    KOP PERUS H N

    REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)

    KEGIATAN : REHABILITASI GEDUNG KUA KECAMATAN SIWALAN KABUPATEN PEKALONGAN

    PEKERJAAN : REHABILITASI GEDUNG KUA KECAMATAN SIWALAN KABUPATEN PEKALONGAN

    LOKASI : KECAMATAN SIWALAN KABUPATEN PEKALONGAN

    TAHUN ANGGARAN : 2015

    NO.

    I . PEKERJAAN TANAH

    II. PEKERJAAN PASANGAN DAN PLESTERAN

    III. PEKERJAAN BETON

    IV. PEKERJAAN KERAMIK LANTAI DAN DINDING

    V. PEKERJAAN KUSEN, PINTU DAN JENDELA

    VI. PEKERJAAN ATAP

    VII. PEKERJAAN SANITASI

    VIII. PEKERJAAN INSTALASI LISTRIK

    JUMLAH BIAYA KONSTRUKSI

    PPN 10%

    JUMLAH BIAYA KONSTRUKSI + PPN

    JUMLAH BIAYA KESELURUHAN DIBULATKAN

    TERBILANG : ...................................................................

    .................., ...................... 20.....

    PENAWAR

    PT./CV. .................................

    ...................................

    Direktur

    JUMLAH BIAYA (Rp.)URAIAN PEKERJAAN

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    2/15

    KOP PERUS H N

    RENCANA ANGGARAN BIAYA (RAB)

    KEGIATAN : REHABILITASI GEDUNG KUA KECAMATAN SIWALAN KABUPATEN PEKALONGAN

    PEKERJAAN : REHABILITASI GEDUNG KUA KECAMATAN SIWALAN KABUPATEN PEKALONGANLOKASI : KECAMATAN SIWALAN KABUPATEN PEKALONGAN

    TAHUN ANGGARAN : 2015

    NO. VOLUME SAT ANALISAHARGA SATUAN

    (Rp.)

    JUMLAH BIAYA

    (Rp.)

