TESIS PENERAPAN REKAYASA NILAI PADA PROYEK PEMBANGUNAN AMARTHA RESIDENCE I MADE PANDU WEDA WIGUNA PROGRAM PASCASARJANA UNIVERSITAS UDAYANA DENPASAR 2016
17

PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

Feb 08, 2018

Download

Documents

dokiet
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

TESIS

PENERAPAN REKAYASA NILAI PADA PROYEK

PEMBANGUNAN AMARTHA RESIDENCE

I MADE PANDU WEDA WIGUNA

PROGRAM PASCASARJANA

UNIVERSITAS UDAYANA

DENPASAR

2016

Page 2: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

TESIS

PENERAPAN REKAYASA NILAI PADA PROYEK

PEMBANGUNAN AMARTHA RESIDENCE

I MADE PANDU WEDA WIGUNA

1491561022

PROGRAM MAGISTER

PROGRAM STUDI TEKNIK SIPIL

PROGRAM PASCASARJANA

UNIVERSITAS UDAYANA

DENPASAR

2016

Page 3: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

PENERAPAN REKAYASA NILAI PADA PROYEK

PEMBANGUNAN AMARTHA RESIDENCE

Tesis untuk Memperoleh Gelar Magister

Pada Program Magister, Program Studi Teknik Sipil

Program Pascasarjana Universitas Udayana

I MADE PANDU WEDA WIGUNA

1491561022

PROGRAM MAGISTER

PROGRAM STUDI TEKNIK SIPIL

PROGRAM PASCASARJANA

UNIVERSITAS UDAYANA

DENPASAR

2016

Page 4: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

Lembar Pengesahan

TESIS INI TELAH DISETUJUI

TANGGAL 13 Juli 2016

Pembimbing I,

Dr. Ir. I Gusti Agung Adnyana Putera, DEA

NIP. 19611207 198903 1 003

Pembimbing II,

GAP. Candra Dharmayanti, ST, MSc, Ph.D

NIP. 19730715 200112 2 001

Mengetahui

Ketua Program Magister Teknik Sipil

Program Pascasarjana

Universitas Udayana,

Putu Alit Suthanaya, ST, MEngSc, Ph.D

NIP. 19690805 199503 1 001

Direktur

Program Pascasarjana

Universitas Udayana,

Prof. Dr. dr. A. A. Raka Sudewi, Sp. S(K)

NIP. 19590215 198510 2 001

Page 5: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

Lembar Penetapan Panitia Penguji Tesis

Tesis ini telah diuji pada

Tanggal 13 Juli 2016

Panitia Penguji Tesis Berdasarkan Surat Keputusan Rektor Universitas Udayana,

No. 169/UN.14.4/TU/TS/2016

Ketua : Dr. Ir. I Gusti Agung Adnyana Putera, DEA

Anggota :

1. GAP. Candra Dharmayanti, ST, MSc, Ph.D

2. A.A. Diah Parami Dewi, ST, MT, Ph.D

3. Dr. Ida Bagus Putu Adnyana, ST, MT

4. Kadek Diana Harmayanti, ST, MT, PhD

Page 6: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

SURAT PERNYATAAN BEBAS PLAGIAT

Nama : I Made Pandu Weda Wiguna

Nim : 1491561022

Program Studi : Pascasarjana Teknik Sipil Universitas Udayana

Judul Tesis : Penerapan Rekayasa Nila Pada Proyek

Pembangunan Amartha Residence

Dengan ini menyatakan bahwa karya ilmiah Tesis ini bebas plagiat. Apabila di

kemudia hari terbukti terdapat plagiat dalam karya ilmiah ini, maka saya bersedia

menerima sanksi sesuai peraturan Mendiknas RI No. 17 tahun 2010 dan

Peraturan Perundang-undangan yang berlaku.

Denpasar, 13 Juli 2016

I Made Pandu Weda Wiguna

Page 7: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

UCAPAN TERIMA KASIH

Puji dan syukur dipanjatkan kehadapan Ida Sang Hyang Widhi Wasa /

Tuhan Yang Maha Esa, karena berkat rahmat-Nya penelitian tesis dengan judul “

Penerapan Rekayasa Nilai pada Proyek Pembangunan Amartha Residence” ini

dapat diselesaikan sebagai pemenuhan syarat penyelesaian Pendidikan Magister

Pascasarjana Teknik Sipil Universitas Udayana.

