ANALISA HARGA SATUAN PEKERJAAN SEMARANG No. URAIAN KOEFISIEN SAT HARGA SATUAN JUMLAH (RP) I PEKERJAAN PERSIAPAN 1 1 M¹ PAGAR SENG GELOMBANG TINGGI : 2 M a Tiang kayu borneo 4/6 0.05 m 3 4,000,000.00 200,000.00 b Semen PC (abu-abu) 0.05 sak 49,500.00 2,475.00 c Seng gelombang 1.20 lbr 67,000.00 80,400.00 d Pasir beton 0.01 m 3 140,000.00 700.00 e Split (batu pecah) 0.01 m 3 140,000.00 1,260.00 f Balok kayu borneo 4/6 0.05 m 3 4,000,000.00 200,000.00 g Paku 5 - 10 cm 0.06 kg 14,700.00 882.00 h Meni Besi 0.45 kg 18,000.00 8,100.00 i Tukang kayu 0.20 org 42,000.00 8,400.00
154

Analisa Harga Satuan Pekerjaan Semarang

Nov 30, 2015

Download

Documents

Muhammad Fahmi

RAB
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Analisa Harga Satuan Pekerjaan Semarang

ANALISA HARGA SATUAN PEKERJAAN SEMARANG

No. URAIAN KOEFISIEN SAT HARGA SATUAN JUMLAH (RP)I PEKERJAAN PERSIAPAN  1 1 M¹ PAGAR SENG GELOMBANG TINGGI : 2 M

    a Tiang kayu borneo 4/6 0.05 m3 4,000,000.00

200,000.00

    b Semen PC (abu-abu) 0.05 sak 49,500.00

2,475.00

    c Seng gelombang 1.20 lbr 67,000.00

80,400.00

    d Pasir beton 0.01 m3 140,000.00

700.00

    e Split (batu pecah) 0.01 m3 140,000.00

1,260.00

    f Balok kayu borneo 4/6 0.05 m3 4,000,000.00

200,000.00

    g Paku 5 - 10 cm 0.06 kg 14,700.00

882.00

    h Meni Besi 0.45 kg 18,000.00

8,100.00

    i Tukang kayu 0.20 org 42,000.00

8,400.00

    j Pembantu tukang 0.10 org 27,500.00

2,750.00

    Jumlah 504,967.00

    Dibulatkan

Page 2: Analisa Harga Satuan Pekerjaan Semarang

504,960.00   2 1 M¹ PAGAR KAWAT BERDURI TINGGI : 1,8 M

    a Tiang kayu borneo 4/6 0.05 m3 4,000,000.00

200,000.00

    b Semen PC (abu-abu) 0.04 sak 49,500.00

1,980.00

    c Kawat duri 2.50 kg 145,500.00

363,750.00

    d Pasir beton 0.01 m3 140,000.00

700.00

    e Split (batu pecah) 0.01 m3 140,000.00

1,260.00

    f Paku 5 - 10 cm 0.06 kg 14,700.00

882.00

    g Tukang kayu 0.20 org 42,000.00

8,400.00

    h Pembantu tukang 0.30 org 27,500.00

8,250.00

    Jumlah 585,222.00

    Dibulatkan 585,220.00

  3 1 M1 PENGUKURAN & PEMASANGAN BOWPLANK

    a Kayu kaso 5/7 borneo 0.02 m3 4,000,000.00

80,000.00

    b Paku 5 - 10 cm 0.02 kg 14,700.00

294.00

    c Papan papan kayu terentang 2/20 0.00 m3 1,750,000.00

7,000.00

    d Tukang kayu 0.10 org 42,000.00

4,200.00

    e Pembantu tukang 0.10 org

Page 3: Analisa Harga Satuan Pekerjaan Semarang

27,500.00 2,750.00

    Jumlah 94,244.00

    Dibulatkan 94,240.00

  4 1 M2 PEMBUATAN KANTOR DIREKSI

    a Kayu kaso 5/7 borneo 0.02 m3 4,000,000.00

80,000.00

    b Papan kayu terentang 0.18 m3 1,750,000.00

315,000.00

    c Paku semua ukuran 0.85 kg 14,700.00

12,495.00

    d Besi strip 1.10 kg 11,000.00

12,100.00

    e Semen PC (abu-abu) 35.00 kg 49,500.00

1,732,500.00

    f Pasir pasang 0.15 m3 125,000.00

18,750.00

    g Pasir beton 0.10 m3 140,000.00

14,000.00

    h Split (batu pecah) 0.15 m3 140,000.00

21,000.00

    i Bata merah 30.00 bh 325.00

9,750.00

    j Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 58,000.00

69,600.00

    k Seng plat BJLS 32 1.00 m2 32,000.00

32,000.00

    l Kawat harmonika 2.00 m2 19,000.00

38,000.00

    m Kaca polos 3 mm 0.08 m2 52,000.00

4,160.00

Page 4: Analisa Harga Satuan Pekerjaan Semarang

    n Kunci tanam standar 0.15 bh 55,000.00

8,250.00

    o Triplek 120 x 240 x 0,4 cm 0.06 lbr 50,000.00

3,000.00

    p Tukang kayu 2.00 org 42,000.00

84,000.00

    q Tukang batu 1.00 org 42,000.00

42,000.00

    r Pembantu tukang 2.00 org 27,500.00

55,000.00

    Jumlah 2,551,605.00

    Dibulatkan 2,551,600.00

  5 1 M2 PEMBUATAN GUDANG PROYEK

    a Kayu kaso 5/7 borneo 0.02 m3 4,000,000.00

80,000.00

    b Papan kayu terentang 0.10 m3 1,750,000.00

175,000.00

    c Paku 0.30 kg 14,700.00

4,410.00

    d Semen PC (abu-abu) 0.21 sak 49,500.00

10,395.00

    e Pasir beton 0.03 m3 140,000.00

4,200.00

    f Split (batu pecah) 0.05 m3 140,000.00

7,000.00

    g Seng gelombang 180 x 90 x 0,05 cm 1.20 lbr 58,000.00

69,600.00

    h Tukang kayu 1.00 org 42,000.00

42,000.00

    i Pembantu tukang 1.00 org 27,500.00

27,500.00

Page 5: Analisa Harga Satuan Pekerjaan Semarang

    Jumlah 420,105.00

    Dibulatkan 420,100.00

  6 1 M2 MEMBERSIHKAN LOKASI ROYEK

    a Pembantu tukang 0.10 org 27,500.00

2,750.00

    Jumlah 2,750.00

    Dibulatkan 2,700.00

  7 1 M2 MEMBERSIHKAN PUING-PUING

    a Pembantu tukang 0.20 org 27,500.00

5,500.00

    Jumlah 5,500.00

    Dibulatkan 5,500.00

  8 1 BH MEMBERSIHKAN TUNGGUL TANAMAN

       

    a Pembantu tukang 2.00 org 27,500.00

55,000.00

    Jumlah 55,000.00

    Dibulatkan 55,000.00

  9 1 M2 PEMBUATAN JALAN MASUK PROYEK

    a Batu belah 15/20 0.10 m3 120,000.00

12,000.00

    b Koral 5/7 (sirtu) 0.05 m3 80,000.00

4,000.00

    c Pasir urug 0.01 m3

Page 6: Analisa Harga Satuan Pekerjaan Semarang

70,000.00 700.00

    d Pembantu tukang 1.00 org 27,500.00

27,500.00

    Jumlah 44,200.00

    Dibulatkan 44,200.00

  10 1 M3 PEMBONGKARAN BETON

    a Pembantu tukang 6.20 org 27,500.00

170,500.00

    Jumlah 170,500.00

    Dibulatkan 170,500.00

  11 1 M3 PEMBONGKARAN DINDING BATA

    a Pembantu tukang 4.60 org 27,500.00

126,500.00

    Jumlah 126,500.00

    Dibulatkan 126,500.00

  12 1 M2 PEKERJAAN PAGAR PAPAN RANGKA BALOK

    a Papan kayu borneo 0.02 m3 4,800,000.00

96,000.00

    b Balok kayu borneo 5/7 0.02 m3 4,000,000.00

80,000.00

    c Pasir beton 0.08 m3 140,000.00

11,200.00

    d Split (batu pecah) 0.15 m3 140,000.00

21,000.00

    e Semen abu-abu 0.50 sak 49,500.00

24,750.00

Page 7: Analisa Harga Satuan Pekerjaan Semarang

    f Tukang kayu 0.13 org 42,000.00

5,460.00

    g Pembantu tukang 0.38 org 27,500.00

10,450.00

    Jumlah 248,860.00

    Dibulatkan 248,800.00

II PEKERJAAN TANAH  1 1 M3 GALIAN TANAH SEDALAM 1 M

    a Pembantu tukang 0.40 org 27,500.00

11,000.00

    b Tukang gali 0.02 org 30,000.00

600.00

    Jumlah 11,600.00

    Dibulatkan 11,600.00

  21 M3 G

         

    a Pembantu tukang 0.53 org 27,500.00

14,575.00

    b Tukang gali 0.02 org 30,000.00

600.00

    Jumlah 15,175.00

    Dibulatkan 15,170.00

  31 M3 G

         