    I. PEKERJAAN TANAH

    1 Pek. Galian tanah 27,91 m3 A.2.3.1.1-KBPKL

    2 Pek. Urugan tanah kembali 13,96 m3 A.2.3.1.9-KBPKL

    3 Pek. Urugan pasir bawah pondasi 4,65 m3 A.2.3.1.11-KBPKL

    4 Pek. Urugan pasir bawah lantai 11,90 m3 A.2.3.1.11-KBPKL

    5 Pek. Urugan tanah peninggian peil 161,84 m3 A.2.3.1.14-KBPKL

    Sub Total

    II. PEKERJAAN PASANGAN DAN PLESTERAN

    1 Pek. Aanstamping/Batu kosong 18,61 m3 A.3.2.1.9-KBPKL

    2 Pek. Pas. Batu kali 1 : 6 70,36 m3 A.3.2.1.4.a

    3 Pek. Pas. Batu bata 1 : 4 31,29 m2 A.4.4.1.9

    4 Pek. Pas. Batu bata 1 : 6 335,29 m2 A.4.4.1.11

    5 Pek. Plesteran 1 : 4 62,58 m2 A,4,4,2.4-KBPKL

    6 Pek. Plesteran 1 : 6 670,59 m2 A,4,4,2.6-KBPKL

    7 Pek. Acian 715,92 m2 A,4,4,2.27-KBPKL

    8 Pek. Sponengan 233,12 m' A,4,4,2.20-KBPKL

    Sub Total

    III. PEKERJAAN BETON

    1 Pek. Beton Sloof 12X18

    ~ Bekisting 41,87 m2 A.4.1.1.21.1-KBPKL

    ~ Besi Beton 502,59 kg A.4.1.1.17-KBPKL~ Beton (Mutu K-175) 2,51 m3 A.4.1.1.5

    2 Pek. Beton Kolom struktur 20X20

    ~ Bekis ting 14,40 m2 A.4.1.1.22.2.1-KBPKL

    ~ Besi Beton 99,44 kg A.4.1.1.17-KBPKL

    ~ Beton (Mutu K-175) 0,72 m3 A.4.1.1.7

    3 Pek. Beton Kolom praktis 12X12

    ~ Bekis ting 29,76 m2 A.4.1.1.22.2.1-KBPKL

    ~ Besi Beton 413,34 kg A.4.1.1.17-KBPKL

    ~ Beton (Mutu K-175) 1,79 m3 A.4.1.1.5

    4 Pek. Beton Balok Latei atas kusen 12X15

    ~ Bekis ting 27,11 m2 A.4.1.1.23.2.1-KBPKL

    ~ Besi Beton 220,97 kg A.4.1.1.17-KBPKL

    ~ Beton (Mutu K-175) 1,16 m3 A.4.1.1.5

    5 Pek. Beton Ring Balk 12X18

    ~ Bekisting 41,87 m2 A.4.1.1.21.1-KBPKL

    ~ Besi Beton 408,57 kg A.4.1.1.17-KBPKL

    ~ Beton (Mutu K-175) 2,51 m3 A.4.1.1.5

    6 Pek. Beton Balok Sunduk Kanopi 15X35

    ~ Bekisting 6 ,75 m2 A.4.1.1.23.2.1-KBPKL

    ~ Besi Beton 57,84 kg A.4.1.1.17-KBPKL

    ~ Beton (Mutu K-175) 0,41 m3 A.4.1.1.7

    7 Pek. Beton Lantai kerja bawah Lantai 5,38 m3 A.4.1.1.4

    Sub Total

    IV. PEKERJAAN KERAMIK LANTAI DAN DINDING

    1 Pek. Lantai keramik 40 x 40 176,57 m2 A.4.4.3.35.6-KBPKL

    2 Pek. Lantai keramik 20 x 20 3,67 m2 A.4.4.3.36.2-KBPKL

    3 Pek. Dinding keramik 20 x 25 17,25 m2 A.4.4.3.36.4-KBPKLSub Total

    URAIAN PEKERJAAN

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    3/15

    NO. VOLUME SAT ANALISAHARGA SATUAN

    (Rp.)

    JUMLAH BIAYA

    (Rp.)URAIAN PEKERJAAN

    V. PEKERJAAN KUSEN, PINTU DAN JENDELA

    1 Pek. Kusen Alumunium 4" silver 199,65 m' A.4.2.1.11.2-KBPKL

    2 Pek. Daun jendela Alumunium silver 89,60 m' A.4.2.1.11.2-KBPKL

    3 Pek. Kaca tebal 5 mm 33,32 m2 A.4.6.2.17

    4 Pek. Daun pintu double teakwood 80 x 210 c m 8,00 unit dihitung

    rk. Kayu kampas + finishing plitur + Acesories

    5 Pek. Daun pintu double teakwood 70 x 210 cm rk. Kayu kampas + 1,00 unit dihitung

    finishing plitur + Acesories + Lapis Alumunium foil

    6 Pek. Daun pintu alumunium kaca 1,00 unit dihitung

    (uk. 80 x 210 cm x 2 daun)

    7 Pek. Casement stay 30,00 set survey

    8 Pek. Ram buncis 30,00 bh survey

    Sub Total

    VI. PEKERJAAN ATAP

    1 Pek. Rangka atap baja ringan 310,74 m2 survey

    2 Pek. Genteng metal lapis pasir 319,41 m2 A.4.5.2.32-KBPKL

    3 Pek. Bubungan sejenis 60,11 m' A.4.5.2.36-KBPKL

    Sub Total

    VII. PEKERJAAN SANITASI

    1 Pek. Pipa PVC 1/2 " Instalasi Air Bersih 12,05 m2 A.5.1.1.25

    2 Pek. Pipa PVC 3" Instalasi Air Kotor + Ujan 6,00 m2 A.5.1.1.313 Pek. Pipa PVC 4" Instalasi Air Tinja 6,00 m2 A.5.1.1.32

    4 Pek. Kran 3,00 m2 A.5.1.1.19

    5 Pek. Closed Jongkok 1,00 m2 A.5.1.1.2-KBPKL

    6 Pek. Floor drain 2,00 bh A.5.1.1.14

    Sub Total

    VIII. PEKERJAAN INSTALASI LISTRIK

    1 Pek. Instalasi Listrik 30,00 Titik survey

    2 Pek. Stop Kontak 9,00 Bh survey

    3 Pek. Saklar Ganda 3,00 Bh survey

    4 Pek. Saklar Tunggal 7,00 Bh survey

    5 Pek. Lampu SL 18 Watt 21,00 Bh survey

    Sub Total

    JUMLAH BIAYA

    PPN 10%

    JUMLAH BIAYA + PPN

    JUMLAH BIAYA KESELURUHAN DIBULATKAN

    TERBILANG : ...................................................................

