & akses service Sesuai shop drawing - Pompa Fire IK.IM.30 ALUR B INSTALASI HYDRANT Menerima pengiriman material d PM-WS-01 Inspeksi material Hydrant yang PM-WS-01 - Pipa & Fitting - fitting Pada saat - Box hydrant & Acessories - Isolasi pipa hydrant - Material bantu & Support pipa Ukuran, kondisi fisik Pemasangan instalasi Hydrant: - Pipa & Fitting - fitting IK.M.10 - Box hydrant & Acessories IK.M.34 &35 - Pilar hidrant & Seamese C IK.M.36 - Pipa hydrant luar IK.M.33 Inspeksi Pemasangan instalasi Hydrant: Jarak gantungan, ketinggian pipa - Pipa & Fitting - fitting IK.IM.10 & kondisi sambungan pipa - Box hydrant & Acessories IK.IM.34 &3 Posisi, level Sesuai shop drawing - Pilar hidrant & Seamese C IK.IM.36 Posisi, level Sesuai shop drawing - Pipa hydrant luar IK.IM.33 Kondisi sambungan pipa, gali Sesuai shop drawing - Tes tekan IK.M.67 Kebocoran pipa Sesuai Spek F.IK.M.67 No. Dok. : QP-MEKANIKAL- 02 Revisi Efektif Halaman Sesuai spesifikasi & material serta penerimaan Setelah Unit dipasang F.IK.IM.3 0 Merk, bahan, ketebalan, Sesuai spesifikasi Merk, Type, Ukuran, material serta penerimaan Merk, bahan, Ukuran, Sesuai Spek & shop drawing F.IK.IM.1 0 Saat/setelah pipa dipasang F.IK.IM.3 4 &35 Saat/setelah box dipasang F.IK.IM.3 6 Saat/ setelahdipasang F.IK.IM.3 3 Saat/setelah pipa dipasang Selesai Instalasi pipa PERALATAN UTAMA MULAI CEK PEMASANGAN PERALATAN UTAMA MULAI CEK CEK CEK M ATERIAL HYDRANT PEMASANGAN INSTALASI HYDRANT
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
QUALITY PLAN No. Dok. : QP-MEKANIKAL-02Revisi : 0
PEKERJAAN FIRE FIGHTING Tgl Efektif : …………2012: 2 / 6
DIAGRAM ALUR PROSES PELAKSANAAN PEKERJAAN PROSES INSPEKSI & PENGETESAN PENANGGUNGALUR A URAIAN PEKERJAAN NOMOR PERSYARATAN MUTU NOMOR WAKTU / JAWAB
FORMULIR PARAMETER SYARAT MUTU FORMULIR FREKUENSIPERALATAN UTAMA I.K YANG DIPERIKSA DITERIMA CEK LIST PEMERIKSAAN PROSES
Menerima pengiriman material dari suplier PM-WS-01 Logistik proyek
Inspeksi material Peralatan utama yang diteri PM-WS-01 Merk, type, spek peralatan, Sesuai spesifikasi & aproval Pada saat Logistik proyekkualitas bahan, surat jalan material serta sesuai PO penerimaan material Quality Control
Pemasangan peralatan utama pada dudukan: PM / SM- Pompa Fire IK.M.30 Supervisor
Inspeksi Pemasangan peralatan utama : Posisi unit & akses service Sesuai shop drawing Setelah Unit dipasang Quality Control - Pompa Fire IK.IM.30 F.IK.IM.30 Supervisor
ALUR B INSTALASI HYDRANT
Menerima pengiriman material dari suplier PM-WS-01 Logistik proyek
Inspeksi material Hydrant yang diterima PM-WS-01- Pipa & Fitting - fitting Merk, bahan, ketebalan, kondisi fisik Sesuai spesifikasi & aproval Pada saat Logistik proyek- Box hydrant & Acessories Merk, Type, Ukuran, ketebalan plat material serta sesuai PO penerimaan material Quality Control- Isolasi pipa hydrant Merk, bahan, Ukuran, kondisi fisik- Material bantu & Support pipa Ukuran, kondisi fisik
Inspeksi Pemasangan instalasi Hydrant: Jarak gantungan, ketinggian pipa Quality Control- Pipa & Fitting - fitting IK.IM.10 & kondisi sambungan pipa Sesuai Spek & shop drawing F.IK.IM.10 Supervisor- Box hydrant & Acessories IK.IM.34 &35 Posisi, level Sesuai shop drawing Saat/setelah box dipasang- Pilar hidrant & Seamese Conection IK.IM.36 Posisi, level Sesuai shop drawing F.IK.IM.36 Saat/setelahdipasang- Pipa hydrant luar IK.IM.33 Kondisi sambungan pipa, galian pipa Sesuai shop drawing F.IK.IM.33- Tes tekan IK.M.67 Kebocoran pipa Sesuai Spek F.IK.M.67 Selesai Instalasi pipa