Pada kesempatan ini penulis ingin mengucapkan terima kasih kepada

Rektor Universitas Udayana Bapak Prof. Dr. dr. Ketut Suastika, SpPD-KEMD

dan Direktur Program Pascasarjana Universitas Udayana Ibu Prof. Dr. dr. A.A.

Raka Sudewi, Sp.S(K) atas fasilitas yang telah diberikan kepada penulis selama

menyelesaikan pendidikan. Ucapan terima kasih yang sebesar-besarnya juga

ditujukan kepada Ketua Program Studi Teknik Sipil Program Pascasarjana

Universitas Udayana, serta selaku dosen pembimbing I Bapak Dr. Ir. I Gusti

Agung Adnyana Putera, DEA yang telah memberikan semangat dan bimbingan

selama masa perkuliahan sampai dengan penyusunan tesis ini. Ucapan terima

kasih yang sebesar-besarnya juga penulis sampaikan kepada Ibu GAP. Candra

Dharmayanti, ST, MSc, Ph.D selaku dosen pembimbing II yang telah

membimbing dan memberikan saran kepada penulis. Ucapan terima kasih juga

penulis sampaikan kepada para penguji Ibu A. A. Diah Parami Dewi, ST, MT,

Ph.D, Bapak Dr. Ida Bagus Putu Adnyana, ST, MT dan Ibu Kadek Diana

Harmayanti, ST, MT, PhD yang telah memberikan banyak masukan dan koreksi

sehingga penulis dapat menyelesaikan tesis ini.

Tidak lupa penulis mengucapkan terima kasih yang tulus kepada

keluarga, Ayah, Ibu dan Kakak yang selalu menyemangati hingga akhir. Akhir

kata tesis ini diharapkan bermanfaat dan semoga Tuhan Yang Maha Esa

senantiasa melimpahkan rahmatnya kepada semua pihak yang telah membantu

dalam menyelesaikan tesis ini.

Denpasar, Juli 2016

Penulis

Page 8: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

ABSTRAK

PENERAPAN REKAYASA NILAI PADA PROYEK PEMBANGUNAN

AMARTHA RESIDENCE

Anggaran biaya sering menjadi kendala dalam mempersiapkan

pembangunan suatu proyek, oleh karena itu perlu adanya analisis biaya

pekerjaan, baik dalam biaya perencanaan konstruksi maupun biaya pelaksanaan,

dengan tujuan mendapat biaya konstruksi yang hemat dan efisien. Salah satu

teknik yang digunakan untuk mengefisienkan biaya adalah dengan menggunakan

metode rekayasa nilai. Rekayasa nilai adalah metode efisiensi biaya digunakan

untuk mengurangi biaya perencanaan awal maupun pelaksanaan tanpa mengubah

fungsi dan kualitas bangunan itu sendiri. Tujuan penelitian ini adalah untuk

mendapat penghematan dan efisiensi biaya dari pekerjaan rencana awal .

Metode yang digunakan adalah analisis rekayasa nilai terhadap biaya

pekerjaan berbiaya tinggi berdasarkan diagram pareto. Metode ini mempunyai

enam tahapan kerja, yaitu tahap informasi, tahap analisis fungsi, tahap kreativitas,

tahap evaluasi, tahap pengembangan, dan tahap penyajian.

Dari hasil analisis didapatkan penghematan menggunakan struktur lantai

pelat bondek sebesar 12%, dari rencana awal menggunakan pelat beton

konvensional. Pekerjaan dinding menggunakan batako menghemat 7 %, dari

rencana awal menggunakan batu bata. Redesain pekerjaan MEP (mekanikal

elektrikal plumbing ) mendapat penghematan sebesar 15 % dari rencana awal.

Kusen jendela menggunakan UPVC mendapat penghematan sebesar 13%, dari

rencana awal menggunakan kayu jati. Penghematan biaya total untuk 20 unit

bangunan adalah Rp.1.250.000.000,- dari Rp. 17.486.000.000,- atau 7% dari

biaya rencana awal.

Kata kunci : value engineering, rekayasa nilai, efisiensi biaya, perencanaan,

metode pelaksanaan

Page 9: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

ABSTRACT

APPLICATION OF VALUE ENGINEERING IN AMARTHA

RESIDENCE DEVELOPMENT PROJECT

Budget cost is often an obstacle in preparing the construction of a project,

hence the need for analysis of the cost of the work, both in the cost of

construction planning and costs of implementation, with the purpose of obtaining

a cost-effective and efficient construction. One technique used to streamline costs

was to use value engineering methods. Value engineering is a cost efficiency

method used to reduce the cost efficiency of the initial planning and

implementation costs without changing the functionality and quality of the

building itself. The aim of this research was to gain savings and cost efficiency of

the initial work plans.