    .................., ...................... 20.....

    PENAWAR

    PT./CV. .................................

    ...................................

    Direktur

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    4/15

    KOP PERUS H N

    REKAPITULASI DAFTAR ANALISA PEKERJAAN

    HARGA

    NO. URAIAN PEKERJAAN SAT. KODE ANALISA SATUAN(Rp.)

    A. PEKERJAAN TANAH

    1 Galian Tanah m3 A.2.3.1.1-KBPKL

    2 Pengurugan Kembali m3 A.2.3.1.9-KBPKL

    3 Urugan Pasir m3 A.2.3.1.11-KBPKL

    4 Mengurug tanah baru padat m3 A.2.3.1.14-KBPKL

    B. PEKERJAAN PASANGAN DAN PLESTERAN

    1 Pemasang Batu Kosong/Anstamping m3 A.3.2.1.9-KBPKL

    2 Pemasangan Pondasi Batu 1SP : 6 PP (30 % Blondos : 70 % Belah) m3 A.3.2.1.4.a

    3 Pemasangan Dinding Bata Mera h Ukura n (5x 11x22)cm Tebal 1/2 Ba ta Camp. 1S P : 4 PP m2 A.4.4.1.9

    4 Pemasangan Dinding Bata Mera h Ukura n (5x 11x22)cm Tebal 1/2 Ba ta Camp. 1S P : 6PP m2 A.4.4.1.11

    5 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 A,4,4,2.4-KBPKL

    6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 A,4,4,2.6-KBPKL

    7 Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm m' A,4,4,2.20-KBPKL

    8 Pemasangan Acian m2 A,4,4,2.27-KBPKL

    C. PEKERJAAN BETON

    1 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 m3 A.4.1.1.4

    2 Membuat Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66 m3 A.4.1.1.5

    3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58 m3 A.4.1.1.7

    4 Pembesian dg Besi Polos atau Besi Ulir Kg A.4.1.1.17-KBPKL

    5 Memasang Bekisting untuk Sloof (2 kali pakai) m2 A.4.1.1.21.1-KBPKL

    6 Memasang Bekisting untuk Kolom (2 kali pakai) m2 A.4.1.1.22.2.1-KBPKL

    7 Memasang Bekisting untuk Balok (2 kali pakai) m2 A.4.1.1.23.2.1-KBPKL

    D. PEKERJAAN KERAMIK

    1 Pemasangan Lantai Keramik 40 x 40 cm Polos Sekualitas Mulia/Asiatile m2 A.4.4.3.35.6-KBPKL

    2 Pemasangan Lantai Keramik 20 x 20 cm motif m2 A.4.4.3.36.2-KBPKL

    3 Pemasangan Lantai Keramik 20 x 25 cm motif m2 A.4.4.3.36.4-KBPKL

    E. PEKERJAAN ATAP

    1 Pemasangan Atap Genteng Metal butir pasir m2 A.4.5.2.32-KBPKL

    2 Pemasangan Nok Genteng Metal butir pasir m' A.4.5.2.36-KBPKL

    F. PEKERJAAN KUNCI DAN KAC A

    1 Pemasangan Kaca tebal 5 mm m2 A.4.6.2.17

    2 Pemasangan Kusen Pintu/jendela Allumunium warna m' A.4.2.1.11.2-KBPKL

    G. PEKERJAAN SANITASI1 Pemasangan Pipa PVC tipe AW " m' A.5.1.1.25

    2 Pemasangan Pipa PVC tipe AW 3" m' A.5.1.1.31

    3 Pemasangan Pipa PVC tipe AW 4" m' A.5.1.1.32

    4 Pemasangan Kran " atau " bh A.5.1.1.19

    5 Pemasangan Floor Drain buah A.5.1.1.14

    6 Memasang Closet Jongkok Porselen Unit A.5.1.1.2-KBPKL

    .................., ...................... 20.....

    PENAWAR

    PT./CV. .................................

    ...................................

    Direktur

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    5/15

    KOP PERUS H N

    DAFTAR ANALISA PEKERJAAN

    HARGA JUMLAH

    No. SNI KODE KOEF SAT. URAIAN PEKERJAAN SATUAN BIAYA

    (Rp.) (Rp.)