Page 8: Analisa Harga Satuan Pekerjaan Semarang

    a Pembantu tukang 0.74 org 27,500.00

20,350.00

    b Tukang gali 0.02 org 30,000.00

600.00

    Jumlah 20,950.00

    Dibulatkan 20,950.00

  41 M3 G

         

    a Pembantu tukang 0.45 org 27,500.00

12,375.00

    b Tukang gali 0.02 org 30,000.00

600.00

    Jumlah 12,975.00

    Dibulatkan 12,970.00

  5 1 M2 PEKERJAAN PENGUPASAN TANAH SETEBAL 10 CM

    a Pembantu tukang 0.05 org 27,500.00

687.50

    b Tukang gali 0.02 org 30,000.00

450.00

    Jumlah 1,137.50

    Dibulatkan 1,130.00

  61 M3 PE

         

    a Pembantu tukang 0.42 org 27,500.00

11,550.00

    b Tukang gali 0.02 org

Page 9: Analisa Harga Satuan Pekerjaan Semarang

30,000.00 600.00

    Jumlah 12,150.00

    Dibulatkan 12,100.00

  7 1 M3 URUGAN TANAH KEMBALI

    a Pembantu tukang 0.19 org 27,500.00

5,225.00

    b Tukang gali 0.02 org 30,000.00

600.00

    Jumlah 5,825.00

    Dibulatkan 5,800.00

  8 1 M3 PEMADATAN TANAH

    a Pembantu tukang 0.50 org 27,500.00

13,750.00

    b Tukang gali 0.02 org 30,000.00

600.00

    Jumlah 14,350.00

    Dibulatkan 14,300.00

  9 1 M3 URUGAN PASIR

    a Pasir urug 1.20 m3 70,000.00

84,000.00

    b Pembantu tukang 0.30 org 27,500.00

8,250.00

    c Tukang gali 0.02 org 30,000.00

600.00

    Jumlah 92,850.00

Page 10: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 92,800.00

  10 1 M3 URUGAN TANAH

    a Tanah urug 1.20 m3 75,000.00

90,000.00

    b Pembantu tukang 0.30 org 27,500.00

8,250.00

    c Tukang gali 0.02 org 30,000.00

600.00

    Jumlah 98,850.00

    Dibulatkan 98,800.00

  11 1 M3 URUGAN SIRTU

    a Sirtu (koral) 1.20 m3 80,000.00

96,000.00

    b Pembantu tukang 0.25 org 27,500.00

6,875.00

    c Tukang gali 0.02 org 30,000.00

600.00

    Jumlah 103,475.00

    Dibulatkan 103,400.00

III PEKERJAAN FONDASI  1 1 M3 PASANG FONDASI BT KALI , 1 Pc : 3 Ps

    a Batu belah 1.10 m3 120,000.00

132,000.00

    b Semen PC (abu-abu) 4.04 sak

Page 11: Analisa Harga Satuan Pekerjaan Semarang

49,500.00 199,980.00

    c Pasir pasang 0.49 m3 125,000.00

60,625.00

    d Pembantu tukang 1.50 org 27,500.00

41,250.00

    e Tukang batu 0.60 org 42,000.00

25,200.00

    Jumlah 459,055.00

    Dibulatkan 459,050.00

  2 1 M3 PASANG FONDASI BT KALI , 1 Pc : 4 Ps

    a Batu belah 1.10 m3 120,000.00

132,000.00

    b Semen PC (abu-abu) 3.26 sak 49,500.00

161,370.00

    c Pasir pasang 0.52 m3 125,000.00

65,000.00

    d Pembantu tukang 1.50 org 27,500.00

41,250.00

    e Tukang batu 0.60 org 42,000.00

25,200.00

    Jumlah 424,820.00

    Dibulatkan 424,820.00

  3 1 M3 PASANG FONDASI BT KALI , 1 Pc : 5 Ps

    a Batu belah 1.10 m3 120,000.00

132,000.00

    b Semen PC (abu-abu) 2.72 sak 49,500.00

134,640.00

    c Pasir pasang 0.54 m3

Page 12: Analisa Harga Satuan Pekerjaan Semarang

125,000.00 68,000.00

    d Pembantu tukang 1.50 org 27,500.00

41,250.00

    e Tukang batu 0.60 org 42,000.00

25,200.00

    Jumlah 401,090.00

    Dibulatkan 401,090.00

  4 1 M3 PASANG FONDASI BATU KOSONG ( AANSTAMPING )

    a Batu belah 1.20 m3 120,000.00

144,000.00

    b Pasir urug 0.30 m3 70,000.00

21,000.00

    c Pembantu tukang 0.78 org 27,500.00

21,450.00

    d Tukang batu 0.39 org 42,000.00

16,380.00

    Jumlah 202,830.00

    Dibulatkan 202,800.00

  5 1 M3 MEMBUAT BETON BERTULANG UNTUK FONDASI 1 Pc : 2 Ps : 3 Kr

    a Semen PC (abu-abu) 6.72 sak 49,500.00

332,640.00

    b Pasir beton 0.54 m3 140,000.00

75,600.00

    c Split (batu pecah) 0.81 m3 140,000.00

113,400.00

    d Pembantu tukang 2.00 org 27,500.00

55,000.00

    e Tukang batu 0.35 org

Page 13: Analisa Harga Satuan Pekerjaan Semarang

42,000.00 14,700.00

    Jumlah 591,340.00

    Dibulatkan 591,300.00

  6 1 KG PENULANGAN BETON FONDASI

    a Besi beton polos 1.05 kg 8,750.00

9,187.50

    b Kawat beton 0.02 kg 15,000.00

225.00

    c Pembantu tukang 0.01 org 27,500.00

192.50

    d Tukang besi 0.01 org 42,000.00

294.00

    Jumlah 9,899.00

    Dibulatkan 9,800.00

  7 1 M2 PEKERJAAN BEKISTING UNTUK FONDASI

    a Papan kayu terentang 0.04 m3 1,750,000.00

70,000.00

    b Paku 5 - 12 cm 0.30 kg 1,925.00

577.50

    c Pelumas bekisting (oli/minyak) 0.10 Ltr 10,000.00

1,000.00

    d Pembantu tukang 0.30 org 27,500.00

8,250.00

    e Tukang kayu 0.26 org 42,000.00

10,920.00

    Jumlah 90,747.50

    Dibulatkan

Page 14: Analisa Harga Satuan Pekerjaan Semarang

90,700.00   8 1 M3 PASANG FONDASI CYCLOOP (60 %BETON : 40% BATU KALI)

    a Besi beton polos 50.00 kg 8,750.00

437,500.00

    b Semen PC (abu-abu) 4.04 sak 49,500.00

199,980.00

    c Pasir beton 0.32 m3 140,000.00

44,800.00

    d Split (batu pecah) 0.49 m3 140,000.00

68,600.00

    e Kawat beton 0.80 kg 15,000.00

12,000.00

    f Batu belah 0.40 m3 120,000.00

48,000.00

    g Pembantu tukang 2.00 org 27,500.00

55,000.00

    h Tukang batu 0.85 org 42,000.00

35,700.00

    Jumlah 901,580.00

    Dibulatkan 901,500.00

  9 1 M3 PASANG FONDASI SUMURAN DIAMETER 100 cm

    a Batu belah 0.45 m3 120,000.00

54,000.00

    b Semen PC (abu-abu) 5.60 sak 49,500.00

277,200.00

    c Pasir beton 0.45 m3 140,000.00

63,000.00

    d Split (batu pecah) 0.67 m3 140,000.00

93,800.00

    e Pembantu tukang 2.38 org

Page 15: Analisa Harga Satuan Pekerjaan Semarang

27,500.00 65,450.00

    f Tukang batu 0.30 org 42,000.00

12,600.00

    Jumlah 566,050.00

    Dibulatkan 566,000.00

  10 1 M¹ PEMBUATAN FONDASI TIANG BETON BERTULANG UKURAN 40 X 40 Cm

    a Pasir beton 0.10 m3 140,000.00

14,000.00

    b Split (batu pecah) 0.15 m3 140,000.00

21,000.00

    c Semen PC (abu-abu) 1.21 sak 49,500.00

59,895.00

    d Besi beton polos 45.00 kg 8,750.00

393,750.00

    e Kawat beton 0.90 kg 15,000.00

13,500.00

    f Balok kayu borneo super 5/7 0.03 m3 4,000,000.00

128,000.00

    g Papan kayu terentang 0.01 m3 1,750,000.00

17,500.00

    h Paku 5 - 12 cm 0.12 kg 14,700.00

1,764.00

    i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00

900.00

    j Plamir tembok 0.24 kg 9,000.00

2,160.00

    k Pembantu tukang 1.00 org 27,500.00

27,500.00

    l Tukang batu 0.67 org 42,000.00

28,140.00

Page 16: Analisa Harga Satuan Pekerjaan Semarang

    Jumlah 708,109.00

    Dibulatkan 708,100.00

  11 1 M¹ PEMBUATAN FONDASI TIANG BETON BERTULANG UKURAN 35 X 35 CM

    a Pasir beton 0.08 m3 140,000.00

11,200.00

    b Split (batu pecah) 0.13 m3 140,000.00

18,200.00

    c Semen PC (abu-abu) 0.98 sak 49,500.00

48,510.00

    d Besi beton polos 34.50 kg 8,750.00

301,875.00

    e Kawat beton 0.70 kg 15,000.00

10,500.00

    f Balok kayu borneo super 5/7 0.03 m3 4,000,000.00

120,000.00

    g Papan kayu terentang 0.01 m3 1,750,000.00

17,500.00

    h Paku 5 - 12 cm 0.12 kg 14,700.00

1,764.00

    i Pelumas begisting (oli/minyak) 0.09 Ltr 10,000.00

900.00

    j Plamir tembok 0.20 kg 9,000.00

1,800.00

    k Pembantu tukang 0.80 org 27,500.00

22,000.00

    l Tukang batu 0.50 org 42,000.00

21,000.00

    Jumlah 575,249.00

    Dibulatkan 575,200.00

Page 17: Analisa Harga Satuan Pekerjaan Semarang

  12 1 M3 MEMBUAT FONDASI TIANG PANCANG UKURAN 25 X 25

  a Pasir beton 0.06 m3 140,000.00

8,400.00

  b Split (batu pecah) 0.11 m3 140,000.00

15,400.00

  c Semen PC (abu-abu) 0.82 sak 49,500.00

40,590.00

  d Besi beton polos 34.50 kg 8,750.00

301,875.00

  e Kawat beton 0.60 kg 15,000.00

9,000.00

  f Balok kayu borneo super 5/7 0.03 m3 4,000,000.00

120,000.00

  g Papan kayu terentang 0.01 m3 1,750,000.00

17,500.00

  h Paku 5 - 12 cm 0.11 kg 14,700.00

1,617.00

  i Pelumas begisting (oli/minyak) 0.08 Ltr 10,000.00

800.00

  j Plamir tembok 0.20 kg 9,000.00

1,800.00

  k Pembantu tukang 0.80 org 27,500.00

22,000.00

  l Tukang batu 0.50 org 42,000.00

21,000.00

    Jumlah 559,982.00

    Dibulatkan 559,900.00

  13 1 M3 MEMBUAT FONDASI PLAT BETON (PENULANGAN 125 kg + BEKISTING )

    a Papan kayu terentang 0.20 m3 1,750,000.00

350,000.00

Page 18: Analisa Harga Satuan Pekerjaan Semarang

    b Paku 5 - 12 cm 1.50 kg 14,700.00

22,050.00

    c Pelumas begisting (oli/minyak) 0.40 Ltr 10,000.00

4,000.00

    d Besi beton polos 125.00 kg 8,750.00

1,093,750.00

    e Kawat beton 2.25 kg 15,000.00

33,750.00

    f Semen PC (abu-abu) 6.46 sak 49,500.00

319,770.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Pembantu tukang 3.90 org 27,500.00