The method used was a value engineering analysis of the cost of high-cost

work based on the Pareto diagram. This method has six phases of work, namely

information phase, function analysis phase, creative phase, evaluation phase,

development phase, and recomendation phase.

From the analysis, the savings was obtained using bondek plate floor

structure by 12%, from the initial plan using conventional concrete slab. Wall

works used batako bricks saving 7%, from the initial plan using plain bricks.

Redesign MEP (mechanical electrical plumbing) work got a savings of 15% from

the initial plan. Window frame using UPVC received a savings of 13%, from the

initial plan using teak. Total cost savings for the 20 unit building was

Rp.1.250.000.000, - from Rp. 17.486.000.000, - or 7% of the cost of the initial

plan.

Keywords: value engineering, cost efficiency, planning, implementation methods

Page 10: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

DAFTAR ISI

Halaman

SAMPUL DALAM .............................................................................................. i

PERSYARATAN GELAR ................................................................................... ii

LEMBAR PENGESAHAN ................................................................................ iii

LEMBAR PENETAPAN PANITIA PENGUJI ................................................. iv

SURAT PERNYATAAN BEBAS PLAGIAT ..................................................... v

UCAPAN TERIMA KASIH ................................................................................ vi

ABSTRAK ............................................................................................................ vii

ABSTRACT ........................................................................................................ viii

DAFTAR ISI ......................................................................................................... ix

DAFTAR GAMBAR .......................................................................................... xii

DAFTAR TABEL .............................................................................................. xiii