Halaman
PENGENDALIAN
Saat/setelah pipa dipasangF.IK.IM.34
&35
Saat/setelah pipa dipasang
PERALATAN UTAMA
MULAI
CEK
PEMASANGAN PERALATAN
UTAMA
MULAI
CEK
CEK
CEK
MATERIAL HYDRANT
PEMASANGAN INSTALASI HYDRANT
QUALITY PLAN No. Dok. : QP-MEKANIKAL-02Revisi : 0
PEKERJAAN FIRE FIGHTING Tgl Efektif : …………2012: 2 / 6Halaman
ASLI: PT. CIPTA BAYU UTAMA
QUALITY PLAN No. Dok. : QP-MEKANIKAL-02Revisi : 0
PEKERJAAN FIRE FIGHTING Tgl Efektif : …………2012: 3 / 6
DIAGRAM ALUR PROSES PELAKSANAAN PEKERJAAN PROSES INSPEKSI & PENGETESAN PENANGGUNGALUR C URAIAN PEKERJAAN NOMOR PERSYARATAN MUTU NOMOR WAKTU / JAWAB
FORMULIR PARAMETER SYARAT MUTU FORMULIR FREKUENSIINSTALASI SPRINKLER I.K YANG DIPERIKSA DITERIMA CEK LIST PEMERIKSAAN PROSES
Menerima pengiriman material dari suplier PM-WS-01 Logistik proyek
Inspeksi material pipa Sprinkler yang diterima PM-WS-01- Pipa & Fitting - fitting Merk, bahan, ketebalan, kondisi fisik Sesuai spesifikasi & aproval Pada saat Logistik proyek
- Head Sprinkler Merk, type, temperatur kerja material serta sesuai PO penerimaan material Quality Control
- Material bantu & Support pipa Ukuran, kondisi fisik
Inspeksi Pemasangan pipa Sprinkler : Quality Control- Pipa & Fitting - fitting IK.IM.10 Jarak gantungan, ketinggian pipa Sesuai Spek & shop drawing F.IK.IM.10 Saat/setelah pipa Supervisor
& kondisi sambungan pipa dipasang- Head Sprinkler IK.IM.37 & 38 Kerapian, simetris dengan yang lain Sesuai Spek & shop drawing F.IK.IM.37&38 Saat/setelah diisolasi- Tes tekan IK.M.67 Kebocoran pipa Sesuai Spek F.IK.M.67 Selesai Instalasi pipa
ALUR D VALVE & ACESSORIES
Menerima pengiriman material dari suplier PM-WS-01 Logistik proyek
Inspeksi material Valve & Acessories yang diterima PM-WS-01- Valve - Valve Merk, bahan, Class, diameter, kondisi fisik Sesuai spesifikasi & aproval Pada saat Logistik proyek
- MCV & BCV Merk, bahan, Class, diameter, kondisi fisik material serta sesuai PO penerimaan material Quality Control
- Flange & Material bantu Class, Ukuran, kondisi fisik
Inspeksi Pemasangan instalasi Valve & Acessories: Quality Control- Valve - Valve IK.IM.12 Kondisi sambungan & kekencangan murbaut Sesuai Spek & shop drawing F.IK.IM.12 Saat & setelah Valve Supervisor
serta akses operasional diisolasi- MCV & BCV IK.IM.39 Fungsi & serta akses operasional Sesuai Spek & shop drawing F.IK.IM.39 Saat/setelah dipasang
Halaman
PENGENDALIANMULAI
CEK
CEK
MULAI
CEK
CEK
VALVE & ASESORIS
PEMASANGAN VALVE &
ASESORIS
MATERIAL SPRINKLER
PEMASANGAN INSTALASI SPRINKLER
QUALITY PLAN No. Dok. : QP-MEKANIKAL-02Revisi : 0
PEKERJAAN FIRE FIGHTING Tgl Efektif : …………2012: 3 / 6Halaman
ASLI: PT. CIPTA BAYU UTAMA
QUALITY PLAN No. Dok. : QP-MEKANIKAL-02Revisi : 0
PEKERJAAN FIRE FIGHTING Tgl Efektif : …………2012: 4 / 6
DIAGRAM ALUR PROSES PELAKSANAAN PEKERJAAN PROSES INSPEKSI & PENGETESAN PENANGGUNGALUR E URAIAN PEKERJAAN NOMOR PERSYARATAN MUTU NOMOR WAKTU / JAWAB
FORMULIR PARAMETER SYARAT MUTU FORMULIR FREKUENSITRAY / LADDER I.K YANG DIPERIKSA DITERIMA CEK LIST PEMERIKSAAN PROSES
Menerima pengiriman material dari suplier PM-WS-01 Logistik proyek
Inspeksi material Tray/Ladder yang diterima PM-WS-01- Tray/Ladder + Fitting Merk, Type, tebal plat, ukuran, kondisi fisik Sesuai spesifikasi & aproval Pada saat Logistik proyek
- Material bantu & Support Ducting Ukuran, kondisi fisik material serta sesuai PO penerimaan material Quality Control