107,250.00

    j Tukang batu 0.35 org 42,000.00

14,700.00

    k Tukang kayu 1.04 org 42,000.00

43,680.00

    l Tukang besi 1.05 org 42,000.00

44,100.00

    Jumlah 2,215,050.00

    Dibulatkan 2,215,000.00

  14 1 M3 MEMBUAT FONDASI PLAT BETON (PENULANGAN 150 kg + BEKISTING )

    a Papan kayu terentang 0.20 m3 1,750,000.00

350,000.00

    b Paku 5 - 12 cm 1.50 kg 14,700.00

22,050.00

    c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00

4,000.00

Page 19: Analisa Harga Satuan Pekerjaan Semarang

    d Besi beton polos Polos 150.00 kg 8,750.00

1,312,500.00

    e Kawat beton 2.25 kg 15,000.00

33,750.00

    f Semen PC (abu-abu) 6.46 sak 49,500.00

319,770.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Pembantu tukang 4.00 org 27,500.00

110,000.00

    j Tukang batu 0.40 org 42,000.00

16,800.00

    k Tukang kayu 1.00 org 42,000.00

42,000.00

    l Tukang besi 1.00 org 42,000.00

42,000.00

    Jumlah 2,434,870.00

    Dibulatkan 2,434,800.00

  15 1 M3 MEMBUAT FONDASI BETON BOREPILE (PENULANGAN 125 kg + BEKISTING )

    a Papan kayu terentang 0.20 m3 1,750,000.00

350,000.00

    b Paku 5 - 12 cm 1.50 kg 14,700.00

22,050.00

    c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00

4,000.00

    d Besi beton polos 125.00 kg 8,750.00

1,093,750.00

    e Kawat beton 2.10 kg 15,000.00

31,500.00

Page 20: Analisa Harga Satuan Pekerjaan Semarang

    f Semen PC (abu-abu) 6.46 sak 49,500.00

319,770.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Pembantu tukang 3.90 org 27,500.00

107,250.00

    j Tukang batu 0.40 org 42,000.00

16,800.00

    k Tukang kayu 1.00 org 42,000.00

42,000.00

    l Tukang besi 1.00 org 42,000.00

42,000.00

    Jumlah 2,211,120.00

    Dibulatkan 2,211,100.00

  16 1 M3 MEMBUAT FONDASI BETON BOREPILE (PENULANGAN 150 kg + BEKISTING )

    a Papan kayu terentang 0.20 m3 1,750,000.00

350,000.00

    b Paku 5 - 12 cm 1.50 kg 14,700.00

22,050.00

    c Pelumas begisting (oli/minyak) 0.40 ltr 10,000.00

4,000.00

    d Besi beton polos 150.00 kg 8,750.00

1,312,500.00

    e Kawat beton 2.25 kg 15,000.00

33,750.00

    f Semen PC (abu-abu) 6.46 sak 49,500.00

319,770.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

Page 21: Analisa Harga Satuan Pekerjaan Semarang

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Pembantu tukang 4.00 org 27,500.00

110,000.00

    j Tukang batu 0.40 org 42,000.00

16,800.00

    k Tukang kayu 1.00 org 42,000.00

42,000.00

    l Tukang besi 1.00 org 42,000.00

42,000.00

    Jumlah 2,434,870.00

    Dibulatkan 2,434,800.00

       IV PEKERJAAN BETON NON STRUKTUR DAN BETON STRUKTUR  A PEKERJAAN BETON

  11 M3 MEMBUAT BETON NON STRUKTUR, 1 Pc : 3 Ps : 5 Splt

     

    a Semen PC (abu-abu) 4.36 sak 49,500.00

215,820.00

    b Pasir beton 0.52 m3 140,000.00

72,800.00

    c Split (batu pecah) 0.87 m3 140,000.00

121,800.00

    d Pembantu tukang 2.00 org 27,500.00

55,000.00

    e Tukang batu 0.35 org 42,000.00

14,700.00

    Jumlah

Page 22: Analisa Harga Satuan Pekerjaan Semarang

480,120.00

    Dibulatkan 480,100.00

  2 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 4 Splt

    a Semen PC (abu-abu) 4.64 sak 49,500.00

229,680.00

    b Pasir beton 0.52 m3 140,000.00

72,800.00

    c Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    d Pembantu tukang 2.00 org 27,500.00

55,000.00

    e Tukang batu 0.35 org 42,000.00

14,700.00

    Jumlah 481,380.00

    Dibulatkan 481,300.00

  3 1 M3 MEMBUAT BETON STRUKTUR 1 Pc : 2 Ps : 3 Splt

    a Semen PC (abu-abu) 6.72 sak 49,500.00

332,640.00

    b Pasir beton 0.54 m3 140,000.00

75,600.00

    c Split (batu pecah) 0.81 m3 140,000.00

113,400.00

    d Pembantu tukang 2.00 org 27,500.00

55,000.00

    e Tukang batu 0.35 org 42,000.00

14,700.00

    Jumlah 591,340.00

    Dibulatkan

Page 23: Analisa Harga Satuan Pekerjaan Semarang

591,300.00   4 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 225

    a Semen PC (abu-abu) 7.76 sak 49,500.00

384,120.00

    b Pasir beton 0.65 m3 140,000.00

91,000.00

    c Split (batu pecah) 0.65 m3 140,000.00

91,000.00

    d Pembantu tukang 2.00 org 27,500.00

55,000.00

    e Tukang batu 0.35 org 42,000.00

14,700.00

    Jumlah 635,820.00

    Dibulatkan 635,800.00

  5 1 M3 MEMBUAT BETON STRUKTUR DENGAN MUTU K 275

    a Semen PC (abu-abu) 8.00 sak 49,500.00

396,000.00

    b Pasir beton 0.55 m3 140,000.00

77,000.00

    c Split (batu pecah) 0.70 m3 140,000.00

98,000.00

    d Pembantu tukang 2.02 org 27,500.00

55,550.00

    e Tukang batu 0.40 org 42,000.00

16,800.00

    Jumlah 643,350.00

    Dibulatkan 643,300.00

  B PEKERJAAN PEMBESIAN

Page 24: Analisa Harga Satuan Pekerjaan Semarang

  1 1 KG PENULANGAN BETON/Besi beton polos

    a Besi beton polos 1.05 kg 8,750.00

9,187.50

    b Kawat beton 0.02 kg 15,000.00

300.00

    c Pembantu tukang 0.01 org 27,500.00

275.00

    d Tukang besi 0.01 org 42,000.00

420.00

    Jumlah 10,182.50

    Dibulatkan 10,100.00

  2 1 KG PENULANGAN BETON/BESI BETON ULIR

    a Besi Beton Ulir 1.10 kg 10,000.00

11,000.00

    b Kawat beton 0.02 kg 15,000.00

225.00

    c Pembantu tukang 0.01 org 27,500.00

275.00

    d Tukang besi 0.02 org 42,000.00

840.00

    Jumlah 12,340.00

    Dibulatkan 12,300.00

  C PEKERJAAN BEGISTING  1 1 M2 PASANG BEKISTING UNTUK SLOOF

    a Papan kayu terentang 0.05 m3 1,750,000.00

78,750.00

    b Paku 5 - 12 cm 0.30 kg 14,700.00

4,410.00

Page 25: Analisa Harga Satuan Pekerjaan Semarang

    c Pelumas begisting (oli/minyak) 0.10 Ltr 10,000.00

1,000.00

    d Pembantu tukang 0.30 org 27,500.00

8,250.00

    e Tukang kayu 0.26 org 42,000.00

10,920.00

    Jumlah 103,330.00

    Dibulatkan 103,300.00

  2 1 M2 PASANG BEKISTING UNTUK KOLOM

    a Papan kayu terentang 0.04 m3 1,750,000.00

70,000.00

    b Paku 5 - 12 cm 0.40 kg 14,700.00

5,880.00

    c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00

2,000.00

    d Balok kayu borneo 0.04 m3 4,000,000.00

160,000.00

    e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00

36,750.00

    f Pembantu tukang 0.30 org 27,500.00

8,250.00

    g Tukang kayu 0.33 org 42,000.00

13,860.00

    Jumlah 296,740.00

    Dibulatkan 296,700.00

  3 1 M2 PASANG BEKISTING UNTUK BALOK

    a Papan kayu terentang 0.04 m3 1,750,000.00

70,000.00

Page 26: Analisa Harga Satuan Pekerjaan Semarang

    b Paku 5 - 12 cm 0.40 kg 14,700.00

5,880.00

    c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00

2,000.00

    d Balok kayu borneo 0.04 m3 4,000,000.00

160,000.00

    e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00

36,750.00

    f Pembantu tukang 0.32 org 27,500.00

8,800.00

    g Tukang kayu 0.33 org 42,000.00

13,860.00

    Jumlah 297,290.00

    Dibulatkan 297,200.00

  4 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI

    a Papan kayu terentang 0.04 m3 1,750,000.00

70,000.00

    b Paku 5 - 12 cm 0.40 kg 14,700.00

5,880.00

    c Pelumas begisting (oli/minyak) 0.20 Ltr 10,000.00

2,000.00

    d Balok kayu borneo 0.04 m3 4,000,000.00

160,000.00

    e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00

36,750.00

    f Pembantu tukang 0.32 org 27,500.00

8,800.00

    g Tukang kayu 0.33 org 42,000.00

13,860.00

    Jumlah 297,290.00

Page 27: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 297,200.00

  5 1 M2 PASANG BEKISTING UNTUK TANGGA

    a Papan kayu terentang 0.03 m3 1,750,000.00

52,500.00

    b Paku 5 - 12 cm 0.40 kg 14,700.00

5,880.00

    c Pelumas begisting (oli/minyak) 0.15 Ltr 10,000.00

1,500.00

    d Balok kayu borneo 0.02 m3 4,000,000.00

80,000.00

    e Multiplex 120 x 240 x 9 mm 0.35 lbr 105,000.00

36,750.00

    f Pembantu tukang 0.32 org 27,500.00

8,800.00

    g Tukang kayu 0.33 org 42,000.00

13,860.00

    Jumlah 199,290.00

    Dibulatkan 199,200.00

  D PEKERJAAN BETON BERTULANG  1 1 M3 MEMBUAT SLOOF BETON BERTULANG ( 200 kg BESI + BEKISTING ) K225

    a Papan kayu terentang 0.27 m3 1,750,000.00

472,500.00

    b Paku 5 - 12 cm 2.00 kg 14,700.00

29,400.00

    c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00

6,000.00

    d Besi beton polos 200.00 kg 8,750.00

1,750,000.00

    e Kawat beton 3.00 kg

Page 28: Analisa Harga Satuan Pekerjaan Semarang

15,000.00 45,000.00

    f Semen PC (abu-abu) 8.00 sak 49,500.00

396,000.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Pembantu tukang 4.50 org 27,500.00