DAFTAR SINGKATAN .................................................................................. xiv

DAFTAR LAMPIRAN ...................................................................................... xv

BAB I PENDAHULUAN ................................................................................... 1

1.1 Latar Belakang ................................................................................. 1

1.2 Rumusan Masalah ........................................................................... 3

1.3 Tujuan Penelitian ............................................................................ 3

1.4 Manfaat Penelitian ........................................................................... 3

1.5 Batasan Penelitian ........................................................................... 4

BAB II TINJAUAN PUSTAKA ......................................................................... 5

2.1 Manajemen Proyek .......................................................................... 5

2.1.2 Rekayasa Nilai (Value Engineering) ..................................... 5

2.2 Konsep Value Engineering ............................................................. .7

2.2.1 Penjelasan Umum .................................................................. 7

2.2.2 Waktu Mengaplikasikan VE (Value Engineering) ................ 9

2.3 Metode Penerapan VE (Value Engineering) ................................ 10

2.3.1 Tahap Informasi (Information Phase) ................................. 10

Page 11: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

2.3.2 Tahap Analisis Fungsi (Function Analisis Phase) .............. 11

2.3.3 Tahap Kreatif ( Creative Phase) ......................................... 11

2.3.4 Tahap Evaluasi (Evaluation Phase) .................................... 13

2.3.5 Tahap Pengembangan (Development Phase) ...................... 15

2.3.6 Tahap Penyajian (Recomendation Phase) .......................... 15

2.4 Diagram Pareto .............................................................................. 16

2.5 F.A.S.T Diagram ........................................................................... 17

2.6 Biaya Siklus Hidup atau Life Cycle Cost ( LCC ) ......................... 18

BAB III METODE PENELITIAN .................................................................. 21

3.1 Rancangan Penelitian .................................................................... 21

3.2 Lokasi Penelitian ........................................................................... 24

3.3 Jenis Data ....................................................................................... 24

3.4 Rencana Kerja ( Job Plan VE ) ..................................................... 25

3.4.1 Tahap Informasi (Information phase) ................................. 25

3.4.2 Tahap Analisis Fungsi (Function Analisis Phase) .............. 26

3.4.3 Tahap Kreatif ( Creative Phase) ......................................... 28

3.4.4 Tahap Evaluasi (Evaluation Phase) .................................... 28

3.4.5 Tahap Pengembangan (Development Phase) ...................... 30

3.4.6 Tahap Penyajian (Recomendation Phase) ........................... 31

BAB IV HASIL DAN PEMBAHASAN ............................................................. 32

4.1 Tahap Informasi (Information Phase) .......................................... 32

4.1.1 Data umum proyek penelitian ............................................. 32

4.1.2 Analisis Pareto .................................................................... 32

4.1.3 Rincian Pekerjaan Struktur ................................................. 34

4.2 Tahap Analisis Fungsi (Function Analysis Phase) ....................... 36

4.2.1 Analisis Fungsi Pekerjaan Struktur ................................... 36

4.2.2 Analisis Fungsi Pekerjaan Dinding .................................. 37

4.2.3 Analisis Fungsi Pekerjaan MEP ....................................... 37

4.2.4 Analisis Fungsi Pekerjaan Kusen Pintu dan Jendela ........ 38

4.2.5 Analisis Fungsi Pekerjaan Plafond ................................... 39

4.3 Tahap Kreativitas ( Creative phase ) ............................................ 40

Page 12: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

4.3.1 Analisis Pekerjaan Struktur ................................................. 40

4.3.2 Analisis Pekerjaan Dinding ................................................. 50

4.3.3 Analisis Pekerjaan MEP ...................................................... 55

4.3.4 Analisis Pekerjaan Kusen Pintu dan Jendela ...................... 61

4.3.5 Analisis Pekerjaan Plafond ................................................. 65

4.4 Tahap Evaluasi (Evaluation Phase) .............................................. 68

4.4.1 Evaluasi Pekerjaan Struktur ................................................ 68

4.4.1.1 Evaluasi Perencanaan Pekerjaan Struktur ............... 67

4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ............... 67

4.4.2 Evaluasi Pekerjaan Dinding ................................................ 77

4.4.3 Evaluasi Pekerjaan MEP .................................................... 78

4.4.4 Evaluasi Pekerjaan Kusen Pintu Jendela ............................ 79

4.4.5 Evaluasi Pekerjaan Plafond ................................................ 80

4.5 Tahap Pengembangan (Development Phase) ............................... 81

4.5.1 Analisis Life Cycle Cost ( LCC ) ......................................... 81

4.6 Tahap Penyajian ( Recomendation Phase ) .................................. 87

BAB V SIMPULAN DAN SARAN ...................................................................... 90

5.1 Simpulan ........................................................................................ 90

5.2 Saran .............................................................................................. 91

DAFTAR PUSTAKA .......................................................................................... 93

LAMPIRAN : Lembaran Kerja Studi VE (Value Engineering) ......................... 95

Page 13: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

DAFTAR GAMBAR

Halaman

3.1 Bagan alir konsep penelitian ........................................................................... 22

3.2 Denah lokasi penelitian ................................................................................... 24

3.3 Contoh F.A.S.T Diagram pekerjaan Struktur Bekisting .................................. 28

4.1 Grafik Pareto untuk Keseluruhan Item Pekerjaan .......................................... 34

4.2 F.A.S.T diagram pekerjaan pelaksanaan struktur bekisting ............................ 36

4.3 F.A.S.T diagram pekerjaan dinding ................................................................ 37

4.4 F.A.S.T diagram pekerjaan MEP .................................................................... 38

4.5 F.A.S.T diagram pekerjaan pintu ................................................................... 38

4.6 F.A.S.T diagram pekerjaan jendela ................................................................. 39

4.7 F.A.S.T diagram pekerjaan plafond ................................................................ 40

4.8 Pelaksanaan bekisting konvensional ............................................................... 41

4.9 Bekisting konvensional model panel ............................................................... 44

4.10 Ide alternatif pekerjaan atap boundeck .......................................................... 46

4.11 Kombinasi pemilihan ide alternatif ............................................................... 72

Page 14: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

DAFTAR TABEL

Halaman

4.1 RAB Type Soho Verde ............................................................................................... 33

4.2 Persentase biaya tertinggi hingga terendah ................................................................. 33

4.3 Rincian Pekerjaan Struktur .......................................................................................... 35

4.4 Jenis pekerjaan struktur ............................................................................................... 35