    1 A.2.3.1.1-KBPKL 1 m3 Menggali Tanah Biasa Sedalam 1 m

    A. Tenaga

    L.01 0,670 OH Pekerja

    L.04 0,020 OH Mandor

    B. Jumlah A

    C. Overhead & Profit 13%

    D. Harga Satuan Pekerjaan (C+D)

    2 A.2.3.1.9-KBPKL 1 m3 Pengurugan Kembali

    Pengurugan Kembali di hitung dari 1/3 kali koefisien Pekerjaan galian

    A. Tenaga

    L.01 0,223 OH Pekerja

    L.04 0,007 OH Mandor

    B. Jumlah A

    C. Overhead & Profit 13%

    D. Harga Satuan Pekerjaan (C+D)

    3 A.2.3.1.11-KBPKL 1 m3 Urugan Pasir

    A. Tenaga

    L.01 0,250 OH Pekerja

    L.04 0,013 OH Mandor

    B. Bahan

    1,050 m3 Pasir Urug

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    4 A.2.3.1.14-KBPKL 1 m3 Mengurug tanah baru padat

    A TENAGA

    L.01 0,250 OH Pekerja

    L.04 0,025 OH Mandor

    B. Bahan

    1,200 m3 Tanah urug baru

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    5 A.3.2.1.9-KBPKL 1 m3 Pemasang Batu Kosong/Anstamping

    A Tenaga

    L.01 0,780 OH Pekerja

    L.02 0,390 OH Tukang Batu

    L.03 0,039 OH Kepala Tukang

    L.04 0,039 OH Mandor

    B. Bahan

    1,200 m3 Batu Blonos

    0,432 m3 Pasir Urug

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    6/15

    HARGA JUMLAH

    No. SNI KODE KOEF SAT. URAIAN PEKERJAAN SATUAN BIAYA

    (Rp.) (Rp.)

    6 A.3.2.1.4.a 1 m3 Pemasangan Pondasi Batu 1SP : 6 PP (30 % Blondos : 70 % Belah)

    A TENAGA

    L.01 1,500 OH Pekerja

    L.02 0,750 OH Tukang Batu

    L.03 0,075 OH Kepala Tukang

    L.04 0,075 OH Mandor

    B. Bahan

    0,840 m3 Batu Belah 15/20

    0,360 m3 Batu bulat

    117,000 Kg Portland Sement

    0,561 m3 Pasir Pasang

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    7 A.4.4.1.9 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP

    A Tenaga

    L.01 0,300 OH Pekerja

    L.02 0,100 OH Tukang Batu

    L.03 0,010 OH Kepala Tukang

    L.04 0,015 OH Mandor

    B. Bahan

    70,000 Buah Bata Merah 5 x 11 x 22

    11,500 Kg Portland Semen

    0,043 m3 Pasir Pasang

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    8 A.4.4.1.11 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PPA Tenaga

    L.01 0,300 OH Pekerja

    L.02 0,100 OH Tukang Batu

    L.03 0,010 OH Kepala Tukang

    L.04 0,015 OH Mandor

    B. Bahan

    70,000 Buah Bata Merah 5 x 11 x 22

    8,320 Kg Portland Semen

    0,049 m3 Pasir Pasang

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    9 A,4,4,2.4-KBPKL 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm

    A Tenaga

    L.01 0,200 OH Pekerja

    L.02 0,150 OH Tukang batu

    L.03 0,015 OH Kepala Tukang

    L.04 0,010 OH Mandor

    B. Bahan

    6,240 Kg Portland Semen

    0,024 m3 Pasir Pasang

    C. Jumlah A+BD. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    7/15

    HARGA JUMLAH

    No. SNI KODE KOEF SAT. URAIAN PEKERJAAN SATUAN BIAYA

    (Rp.) (Rp.)

    10 A,4,4,2.6-KBPKL 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm

    Tenaga

    L.01 0,200 OH Pekerja

    L.02 0,150 OH Tukang batu

    L.03 0,015 OH Kepala Tukang

    L.04 0,010 OH Mandor

    B. Bahan

    4,416 Kg Portland Semen

    0,027 m3 Pasir Pasang

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    11 A,4,4,2.20-KBPKL 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm

    A Tenaga

    L.01 0,080 OH Pekerja

    L.02 0,140 OH Tukang batu

    L.03 0,040 OH Kepala Tukang

    L.04 0,004 OH Mandor

    B. Bahan

    0,500 Kg Portland Semen

    0,013 m3 Pasir Pasang

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    12 A,4,4,2.27-KBPKL 1 m2 Pemasangan Acian