123,750.00

    j Tukang batu 0.35 org 42,000.00

14,700.00

    k Tukang kayu 1.56 org 42,000.00

65,520.00

    l Tukang besi 1.40 org 42,000.00

58,800.00

    Jumlah 3,143,670.00

    Dibulatkan 3,143,600.00

  2 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 125 kg BESI + BEKISTING )

    a Papan kayu terentang 0.40 m3 1,750,000.00

700,000.00

    b Paku 5 - 12 cm 4.00 kg 14,700.00

58,800.00

    c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00

20,000.00

    d Besi beton polos 125.00 kg 8,750.00

1,093,750.00

    e Kawat beton 4.50 kg 15,000.00

67,500.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

Page 29: Analisa Harga Satuan Pekerjaan Semarang

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo Super 0.30 m3 4,000,000.00

1,200,000.00

    j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00

367,500.00

    k Pembantu tukang 7.30 org 27,500.00

200,750.00

    l Tukang batu 0.35 org 42,000.00

14,700.00

    m Tukang kayu 3.30 org 42,000.00

138,600.00

    n Tukang besi 2.10 org 42,000.00

88,200.00

    Jumlah 4,451,075.00

    Dibulatkan 4,451,000.00

  3 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 150 kg BESI + BEKISTING )

    a Papan kayu terentang 0.40 m3 1,750,000.00

700,000.00

    b Paku 5 - 12 cm 4.00 kg 14,700.00

58,800.00

    c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00

20,000.00

    d Besi beton polos 150.00 kg 8,750.00

1,312,500.00

    e Kawat beton 4.50 kg 15,000.00

67,500.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

Page 30: Analisa Harga Satuan Pekerjaan Semarang

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo Super 0.30 m3 4,000,000.00

1,200,000.00

    j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00

367,500.00

    k Pembantu tukang 7.30 org 27,500.00

200,750.00

    l Tukang batu 0.35 org 42,000.00

14,700.00

    m Tukang kayu 3.30 org 42,000.00

138,600.00

    n Tukang besi 2.10 org 42,000.00

88,200.00

    Jumlah 4,669,825.00

    Dibulatkan 4,669,800.00

  4 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 160 kg BESI + BEKISTING )

    a Papan kayu terentang 0.40 m3 1,750,000.00

700,000.00

    b Paku 5 - 12 cm 4.00 kg 14,700.00

58,800.00

    c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00

20,000.00

    d Besi beton polos 160.00 kg 8,750.00

1,400,000.00

    e Kawat beton 4.50 kg 15,000.00

67,500.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

Page 31: Analisa Harga Satuan Pekerjaan Semarang

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo Super 0.30 m3 4,000,000.00

1,200,000.00

    j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00

367,500.00

    k Pembantu tukang 7.30 org 27,500.00

200,750.00

    l Tukang batu 0.35 org 42,000.00

14,700.00

    m Tukang kayu 3.30 org 42,000.00

138,600.00

  n Tukang besi 2.10 org 42,000.00

88,200.00

  Jumlah 4,757,325.00

    Dibulatkan 4,757,300.00

  5 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 175 kg BESI + BEKISTING )

    a Papan kayu terentang 0.40 m3 1,750,000.00

700,000.00

    b Paku 5 - 12 cm 4.00 kg 14,700.00

58,800.00

    c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00

20,000.00

    d Besi beton polos 175.00 kg 8,750.00

1,531,250.00

    e Kawat beton 4.50 kg 15,000.00

67,500.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

Page 32: Analisa Harga Satuan Pekerjaan Semarang

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo Super 0.30 m3 4,000,000.00

1,200,000.00

    j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00

367,500.00

    k Pembantu tukang 7.30 org 27,500.00

200,750.00

    l Tukang batu 0.35 org 42,000.00

14,700.00

    m Tukang kayu 3.30 org 42,000.00

138,600.00

    n Tukang besi 2.10 org 42,000.00

88,200.00

    Jumlah 4,888,575.00

    Dibulatkan 4,888,500.00

  6 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 200 kg BESI + BEKISTING )

    a Papan kayu terentang 0.40 m3 1,750,000.00

700,000.00

    b Paku 5 - 12 cm 4.00 kg 14,700.00

58,800.00

    c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00

20,000.00

    d Besi beton polos 200.00 kg 8,750.00

1,750,000.00

    e Kawat beton 4.50 kg 15,000.00

67,500.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

Page 33: Analisa Harga Satuan Pekerjaan Semarang

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo Super 0.30 m3 4,000,000.00

1,200,000.00

    j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00

367,500.00

    k Pembantu tukang 7.30 org 27,500.00

200,750.00

    l Tukang batu 0.35 org 42,000.00

14,700.00

    m Tukang kayu 3.30 org 42,000.00

138,600.00

    n Tukang besi 2.10 org 42,000.00

88,200.00

    Jumlah 5,107,325.00

    Dibulatkan 5,107,300.00

  7 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 250 kg BESI + BEKISTING )

    a Papan kayu terentang 0.40 m3 1,750,000.00

700,000.00

    b Paku 5 - 12 cm 4.00 kg 14,700.00

58,800.00

    c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00

20,000.00

    d Besi beton polos 250.00 kg 8,750.00

2,187,500.00

    e Kawat beton 4.50 kg 15,000.00

67,500.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

Page 34: Analisa Harga Satuan Pekerjaan Semarang

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo super 0.30 m3 4,000,000.00

1,200,000.00

    j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00

367,500.00

    k Pembantu tukang 7.30 org 27,500.00

200,750.00

    l Tukang batu 0.35 org 42,000.00

14,700.00

    m Tukang kayu 3.30 org 42,000.00

138,600.00

    n Tukang besi 2.10 org 42,000.00

88,200.00

    Jumlah 5,544,825.00

    Dibulatkan 5,544,800.00

  8 1 M3 MEMBUAT KOLOM BETON BERTULANG ( 300 kg BESI + BEKISTING )

    a Papan kayu terentang 0.40 m3 1,750,000.00

700,000.00

    b Paku 5 - 12 cm 4.00 kg 14,700.00

58,800.00

    c Pelumas begisting (oli/minyak) 2.00 Ltr 10,000.00

20,000.00

    d Besi beton polos 300.00 kg 8,750.00

2,625,000.00

    e Kawat beton 4.50 kg 15,000.00

67,500.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

Page 35: Analisa Harga Satuan Pekerjaan Semarang

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo Super 0.30 m3 4,000,000.00

1,200,000.00

    j Multiplex 120 x 240 x 9 mm 3.50 lbr 105,000.00

367,500.00

    k Pembantu tukang 7.30 org 27,500.00

200,750.00

    l Tukang batu 0.35 org 42,000.00

14,700.00

    m Tukang kayu 3.30 org 42,000.00

138,600.00

    n Tukang besi 2.10 org 42,000.00

88,200.00

    Jumlah 5,982,325.00

    Dibulatkan 5,982,300.00

  9 1 M3 MEMBUAT BALOK BETON BERTULANG ( 125 kg BESI + BEKISTING )

    a Papan kayu terentang 0.32 m3 1,750,000.00

560,000.00

    b Paku 5 - 12 cm 3.20 kg 14,700.00

47,040.00

    c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00

16,000.00

    d Besi beton polos 125.00 kg 8,750.00

1,093,750.00

    e Kawat beton 2.25 kg 15,000.00

33,750.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

Page 36: Analisa Harga Satuan Pekerjaan Semarang

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo Super 0.12 m3 4,000,000.00

480,000.00

    j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00

294,000.00

    kDolken Ø-8 cm atau kayu 4 x 6 cm / 4m

32.00 btg 18,000.00

576,000.00

    l Pembantu tukang 5.80 org 27,500.00

159,500.00

    m Tukang batu 0.35 org 42,000.00

14,700.00

    n Tukang kayu 2.80 org 42,000.00

117,600.00

    o Tukang besi 1.05 org 42,000.00

44,100.00

    Jumlah 3,937,715.00

    Dibulatkan 3,937,700.00

  10 1 M3 MEMBUAT BALOK BETON BERTULANG ( 150 kg BESI + BEKISTING )

    a Papan kayu terentang 0.32 m3 1,750,000.00

560,000.00

    b Paku 5 - 12 cm 3.20 kg 14,700.00

47,040.00

    c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00

16,000.00

    d Besi beton polos 150.00 kg 8,750.00

1,312,500.00

    e Kawat beton 2.25 kg

Page 37: Analisa Harga Satuan Pekerjaan Semarang

15,000.00 33,750.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo Super 0.12 m3 4,000,000.00