4.5 Perhitungan biaya total pekerjaan balok dan pelat konvensional ................................ 42

4.6 Siklus pemakaian bekisting balok dan pelat konvensional ......................................... 42

4.7 Biaya total pekerjaan balok dan pelat konvensional ............................................ 43

4.8 Perhitungan biaya total pekerjaan balok dan pelat panel konvensional ...................... 44

4.9 Siklus pemakian bekisting balok dan pelat konvensional model panel ....................... 45

4.10 Perhitungan biaya total pekerjaan balok dan pelat konvensional model panel ......... 46

4.11 Perhitungan biaya total pekerjaan balok dan pelat bondek ....................................... 48

4.12 Siklus pemakaian bekisting balok secara berulang dan pelat bondek ....................... 49

4.13 Perhitungan biaya total pekerjaan balok konvensional dan pelat lantai bondek ....... 50

4.14 Kebutuhan bahan dinding bata merah ....................................................................... 51

4.15 Kebutuhan bahan dinding batako .............................................................................. 52

4.16 Kebutuhan bahan dinding hebel ................................................................................ 54

4.17 Rencana Awal Kebutuhan Daya Listrik .................................................................... 55

4.18 Rekapitulasi biaya pekerjaan MEP rencana awal ...................................................... 56

4.19 Ukuran lampu LED berdasarkan lumens .................................................................. 56

4.20 Ukuran lumen level standar ...................................................................................... 57

4.21 Perhitungan jumlah lampu......................................................................................... 58

4.22 Kebutuhan Kapasitas AC .......................................................................................... 59

4.23 Total kebutuhan daya listrik ...................................................................................... 60

4.24 Rekapitulasi biaya total redesain pekerjaan MEP ..................................................... 60

4.25 Kebutuhan material dan bahan pekerjaan kusen pintu jendela.................................. 61

4.26 Kombinasi antara pintu kusen jati dan jendela aluminium........................................ 63

4.27 Kombinasi antara pintu kusen jati dan jendela UPVC .............................................. 64

4.28 Biaya pekerjaan plafond kalsiboard .......................................................................... 65

4.29 Biaya pekerjaan plafond gypsum .............................................................................. 66

4.30 Biaya pekerjaan plafond GRC ................................................................................... 68

4.31 Perbandingan perencanaan awal dan alternatif pekerjaan balok dan pelat ............... 69

Page 15: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

4.32 Kombinasi pemilihan ide alternatif ........................................................................... 71

4.33 Perbandingan penggunaan bekisting balok dan pelat konvensional ......................... 73

4.34 Perbandingan penggunaan scaffolding dan waktu pengerjaan .................................. 73

4.35 Perbandingan keuntungan dan kerugian ide alternatif pekerjaan bekisting .............. 76

4.36 Perbandingan biaya pasangan dinding rencana dan alternatif ................................... 77

4.37 Perbandingan keuntungan dan kerugian ide alternatif pekerjaan dinding ................. 78

4.38 Perbandingan redesain pekerjaan MEP ..................................................................... 78

4.39 Perbandingan biaya pekerjaan kusen pintu dan jendela ........................................... 79

4.40 Perbandingan keuntungan dan kerugian pekerjaan kusen pintu jendela ................... 80

4.41 Perbandingan biaya alternatif pekerjaan atap plafond ............................................... 80

4.42 LCC perbandingan pekerjaan dinding ....................................................................... 82

4.43 LCC perbandingan pekerjaan kusen pintu dan jendela ............................................. 84

4.44 Perbandingan biaya sebelum dan sesudah VE .......................................................... 86

4.45 Alasan pemilihan ide alternatif .................................................................................. 88

Page 16: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

DAFTAR SINGKATAN

SINGKATAN

VE : Value Engineering

RAB : Rencana Anggaran Biaya

LCC : Life Cycle Cost

GRC : Glassfibre Reinforced Concrete

F.A.S.T : Functional Analysis System Technique

MEP : Mekanikal Electrical Plumbing

PV : Present Value

UPVC : Unplasticised Polivinyl Chloride

Page 17: PENERAPAN REKAYASA NILAI PADA PROYEK · PDF filemetode pelaksanaan . ... 4.4.1.2 Evaluasi Pelaksanaan Pekerjaan Struktur ... 4.11 Perhitungan biaya total pekerjaan balok dan pelat

DAFTAR LAMPIRAN

Lampiran 1 : Gambar 3D Type soho verde

Lampiran 2 : Layout plan type soho verde

Lampiran 3 : Layout Plan existing dan foto proyek Amartha Residence

Lampiran 4 : Perbandingan Siklus pemakaian Bekisting

Lampiran 5 : Schedule pekerjaan balok dan pelat konvensional

Lampiran 6 : Schedule pekerjaan balok dan pelat panel konvensional

Lampiran 7 : Schedule pekerjaan balok dan pelat boundeck

Lampiran 8 : Perhitungan LCC

Lampiran 9 : RAB pekerjaan MEP awal

Lampiran 10 : RAB redesain pekerjaan MEP awal

Lampiran 11 : Perbandingan RAB awal dan setelah VE

Lampiran 12 : Kombinasi biaya desain alternatif pekerjaan VE