    Tenaga

    L.01 0,140 OH Pekerja

    L.02 0,100 OH Tukang batuL.03 0,010 OH Kepala Tukang

    L.04 0,008 OH Mandor

    B. Bahan

    3,250 Kg Portland Semen

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    13 A.4.1.1.4 1 m3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87

    A. Tenaga

    L.01 1,200 OH Pekerja

    L.02 0,200 OH Tukang Batu

    L.03 0,020 OH Kepala Tukang

    L.04 0,006 OH Mandor

    B. Bahan

    230,000 Kg Portland Semen

    893,000 kg Pasir Beton

    1.027,000 kg Kerikil (maksimu m 30 mm)

    200,000 ltr Air

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    * (Conversi Harga) Harga pasir beton 1 kg = Harga Pasir beton 1 m3 dibagi 1400(Conversi Harga) Harga Kerikil 1 kg = Harga Kerikil 1 m3 dibagi 1350

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    8/15

    HARGA JUMLAH

    No. SNI KODE KOEF SAT. URAIAN PEKERJAAN SATUAN BIAYA

    (Rp.) (Rp.)

    14 A.4.1.1.5 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (122)cm, w/c = 0,66

    A. Tenaga

    L.01 1,650 OH Pekerja

    L.02 0,275 OH Tukang Batu

    L.03 0,028 OH Kepala Tukang

    L.04 0,083 OH Mandor

    B. Bahan

    326,000 Kg Portland Semen

    760,000 Kg Pasir Beton

    1.029,000 Kg Kerikil (maksimu m 30 mm)

    215,000 ltr Air

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    15 A.4.1.1.7 1 m3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (122)cm, w/c = 0,58

    A Tenaga

    L.01 1,650 OH Pekerja

    L.02 0,275 OH Tukang Batu

    L.03 0,028 OH Kepala Tukang

    L.04 0,083 OH Mandor

    B. Bahan

    371,000 Kg Portland Semen

    698,000 Kg Pasir Beton

    1.047,000 Kg Kerikil (maksimu m 30 mm)

    215,000 ltr Air

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    16 A.4.1.1.17-KBPKL Kg Pembesian dg Besi Polos atau Besi Ulir

    A. Tenaga

    L.01 0,007 OH Pekerja

    L.02 0,007 OH Tukang Besi

    L.03 0,001 OH Kepala Tukang

    L.04 0,000 OH Mandor

    B. Bahan

    1,050 Kg Bes i Beton (polos/ul ir )

    0,015 Kg Kawat Beton

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    17 A.4.1.1.21.1-KBPKL 1 m2 Memasang Bekisting untuk Sloof (2 kali pakai)

    A Tenaga

    L.01 0,171 OH Pekerja

    L.02 0,240 OH Tukang Kayu

    L.03 0,024 OH Kepala Tukang

    L.04 0,024 OH Mandor

    B. Bahan

    0,013 m3 Kay u Klas I II (Terentang)

    0,300 Kg Paku Biasa 2" - 5"

    0 ,050 Ltr Minyak Bekis ting

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    9/15

    HARGA JUMLAH

    No. SNI KODE KOEF SAT. URAIAN PEKERJAAN SATUAN BIAYA

    (Rp.) (Rp.)

    18 A.4.1.1.22.2.1-KBPKL m2 Memasang Bekisting untuk Kolom (2 kali pakai)

    A. Tenaga

    L.01 0,240 OH Pekerja

    L.02 0,300 OH Tukang Kayu

    L.03 0,030 OH Kepala Tukang

    L.04 0,030 OH Mandor

    B. Bahan

    0,014 m3 Kay u Klas I II (Terentang)

    0,400 Kg Paku Biasa 2" - 5"

    0, 100 Ltr Minyak Bekis ting

    0,500 Btg Bambu

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    19 A.4.1.1.23.2.1-KBPKL 1 m2 Memasang Bekisting untuk Balok (2 kali pakai)

    A Tenaga

    L.01 0,240 OH Pekerja

    L.02 0,300 OH Tukang Kayu

    L.03 0,030 OH Kepala Tukang

    L.04 0,030 OH Mandor

    B. Bahan

    0,010 m3 Kay u Klas I II (Terentang)

    0,400 Kg Paku Biasa 2" - 5"