480,000.00

    j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00

294,000.00

    kDolken Ø-8 Cm atau kayu 4 x 6 cm / 4m

32.00 btg 18,000.00

576,000.00

    l Pembantu tukang 5.80 org 27,500.00

159,500.00

    m Tukang batu 0.35 org 42,000.00

14,700.00

    n Tukang kayu 2.80 org 42,000.00

117,600.00

    o Tukang besi 1.05 org 42,000.00

44,100.00

      Jumlah   4,156,465.00

      Dibulatkan       4,156,400.00

  11 1 M3 MEMBUAT BALOK BETON BERTULANG ( 200 kg BESI + BEKISTING )

    a Papan kayu terentang 0.32 m3 1,750,000.00

560,000.00

    b Paku 5 - 12 cm 3.20 kg 14,700.00

47,040.00

    c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00

16,000.00

Page 38: Analisa Harga Satuan Pekerjaan Semarang

    d Besi beton polos 200.00 kg 8,750.00

1,750,000.00

    e Kawat beton 3.00 kg 15,000.00

45,000.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

  i Balok kayu borneo Super 0.14 m3 4,000,000.00

560,000.00

  j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00

294,000.00

  kDolken Ø-8 Cm atau kayu 4 x 6 cm / 4m

16.00 btg 18,000.00

288,000.00

  l Pembantu tukang 5.96 org 27,500.00

163,900.00

  m Tukang batu 0.35 org 42,000.00

14,700.00

  n Tukang kayu 2.80 org 42,000.00

117,600.00

  o Tukang besi 1.40 org 42,000.00

58,800.00

  Jumlah 4,416,315.00

    Dibulatkan 4,416,300.00

  12 1 M3 MEMBUAT BALOK BETON BERTULANG (200 kg BESI + BEKISTING)

  a Papan kayu terentang 0.32 m3 1,750,000.00

560,000.00

  b Paku 5 - 12 cm 3.20 kg

Page 39: Analisa Harga Satuan Pekerjaan Semarang

14,700.00 47,040.00

  c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00

16,000.00

  d Besi beton polos 225.00 kg 8,750.00

1,968,750.00

  e Kawat beton 4.00 kg 15,000.00

60,000.00

  f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

  g Pasir beton 0.52 m3 140,000.00

72,800.00

  h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

  i Balok kayu borneo Super 0.14 m3 4,000,000.00

560,000.00

    j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00

294,000.00

    kDolken Ø-8 Cm atau kayu 4 x 6 cm / 4m

16.00 btg 18,000.00

288,000.00

    l Pembantu tukang 5.96 org 27,500.00

163,900.00

    m Tukang batu 0.35 org 42,000.00

14,700.00

    n Tukang kayu 2.80 org 42,000.00

117,600.00

    o Tukang besi 1.40 org 42,000.00

58,800.00

    Jumlah 4,650,065.00

    Dibulatkan 4,650,000.00

  13 1 M3 MEMBUAT BALOK BETON BERTULANG ( 250 kg BESI + BEKISTING )

Page 40: Analisa Harga Satuan Pekerjaan Semarang

    a Papan kayu terentang 0.32 m3 1,750,000.00

560,000.00

    b Paku 5 - 12 cm 3.20 kg 14,700.00

47,040.00

    c Pelumas begisting (oli/minyak) 1.60 Ltr 10,000.00

16,000.00

    d Besi beton polos 250.00 kg 8,750.00

2,187,500.00

    e Kawat beton 6.00 kg 15,000.00

90,000.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo super 0.14 m3 4,000,000.00

560,000.00

    j Multiplex 120 x 240 x 9 mm 2.80 lbr 105,000.00

294,000.00

    kDolken Ø-8 Cm atau kayu 4 x 6 cm / 4m

16.00 btg 18,000.00

288,000.00

    l Pembantu tukang 5.96 org 27,500.00

163,900.00

    m Tukang batu 0.35 org 42,000.00

14,700.00

    n Tukang kayu 2.80 org 42,000.00

117,600.00

    o Tukang besi 1.40 org 42,000.00

58,800.00

    Jumlah 4,898,815.00

    Dibulatkan

Page 41: Analisa Harga Satuan Pekerjaan Semarang

4,898,800.00   14 1 M3 MEMBUAT TANGGA BETON BERTULANG ( 200 kg BESI + BEKISTING )

    a Papan kayu terentang 0.25 m3 1,750,000.00

437,500.00

    b Paku 5 - 12 cm 3.00 kg 14,700.00

44,100.00

    c Pelumas begisting (oli/minyak) 1.20 Ltr 10,000.00

12,000.00

    d Besi beton polos 200.00 kg 8,750.00

1,750,000.00

    e Kawat beton 3.00 kg 15,000.00

45,000.00

    f Semen PC (abu-abu) 6.45 sak 49,500.00

319,275.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Balok kayu borneo super 0.30 m3 4,000,000.00

1,200,000.00

    j Multiplex 120 x 240 x 9 mm 2.50 lbr 105,000.00

262,500.00

    k Pembantu tukang 5.60 org 27,500.00

154,000.00

    l Tukang batu 0.35 org 42,000.00

14,700.00

    m Tukang kayu 2.30 org 42,000.00

96,600.00

    n Tukang besi 1.40 org 42,000.00

58,800.00

    Jumlah 4,576,475.00

Page 42: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 4,576,400.00

  15 1 M3 MEMBUAT PLAT LANTAI Tb. 10 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )

    aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr

1.00 m3 591,340.00

591,340.00

    b Pasang bekisting untuk lantai 10.00 m2 297,290.00

2,972,900.00

    c Besi beton rakit 100.00 kg 8,750.00

875,000.00

    Jumlah 4,439,240.00

    Dibulatkan 4,439,200.00

  16 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )

    aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr

1.00 m3 591,340.00

591,340.00

    b Pasang bekisting untuk lantai 8.33 m2 297,290.00

2,476,425.70

    c Besi beton rakit 115.00 kg 8,750.00

1,006,250.00

    Jumlah 4,074,015.70

    Dibulatkan 4,074,000.00

  17 1 M3 MEMBUAT PLAT LANTAI Tb. 12 Cm BETON BERTULANG ( 125 kg BESI + BEKISTING )

    aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr

1.00 m3 591,340.00

591,340.00

    b Pasang Bekisting untuk lantai 8.33 m2 297,290.00

2,476,425.70

    c Besi Beton rakit 125.00 kg 8,750.00

1,093,750.00

    Jumlah

Page 43: Analisa Harga Satuan Pekerjaan Semarang

4,161,515.70

    Dibulatkan 4,161,500.00

  18 1 M3 MEMBUAT PLAT LANTAI Tb. 15 Cm BETON BERTULANG ( 100 kg BESI + BEKISTING )

    aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr

1.00 m3 591,340.00

591,340.00

    b Pasang Bekisting untuk lantai 6.67 m2 297,290.00

1,982,924.30

    c Besi Beton rakit 100.00 kg 8,750.00

875,000.00

    Jumlah 3,449,264.30

    Dibulatkan 3,449,200.00

  19 1 M3 MEMBUAT PLAT LANTAI Tb. 20 Cm BETON BERTULANG ( 115 kg BESI + BEKISTING )

    aBeton bertulang camp. 1Pc : 2 Ps : 3 Kr

1.00 m3 591,340.00

591,340.00

    b Pasang Bekisting untuk lantai 7.50 m2 297,290.00

2,229,675.00

    c Besi Beton rakit 115.00 kg 8,750.00

1,006,250.00

    Jumlah 3,827,265.00

    Dibulatkan 3,827,200.00

  20 1 M3 MEMBUAT RING BALK BETON BERTULANG ( 175 kg BESI + BEKISTING ) K225

    a Papan kayu terentang 0.27 m3 1,750,000.00

472,500.00

    b Paku 5 - 12 cm 2.00 kg 14,700.00

29,400.00

    c Pelumas begisting (oli/minyak) 0.60 Ltr 10,000.00

6,000.00

Page 44: Analisa Harga Satuan Pekerjaan Semarang

    d Besi beton polos 175.00 kg 8,750.00

1,531,250.00

    e Kawat beton 3.00 kg 15,000.00

45,000.00

    f Semen PC (abu-abu) 8.00 sak 49,500.00

396,000.00

    g Pasir beton 0.52 m3 140,000.00

72,800.00

    h Split (batu pecah) 0.78 m3 140,000.00

109,200.00

    i Pembantu tukang 4.85 org 27,500.00

133,375.00

    j Tukang batu 0.40 org 42,000.00

16,800.00

    k Tukang kayu 1.75 org 42,000.00

73,500.00

    l Tukang besi 1.45 org 42,000.00

60,900.00

    Jumlah 2,946,725.00

    Dibulatkan 2,946,700.00

V PEKERJAAN DINDING  1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 3 Ps

    a Bata merah 140.00 bh 325.00

45,500.00

    b Semen PC (abu-abu) 0.65 sak 49,500.00

32,175.00

    c Pasir pasang 0.09 m3 125,000.00

11,250.00

Page 45: Analisa Harga Satuan Pekerjaan Semarang

    d Pembantu tukang 0.65 org 27,500.00

17,875.00

    e Tukang batu 0.20 org 42,000.00

8,400.00

    Jumlah 115,200.00

    Dibulatkan 115,200.00

  2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 4 Ps

    a Bata merah 140.00 bh 325.00

45,500.00

    b Semen PC (abu-abu) 0.55 sak 49,500.00

27,225.00

    c Pasir pasang 0.09 m3 125,000.00

11,250.00

    d Pembantu tukang 0.65 org 27,500.00

17,875.00

    e Tukang batu 0.20 org 42,000.00

8,400.00

    Jumlah 110,250.00

    Dibulatkan 110,200.00

  3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, CAMPURAN 1 Pc : 5 Ps

    a Bata merah 140.00 bh 325.00

45,500.00

    b Semen PC (abu-abu) 0.45 sak 49,500.00

22,275.00

    c Pasir pasang 0.10 m3 125,000.00

12,500.00

    d Pembantu tukang 0.65 org 27,500.00

17,875.00

Page 46: Analisa Harga Satuan Pekerjaan Semarang

    e Tukang batu 0.20 org 42,000.00

8,400.00

    Jumlah 106,550.00

    Dibulatkan 106,500.00

  4 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 3 Ps

    a Bata merah 70.00 bh 325.00

22,750.00

    b Semen PC (abu-abu) 0.29 sak 49,500.00

14,355.00

    c Pasir pasang 0.04 m3 125,000.00

5,000.00

    d Pembantu tukang 0.32 org 27,500.00

8,800.00

    e Tukang batu 0.10 org 42,000.00

4,200.00

    Jumlah 55,105.00

    Dibulatkan 55,100.00

  5 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 4 Ps

    a Bata merah 70.00 bh 325.00

22,750.00

    b Semen PC (abu-abu) 0.25 sak 49,500.00

12,375.00

    c Pasir pasang 0.05 m3 125,000.00

6,250.00

    d Pembantu tukang 0.32 org 27,500.00

8,800.00

    e Tukang batu 0.10 org 42,000.00

4,200.00

Page 47: Analisa Harga Satuan Pekerjaan Semarang

    Jumlah 54,375.00

    Dibulatkan 54,300.00

  6 1 M2 PASANGAN BATA MERAH TEBAL ½ BATA, CAMPURAN 1 Pc : 5 Ps

    a Bata merah 70.00 bh 325.00

22,750.00

    b Semen PC (abu-abu) 0.22 sak 49,500.00

10,890.00

    c Pasir pasang 0.05 m3 125,000.00

6,250.00

    d Pembantu tukang 0.32 org 27,500.00

8,800.00

    e Tukang batu 0.10 org 42,000.00

4,200.00

    Jumlah 52,890.00

    Dibulatkan 52,800.00

  7 1 M2 PASANG DINDING BATA ROOSTER / BATA TERAWANG

    aRooster/Terawang ukuran 12 x 11 x 24

37.00 bh 3,000.00

111,000.00

    b Semen PC (abu-abu) 0.27 sak 49,500.00

13,365.00

    c Pasir pasang 0.04 m3 125,000.00

5,000.00

    d Pembantu tukang 0.30 org 27,500.00

8,250.00

    e Tukang batu 0.10 org 42,000.00

4,200.00

    Jumlah 141,815.00

Page 48: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 141,800.00

  8 1 M2 PASANG DINDING GLASSBLOCK

    a Glassblock ukuran 18 x 18 cm 30.00 bh 17,000.00

510,000.00

    b Semen Putih 0.27 sak 12,700.00

3,429.00

    c Pembantu tukang 0.30 org 27,500.00

8,250.00

    d Tukang batu 0.10 org 42,000.00

4,200.00

    Jumlah 525,879.00

    Dibulatkan 525,800.00

  9 1 M2 PASANGAN BATACO PUTIH, CAMPURAN 1 Pc : 5 Ps

    a Batako putih 15.00 bh 4,200.00

63,000.00

    b Semen PC (abu-abu) 0.25 sak 42,000.00

10,500.00

    c Pasir pasang 0.03 m3 68,000.00

2,040.00

    d Pembantu tukang 0.30 org 27,500.00

8,250.00

    e Tukang batu 0.15 org 40,000.00

6,000.00

    Jumlah 89,790.00

    Dibulatkan 89,700.00

  10 1 M2 PASANGAN BATACO PRES SEMEN, CAMPURAN 1 Pc : 5 Ps    a Bataco press semen 15.00 bh

Page 49: Analisa Harga Satuan Pekerjaan Semarang

2,650.00 39,750.00

    b Semen PC (abu-abu) 0.20 sak 49,500.00

9,900.00

    c Pasir pasang 0.02 m3 125,000.00

2,500.00

    d Pembantu tukang 0.30 org 27,500.00

8,250.00

    e Tukang batu 0.15 org 42,000.00

6,300.00

    Jumlah 66,700.00

    Dibulatkan 66,700.00

  11 1 M2 PASANGAN BATA RINGAN ( HEBEL/CELCON )

    a Bata ringan ( hebel/celcon ) 8.00 bh 2,550.00

20,400.00

    b Semen instan 11.45 kg 2,450.00

28,052.50

    c Pembantu tukang 0.30 org 27,500.00

8,250.00

    d Tukang batu 0.20 org 42,000.00

8,400.00

    Jumlah 65,102.50

    Dibulatkan 65,100.00

           VI PEKERJAAN PLESTERAN/ACCI  1 1 M2 PLESTERAN CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm    a Semen PC (abu-abu) 0.14 sak