    0, 100 Ltr Minyak Bekis ting

    1,000 Btg bambu

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    20 A.4.4.3.35.6-KBPKL 1 m2 Pemasangan Lantai Keramik 40 x 40 cm Polos Sekualitas Mulia/Asiatile

    A Tenaga

    L.01 0,250 OH Pekerja

    L.02 0,170 OH Tukang Batu

    L.03 0,017 OH Kepala Tukang

    L.04 0,017 OH Mandor

    B. Bahan

    6,250 Buah Ubin Keramik 40 x 40 cm Sekualitas Mulia/Asiatile

    6,912 Kg Portland Semen

    0,035 m3 Pasir Pasang

    0,691 Kg Semen Warna

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    10/15

    HARGA JUMLAH

    No. SNI KODE KOEF SAT. URAIAN PEKERJAAN SATUAN BIAYA

    (Rp.) (Rp.)

    21 A.4.4.3.36.2-KBPKL 1 m2 Pemasangan Lantai Keramik 20 x 20 cm motif

    A Tenaga

    L.01 0,250 OH Pekerja

    L.02 0,170 OH Tukang Batu

    L.03 0,017 OH Kepala Tukang

    L.04 0,017 OH Mandor

    B. Bahan

    26,500 Buah Ubin Keramik 20 x 20 cm

    6,912 Kg Portland Semen

    0,691 Kg Semen Warna

    0,035 m3 Pasir Pasang

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    22 A.4.4.3.54-KBPKL 1 m2 Pemasangan Dinding Keramik 20x25 cm,

    A Tenaga

    L.01 0,250 OH Pekerja

    L.02 0,170 OH Tukang Batu

    L.03 0,017 OH Kepala Tukang

    L.04 0,017 OH Mandor

    B. Bahan

    26,50 0 Buah K eramik

    6,912 Kg Portland Semen

    0,018 m3 Pasir Pasang

    0,691 Kg Semen Warna

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    23 A.4.5.2.32-KBPKL 1 m2 Pemasangan Atap Genteng Metal butir pasir

    A Tenaga

    L.01 0,067 OH Pekerja

    L.02 0,083 OH Tukang Kayu

    L.03 0,007 OH Kepala Tukang

    L.04 0,001 OH Mandor

    B. Bahan

    1,020 m2 Genteng M etal bu tir pasir

    0,200 Kg Paku Biasa " - 1"

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    24 A.4.5.2.36-KBPKL 1 m' Pemasangan Nok Genteng Metal butir pasir

    A Tenaga

    L.01 0,067 OH Pekerja

    L.02 0,083 OH Tukang Kayu

    L.03 0,007 OH Kepala Tukang

    L.04 0,001 OH Mandor

    B. Bahan

    1,100 Buah Nok Genteng Metal butir pasir

    0,050 Kg Paku Biasa " - 1"

    C. Jumlah A+BD. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    11/15

    HARGA JUMLAH

    No. SNI KODE KOEF SAT. URAIAN PEKERJAAN SATUAN BIAYA

    (Rp.) (Rp.)

    25 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm

    A Tenaga

    L.01 0,015 OH Pekerja

    L.02 0,150 OH Tukang Kayu

    L.03 0,015 OH Kepala Tukang

    L.04 0,001 OH Mandor

    B. Bahan

    1,100 m2 Kaca tebal 5mm

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    26 A.4.2.1.11.2-KBPKL 1 m' Pemasangan Kusen Pintu/jendela Allumunium warna

    A Tenaga

    L.01 0,043 OH Pekerja

    L.02 0,043 OH Tukang Besi

    L.03 0,004 OH Kepala Tukang

    L.04 0,002 OH Mandor

    B. Bahan

    1,100 m' P rofil All umuni um war na

    2,0 00 b uah Skrup Fi xer

    0,060 Tube Sealant

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    27 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW "

    A Tenaga

    L.01 0,036 OH Pekerja

    L.02 0,060 OH Tukang BatuL.03 0,006 OH Kepala Tukang

    L.04 0,002 OH Mandor

    B. Bahan

    1,200 m' Pipa PVC "

    0, 350 Ls P er lengkapan 35% x pipa

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    28 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW 3"

    A Tenaga

    L.01 0,081 OH Pekerja

    L.02 0,135 OH Tukang Batu

    L.03 0,014 OH Kepala Tukang

    L.04 0,004 OH Mandor

    B. Bahan

    1,200 m' Pipa PVC 3"

    0, 350 Ls P er lengkapan 35% x pipa

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    12/15

    HARGA JUMLAH

    No. SNI KODE KOEF SAT. URAIAN PEKERJAAN SATUAN BIAYA

    (Rp.) (Rp.)