Page 50: Analisa Harga Satuan Pekerjaan Semarang

49,500.00 6,930.00

    b Pasir pasang 0.02 m3 125,000.00

2,500.00

    c Pembantu tukang 0.20 org 27,500.00

5,500.00

    d Tukang batu 0.15 org 42,000.00

6,300.00

    Jumlah 21,230.00

    Dibulatkan 21,200.00

  2 1 M2 PLESTERAN CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm

    a Semen PC (abu-abu) 0.13 sak 49,500.00

6,435.00

    b Pasir pasang 0.02 m3 125,000.00

2,500.00

    c Pembantu tukang 0.20 org 27,500.00

5,500.00

    d Tukang batu 0.15 org 42,000.00

6,300.00

    Jumlah 20,735.00

    Dibulatkan 20,700.00

  3 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 1,5 cm

    a Semen PC (abu-abu) 0.10 sak 49,500.00

4,950.00

    b Pasir pasang 0.02 m3 125,000.00

2,500.00

    c Pembantu tukang 0.20 org 27,500.00

5,500.00

    d Tukang batu 0.15 org

Page 51: Analisa Harga Satuan Pekerjaan Semarang

42,000.00 6,300.00

    Jumlah 19,250.00

    Dibulatkan 19,200.00

  4 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm

    a Semen PC (abu-abu) 0.09 sak 49,500.00

4,455.00

    b Pasir pasang 0.02 m3 125,000.00

2,500.00

    c Pembantu tukang 0.20 org 27,500.00

5,500.00

    d Tukang batu 0.15 org 42,000.00

6,300.00

    Jumlah 18,755.00

    Dibulatkan 18,700.00

  5 1 M2 PLESTERAN CAMPURAN 1 Pc : 4 Ps TEBAL 2,0 cm

    a Semen PC (abu-abu) 0.17 sak 49,500.00

8,415.00

    b Pasir pasang 0.03 m3 125,000.00

3,750.00

    c Pembantu tukang 0.22 org 27,500.00

6,050.00

    d Tukang batu 0.16 org 42,000.00

6,720.00

    Jumlah 24,935.00

    Dibulatkan 24,900.00

  6 1 M2 PLESTERAN CAMPURAN 1 Pc : 5 Ps TEBAL 2,0 cm

Page 52: Analisa Harga Satuan Pekerjaan Semarang

    a Semen PC (abu-abu) 0.15 sak 49,500.00

7,425.00

    b Pasir pasang 0.03 m3 125,000.00

3,750.00

    c Pembantu tukang 0.25 org 27,500.00

6,875.00

    d Tukang batu 0.20 org 42,000.00

8,400.00

    Jumlah 26,450.00

    Dibulatkan 26,400.00

  7 1 M2 BERAPEN CAMPURAN 1 Pc : 5 Ps TEBAL 1,5 cm

    a Semen PC (abu-abu) 0.11 sak 49,500.00

5,445.00

    b Pasir pasang 0.03 m3 125,000.00

3,125.00

    c Pembantu tukang 0.15 org 27,500.00

4,125.00

    d Tukang batu 0.07 org 42,000.00

2,940.00

    Jumlah 15,635.00

    Dibulatkan 15,600.00

  8 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 2 Ps TEBAL 1,5 cm

    a Semen PC (abu-abu) 0.19 sak 49,500.00

9,405.00

    b Pasir pasang 0.02 m3 125,000.00

2,500.00

    c Pembantu tukang 0.26 org 27,500.00

7,150.00

Page 53: Analisa Harga Satuan Pekerjaan Semarang

    d Tukang batu 0.20 org 42,000.00

8,400.00

    Jumlah 27,455.00

    Dibulatkan 27,400.00

  9 1 M2 PLESTERAN BETON CAMPURAN 1 Pc : 3 Ps TEBAL 1,5 cm

    a Semen PC (abu-abu) 0.15 sak 49,500.00

7,425.00

    b Pasir pasang 0.02 m3 125,000.00

2,500.00

    c Pembantu tukang 0.26 org 27,500.00

7,150.00

    d Tukang batu 0.20 org 42,000.00

8,400.00

    Jumlah 25,475.00

    Dibulatkan 25,400.00

  10 1 M2 PLESTERAN SKONENG CAMPURAN 1 Pc : 2 Ps

    a Semen PC (abu-abu) 0.01 sak 49,500.00

495.00

    b Pasir pasang 0.01 m3 125,000.00

1,250.00

    c Pembantu tukang 0.06 org 27,500.00

1,650.00

    d Tukang batu 0.04 org 42,000.00

1,680.00

    Jumlah 5,075.00

    Dibulatkan 5,000.00

Page 54: Analisa Harga Satuan Pekerjaan Semarang

  11 1 M2 ACIAN PLESTERAN

    a Semen PC (abu-abu) 0.08 sak 49,500.00

3,960.00

    b Pembantu tukang 0.14 org 27,500.00

3,850.00

    c Tukang batu 0.11 org 42,000.00

4,620.00

    Jumlah 12,430.00

    Dibulatkan 12,400.00

  12 1 M2 PLESTERAN SIAR CAMPURAN 1 Pc : 2 Ps

    a Semen PC (abu-abu) 0.09 sak 49,500.00

4,455.00

    b Pasir pasang 0.02 m3 125,000.00

2,500.00

    c Pembantu tukang 0.15 org 27,500.00

4,125.00

    d Tukang batu 0.07 org 42,000.00

2,940.00

    Jumlah 14,020.00

    Dibulatkan 14,000.00

VII PEKERJAAN PELAPIS LANTAI  1 1 M2 P   

    a Keramik ukuran 40 x 40 cm 1.00 m2 200,000.00

200,000.00

    b Semen PC (abu-abu) 0.16 sak 49,500.00

7,920.00

Page 55: Analisa Harga Satuan Pekerjaan Semarang

    c Pasir pasang 0.02 m3 125,000.00

2,687.50

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.25 org 27,500.00

6,875.00

    f Tukang batu 0.12 org 42,000.00

5,040.00

    Jumlah 222,776.50

    Dibulatkan 222,770.00

  2 1 M2 PASANG LANTAI KERAMIK UKURAN 40 x 40 cm UNPOLISH

    a Keramik ukuran 40 x 40 cm 1.00 m2 200,000.00

200,000.00

    b Semen PC (abu-abu) 0.16 sak 49,500.00

7,920.00

    c Pasir pasang 0.02 m3 125,000.00

2,500.00

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.26 org 27,500.00

7,150.00

    f Tukang batu 0.13 org 42,000.00

5,250.00

    Jumlah 223,074.00

    Dibulatkan 223,070.00

  3 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 60 cm

    a Keramik ukuran 60 x 60 cm 1.00 m2 276,000.00

276,000.00

Page 56: Analisa Harga Satuan Pekerjaan Semarang

    b Semen PC (abu-abu) 0.18 sak 49,500.00

8,910.00

    c Pasir pasang 0.02 m3 125,000.00

2,687.50

    d Semen warna 0.01 kg 12,700.00

165.10

    e Pembantu tukang 0.25 org 27,500.00

6,875.00

    f Tukang batu 0.12 org 42,000.00

5,040.00

    Jumlah 299,677.60

    Dibulatkan 299,670.00

  4 1 M2 PASANG LANTAI KERAMIK UKURAN 60 x 90 cm  

    a Keramik ukuran 60 x 90 cm 1.00 m2 300,000.00

300,000.00

    b Semen PC (abu-abu) 0.17 sak 49,500.00

8,415.00

    c Pasir pasang 0.02 m3 125,000.00

2,687.50

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.26 org 27,500.00

7,150.00

    f Tukang batu 0.14 org 42,000.00

5,880.00

    Jumlah 324,386.50

    Dibulatkan 324,380.00

  5 1 M2 PASANG LANTAI KERAMIK 10 x 20 cm

Page 57: Analisa Harga Satuan Pekerjaan Semarang

    a Keramik lantai 10 x 20 cm 1.00 m2 35,000.00

35,000.00

    b Semen PC ( abu-abu ) 0.18 sak 49,500.00

8,910.00

    c Pasir pasang 0.02 m3 125,000.00

2,500.00

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.22 org 27,500.00

6,050.00

    f Tukang batu 0.40 org 42,000.00

16,800.00

    Jumlah 69,514.00

    Dibulatkan 69,510.00

  6 1 M2 PASANG LANTAI KERAMIK POLOS 20 x 20 cm

    a Keramik polos 20 x 20 cm 1.00 m2 35,000.00

35,000.00

    b Semen PC (abu-abu) 0.17 sak 49,500.00

8,415.00

    c Pasir pasang 0.02 m3 125,000.00

2,687.50

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.30 org 27,500.00

8,250.00

    f Tukang batu 0.15 org 42,000.00

6,300.00

    Jumlah 60,906.50

    Dibulatkan 60,900.00

Page 58: Analisa Harga Satuan Pekerjaan Semarang

  7 1 M2 PASANG LANTAI KERAMIK MOTIF 20 x 20 cm

    a Keramik motif 20 x 20 cm 1.00 m2 37,000.00

37,000.00

    b Semen PC (abu-abu) 0.17 sak 49,500.00

8,415.00

    c Pasir pasang 0.02 m3 125,000.00

2,687.50

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.30 org 27,500.00

8,250.00

    f Tukang batu 0.15 org 42,000.00

6,300.00

    Jumlah 62,906.50

    Dibulatkan 62,900.00

  8 1 M2 PASANG LANTAI KERAMIK POLOS 30 x 30 cm

    a Keramik polos 30 x 30 cm 1.00 m2 33,000.00

33,000.00

    b Semen PC (abu-abu) 0.16 sak 49,500.00

7,920.00

    c Pasir pasang 0.02 m3 125,000.00

2,500.00

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.25 org 27,500.00

6,875.00

    f Tukang batu 0.12 org 42,000.00

5,040.00

    Jumlah 55,589.00

Page 59: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 55,580.00

  9 1 M2 PASANG LANTAI KERAMIK MOTIF 30 x 30 cm

    a Keramik motif 30 x 30 cm 1.00 m2 42,000.00

42,000.00

    b Semen PC (abu-abu) 0.16 sak 49,500.00

7,920.00

    c Pasir pasang 0.02 m3 125,000.00

2,500.00

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.25 org 27,500.00

6,875.00

    f Tukang batu 0.12 org 42,000.00

5,040.00

    Jumlah 64,589.00

    Dibulatkan 64,580.00

  10 1 M2 PASANG LANTAI MARMER

    a Marmer standart 1.00 m2 135,000.00

135,000.00

    b Semen PC (abu-abu) 0.48 sak 49,500.00

23,760.00

    c Pasir pasang 0.10 m3 125,000.00

12,500.00

    d Semen warna 0.20 sak 12,700.00

2,540.00

    e Pembantu tukang 0.62 org 27,500.00

17,050.00

    f Tukang batu 0.35 org 42,000.00

14,700.00

Page 60: Analisa Harga Satuan Pekerjaan Semarang

    Jumlah 205,550.00

    Dibulatkan 205,550.00

  11 1 M2 PASANG LANTAI PARQUET JATI

    a Parquet jati 1.05 m2 260,000.00

273,000.00

    b Lem vinyl 0.60 kg 30,800.00

18,480.00

    c Pembantu tukang 0.65 org 27,500.00

17,875.00

    d Tukang 0.35 org 42,000.00

14,700.00

    Jumlah 324,055.00

    Dibulatkan 324,050.00

  12 1 M2 PASANG LANTAI GRANIT

    a Granit Standart 1.00 m2 650,000.00

650,000.00

    b Semen PC (abu-abu) 0.48 sak 49,500.00

23,760.00

    c Pasir pasang 0.08 m3 125,000.00

10,000.00

    d Semen warna 0.10 sak 12,700.00

1,270.00

    e Pembantu tukang 0.60 org 27,500.00

16,500.00

    f Tukang batu 0.48 org 42,000.00

20,160.00

    Jumlah 721,690.00

Page 61: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 721,690.00

     VIII PEKERJAAN PELAPIS DINDING  1 1 M2 P   

    a Keramik motif 10 x 20 cm 1.00 m2 37,000.00

37,000.00

    b Semen PC ( abu-abu ) 0.18 sak 49,500.00

8,910.00

    c Pasir pasang 0.02 m3 125,000.00

2,500.00

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.22 org 27,500.00

6,050.00

    f Tukang batu 0.40 org 42,000.00

16,800.00

    Jumlah 71,514.00

    Dibulatkan 71,510.00

  2 1 M2 PASANG DINDING KERAMIK POLOS 10 x 20 cm

    a Keramik polos 10 x 20 cm 1.00 m2 34,000.00

34,000.00

    b Semen PC ( abu-abu ) 0.18 sak 49,500.00

8,910.00

    c Pasir pasang 0.02 m3 125,000.00

2,500.00

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.22 org