    29 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW 4"

    A Tenaga

    L.01 0,036 OH Pekerja

    L.02 0,060 OH Tukang Batu

    L.03 0,006 OH Kepala Tukang

    L.04 0,002 OH Mandor

    B. Bahan

    1,200 m' Pipa PVC 4"

    0, 350 Ls P er lengkapan 35% x pipa

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    30 A.5.1.1.19 1 bh Pemasangan Kran " atau "

    A Tenaga

    L.01 0,010 OH Pekerja

    L.02 0,400 OH Tukang Batu

    L.03 0,040 OH Kepala Tukang

    L.04 0,005 OH Mandor

    B. Bahan

    1,000 bh Kran Air

    0,003 bh Sealtape

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    31 A.5.1.1.14 1 buah Pemasangan Floor Drain

    A Tenaga

    L.01 0,010 OH Pekerja

    L.02 0,100 OH Tukang BatuL.03 0,010 OH Kepala Tukang

    L.04 0,005 OH Mandor

    B. Bahan

    1,000 bh Floor Drain

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    13/15

    HARGA JUMLAH

    No. SNI KODE KOEF SAT. URAIAN PEKERJAAN SATUAN BIAYA

    (Rp.) (Rp.)

    32 A.5.1.1.2-KBPKL 1 Unit Memasang Closet Jongkok Porselen

    A Tenaga

    L.01 0,330 OH Pekerja

    L.02 0,250 OH Tukang Batu

    L.03 0,033 OH Kepala Tukang

    L.04 0,033 OH Mandor

    B. Bahan

    1,000 Bu ah Kloset Jongkok

    6,000 Kg Portland Semen

    0,010 m3 Pasir Pasang

    C. Jumlah A+B

    D. Overhead & Profit 13%

    E. Harga Satua n Pekerjaan (D+E)

    .................., ...................... 20.....

    PENAWAR

    PT./CV. .................................

    ...................................

    Direktur

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    14/15

    KOP PERUS H N

    DAFTAR HARGA BAHAN DAN UPAH

    HARGA

    No. URAIAN PEKERJAAN SAT. SATUAN

    (Rp.)

    A. HARGA UPAH PEKERJA

    1 Pekerja OH

    2 Tukang Batu OH

    3 Tukang Besi OH

    4 Tukang Kayu OH

    5 Kepala Tukang Batu OH6 Kepala Tukang Besi OH

    7 Kepala Tukang Kayu OH

    8 Mandor OH

    B. HARGA BAHAN MATERIAL

    1 Pasir Urug m3

    2 Tanah urug baru m3

    3 Batu Blonos m3

    4 Batu Belah 15/20 m3

    5 Portland Sement Kg

    6 Semen Warna Kg

    7 Pasir Pasang m3

    8 Bata Merah 5 x 11 x 22 Buah

    9 Pasir Beton kg

    10 Kerikil (maksimum 30 mm) kg

    11 Air ltr

    12 Besi Beton (polos/ulir) Kg

    13 Kawat Beton Kg

    14 Kayu Klas III (Terentang) m315 Balok Kayu Klas III m3

    16 bambu Btg

    17 Minyak Bekisting Ltr

    18 Ubin Keramik 40 x 40 cm Sekualitas Mulia/Asiatile m2

    19 Ubin Keramik 20 x 20 cm m2

    20 Ubin Keramik 25 x 25 cm m2

    21 Paku kg

    22 Genteng Metal butir pasir m2

    23 Nok Genteng Metal butir pasir Buah

    24 Kaca bening tebal 5 mm m2

    25 Profil Allumunium warna m'

  • 7/26/2019 BQ KUA Siwalan_2015 Oke.pdf

    15/15

    HARGA

    No. URAIAN PEKERJAAN SAT. SATUAN

    (Rp.)

    26 Skrup Fixer buah

    27 Sealant Tube

    28 Pipa PVC " m'

    29 Pipa PVC 3" m'

    30 Pipa PVC 4" m'

    31 Kran Air bh

    32 Sealtape bh

    33 Floor Drain bh

    34 Kloset Jongkok Buah

    .................., ...................... 20.....

    PENAWAR

    PT./CV. .................................

    ...................................

    Direktur