Page 62: Analisa Harga Satuan Pekerjaan Semarang

27,500.00 6,050.00

    f Tukang batu 0.40 org 42,000.00

16,800.00

    Jumlah 68,514.00

    Dibulatkan 68,510.00

  3 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 20 cm

    a Keramik motif 20 x 20 cm 1.00 m2 37,000.00

37,000.00

    b Semen PC ( abu-abu ) 0.17 sak 49,500.00

8,415.00

    c Pasir pasang 0.02 m3 125,000.00

2,500.00

    d Semen warna 0.02 kg 12,700.00

254.00

    e Pembantu tukang 0.20 org 27,500.00

5,500.00

    f Tukang batu 0.39 org 42,000.00

16,380.00

    Jumlah 70,049.00

    Dibulatkan 70,040.00

  4 1 M2 PASANG DINDING KERAMIK POLOS 20 x 20 cm

    a Keramik polos 20 x 20 cm 1.00 m2 38,000.00

38,000.00

    b Semen PC ( abu-abu ) 0.17 sak 49,500.00

8,415.00

    c Pasir pasang 0.02 m3 125,000.00

2,500.00

    d Semen warna 0.02 kg

Page 63: Analisa Harga Satuan Pekerjaan Semarang

12,700.00 254.00

    e Pembantu tukang 0.20 org 27,500.00

5,500.00

    f Tukang batu 0.39 org 42,000.00

16,380.00

    Jumlah 71,049.00

    Dibulatkan 71,040.00

  5 1 M2 PASANG DINDING KERAMIK POLOS 20 x 25 cm

    a Keramik polos 20 x 25 cm 1.00 m2 38,500.00

38,500.00

    b Semen PC ( abu-abu ) 0.16 sak 49,500.00

7,920.00

    c Pasir pasang 0.02 m3 125,000.00

2,250.00

    d Semen warna 0.01 kg 12,700.00

165.10

    e Pembantu tukang 0.19 org 27,500.00

5,156.25

    f Tukang batu 0.38 org 42,000.00

15,750.00

    Jumlah 69,741.35

    Dibulatkan 69,740.00

  6 1 M2 PASANG DINDING KERAMIK MOTIF 20 x 25 cm

    a Keramik motif 20 x 25 cm 1.00 m2 38,500.00

38,500.00

    b Semen PC ( abu-abu ) 0.16 sak 49,500.00

7,920.00

    c Pasir pasang 0.02 m3

Page 64: Analisa Harga Satuan Pekerjaan Semarang

125,000.00 2,250.00

    d Semen warna 0.01 kg 12,700.00

165.10

    e Pembantu tukang 0.19 org 27,500.00

5,156.25

    f Tukang batu 0.38 org 42,000.00

15,750.00

    Jumlah 69,741.35

    Dibulatkan 69,740.00

  7 1 M2 PASANG DINDING MARMER

    a Marmer standar 1.00 m2 135,000.00

135,000.00

    b Paku sekrup 4.00 bh 700.00

2,800.00

    c Semen PC ( abu-abu ) 0.25 sak 49,500.00

12,375.00

    d Pasir pasang 0.03 m3 125,000.00

3,125.00

    e Semen warna 1.50 kg 12,700.00

19,050.00

    f Kawat ikat 0.03 kg 15,000.00

375.00

    g Paku 0.03 kg 14,700.00

367.50

    h Pembantu tukang 0.72 org 27,500.00

19,800.00

    i Tukang batu 0.65 org 42,000.00

27,300.00

    Jumlah 220,192.50

Page 65: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 220,190.00

  8 1 M2 PASANG DINDING GRANIT

    a Granit standar 1.00 m2 650,000.00

650,000.00

    b Paku sekrup 2.00 bh 700.00

1,400.00

    c Semen PC ( abu-abu ) 0.25 sak 49,500.00

12,375.00

    d Pasir pasang 0.03 m3 125,000.00

3,125.00

    e Semen warna 1.50 kg 12,700.00

19,050.00

    f Kawat ikat 0.03 kg 15,000.00

375.00

    g Paku 0.03 kg 14,700.00

367.50

    h Pembantu tukang 0.72 org 27,500.00

19,800.00

    i Tukang batu 0.65 org 42,000.00

27,300.00

    Jumlah 733,792.50

    Dibulatkan 733,790.00

  9 1 M2 PASANG DINDING BATU TEMPEL HITAM

    a Batu tempel hitam 1.00 m2 80,000.00

80,000.00

    b Semen PC ( abu-abu ) 0.24 sak 49,500.00

11,880.00

    c Pasir pasang 0.04 m3 125,000.00

4,375.00

Page 66: Analisa Harga Satuan Pekerjaan Semarang

    d Pembantu tukang 0.32 org 27,500.00

8,800.00

    e Tukang batu 0.25 org 42,000.00

10,500.00

    Jumlah 115,555.00

    Dibulatkan 115,550.00

  10 1 M2 PASANG DINDING BATU ALAM

    a Batu alam 1.00 m2 78,000.00

78,000.00

    b Semen PC ( abu-abu ) 0.25 sak 49,500.00

12,375.00

    c Pasir pasang 0.04 m3 125,000.00

4,375.00

    d Pembantu tukang 0.32 org 27,500.00

8,800.00

    e Tukang batu 0.25 org 42,000.00

10,500.00

    Jumlah 114,050.00

    Dibulatkan 114,050.00

  11 1 M¹ PASANG PLINT KERAMIK UKURAN 10 x 40 cm

    a Plint keramik ukuran 10 x 40 cm 2.65 bh 7,500.00

19,875.00

    b Semen PC (abu-abu) 0.02 sak 49,500.00

990.00

    c Pasir pasang 0.01 m3 125,000.00

1,250.00

    d Semen warna 0.10 kg 12,700.00

1,270.00

Page 67: Analisa Harga Satuan Pekerjaan Semarang

    e Pembantu tukang 0.06 org 27,500.00

1,650.00

    f Tukang batu 0.03 org 42,000.00

1,260.00

    Jumlah 26,295.00

    Dibulatkan 26,290.00

  12 1 M¹ PASANG PLINT KERAMIK UKURAN 10 x 30 cm

    a Plint keramik ukuran 10 x 30 cm 3.30 bh 6,500.00

21,450.00

    b Semen PC (abu-abu) 0.02 sak 49,500.00

990.00

    c Pasir pasang 0.01 m3 125,000.00

1,250.00

    d Semen warna 0.12 kg 12,700.00

1,524.00

    e Pembantu tukang 0.06 org 27,500.00

1,650.00

    f Tukang batu 0.03 org 42,000.00

1,260.00

    Jumlah 28,124.00

    Dibulatkan 28,120.00

IX PEKERJAAN KUSEN, PINTU, JENDELA, PARTISI  1 1 M3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER SAMARINDA

    a Balok kayu kamper samarinda 1.20 m3 5,000,000.00

6,000,000.00

Page 68: Analisa Harga Satuan Pekerjaan Semarang

    b Pembantu tukang 6.00 org 27,500.00

165,000.00

    c Tukang kayu 15.00 org 42,000.00

630,000.00

    Jumlah 6,795,000.00

    Dibulatkan 6,795,000.00

  2 1 M3 PASANG KUSEN PINTU & JENDELA KAYU KAMPER MEDAN / KRUING

    a Balok kayu kamper medan 1.20 m3 4,100,000.00

4,920,000.00

    b Pembantu tukang 6.00 org 27,500.00

165,000.00

    c Tukang kayu 15.00 org 42,000.00

630,000.00

    Jumlah 5,715,000.00

    Dibulatkan 5,715,000.00

  3 1 M3 PASANG KUSEN PINTU & JENDELA KAYU BORNEO SUPER

    a Kayu balok borneo super 1.20 m3 4,000,000.00

4,800,000.00

    b Pembantu tukang 6.00 org 27,500.00

165,000.00

    c Tukang kayu 15.00 org 42,000.00

630,000.00

    Jumlah 5,595,000.00

    Dibulatkan 5,595,000.00

  4 1 M2 PASANG PINTU PANEL KAYU KAMPER SAMARINDA    a Papan kayu kamper samarinda 0.04 m3

Page 69: Analisa Harga Satuan Pekerjaan Semarang

5,350,000.00 214,000.00

    b Pembantu tukang 1.00 org 27,500.00

27,500.00

    c Tukang kayu 2.50 org 42,000.00

105,000.00

    Jumlah 346,500.00

    Dibulatkan 346,500.00

  5 1 M2 PASANG PINTU PANEL KAYU KAMPER MEDAN / KRUING

    a Papan kayu Kamper Medan 0.04 m3 4,275,000.00

171,000.00

    b Pembantu tukang 1.00 org 27,500.00

27,500.00

    c Tukang kayu 2.50 org 42,000.00

105,000.00

    Jumlah 303,500.00

    Dibulatkan 303,500.00

  6 1 M2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER MEDAN

    a Papan kayu kamper medan 0.04 m3 4,275,000.00

117,600.00

    b Pembantu tukang 0.80 org 27,500.00

44,100.00

    c Tukang kayu 2.00 org 42,000.00

117,600.00

    Jumlah 279,300.00

    Dibulatkan 279,300.00

  7 1 M2 PASANG PINTU DAN JENDELA KACA KAYU BORNEO

Page 70: Analisa Harga Satuan Pekerjaan Semarang

    a Papan kayu borneo super 0.04 m3 4,800,000.00

47,040.00

    b Pembantu tukang 0.80 org 27,500.00

16,000.00

    c Tukang kayu 2.00 org 42,000.00

84,000.00

    Jumlah 147,040.00

    Dibulatkan 147,000.00

  8 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU KAMPER MEDAN

    a Papan kayu kamper medan 0.06 m3 4,275,000.00

273,600.00

    b Pembantu tukang 1.00 org 27,500.00

27,500.00

    c Tukang kayu 3.00 org 42,000.00

126,000.00

    Jumlah 427,100.00

    Dibulatkan 427,100.00

  9 1 M2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU KAMPER MEDAN

    a Papan kayu kamper medan 0.02 m3 4,275,000.00

83,790.00

    b Paku 1 s/d 5 cm 0.03 kg 14,700.00

441.00

    c Lem kayu 0.30 Ltr 20,000.00

6,000.00

    d Triplek 0,4 cm ukuran pintu 1.00 lbr 36,000.00

36,000.00

    e Pembantu tukang 0.60 org 27,500.00

16,500.00

Page 71: Analisa Harga Satuan Pekerjaan Semarang

    f Tukang kayu 2.00 org 42,000.00

84,000.00

    Jumlah 226,731.00

    Dibulatkan 226,700.00

  10 1 M2 PASANG JALUSI MATI KUSEN KAYU KAMPER MEDAN

    a Papan kayu kamper medan 0.06 m3 4,275,000.00

256,500.00

    b Paku 1 s/d 5 cm 0.15 kg 14,700.00

2,205.00

    c Pembantu tukang 0.50 org 27,500.00

13,750.00

    d Tukang kayu 2.00 org 42,000.00

84,000.00

    Jumlah 356,455.00

    Dibulatkan 356,400.00

  11 1 M2 PASANG PINTU TRIPLEK RANGKAP , RANGKA KAYU BORNEO SUPER

    a Papan kayu borneo Super 0.02 m3 4,800,000.00

94,080.00

    b Paku 1 s/d 5 cm 0.03 kg 14,700.00

441.00

    c Lem Kayu 0.30 Ltr 20,000.00

6,000.00

    d Triplek 0,4 cm ukuran pintu 1.00 lbr 36,000.00

36,000.00

    e Pembantu tukang 0.60 org 27,500.00

16,500.00

    f Tukang kayu 2.00 org 42,000.00

84,000.00

Page 72: Analisa Harga Satuan Pekerjaan Semarang

    Jumlah 237,021.00

    Dibulatkan 237,000.00

  12 1 M2 PASANG PINTU TEAKWOOD RANGKAP , RANGKA KAYU KAMPER MEDAN

    a Papan kayu kamper medan 0.02 m3 4,275,000.00

83,790.00

    b Paku 1 s/d 5 cm 0.30 kg 14,700.00

4,410.00

    c Lem kayu 0.30 Ltr 20,000.00

6,000.00

    d Teakwood 120 x 240 x 0,4 cm 1.00 lbr 85,000.00

85,000.00

    e Pembantu tukang 0.60 org 27,500.00

16,500.00

    f Tukang kayu 2.00 org 42,000.00

84,000.00

    Jumlah 279,700.00

    Dibulatkan 279,700.00

  13 1 M2 PASANG PINTU TRIPLEK & FORMIKA RANGKA KAYU KAMPER MEDAN

    a Papan kayu kamper medan 0.02 m3 4,800,000.00

94,080.00

    b Paku 1 s/d 5 cm 0.30 kg 14,700.00

4,410.00

    c Lem Kayu 0.80 Ltr 20,000.00

16,000.00

    d Triplek 0,4 cm ukuran pintu 1.00 lbr 36,000.00

36,000.00

    e Formica 3" x 6" 0.50 lbr 135,000.00

67,500.00

Page 73: Analisa Harga Satuan Pekerjaan Semarang

    f Pembantu tukang 0.80 org 27,500.00

22,000.00

    g Tukang kayu 2.50 org 42,000.00

105,000.00

    Jumlah 344,990.00

    Dibulatkan 344,900.00

  14 1 M2 PASANG PINTU TEAKWOOD & FORMIKA RANGKA KAYU KAMPER MEDAN

    a Papan kayu kamper medan 0.02 m3 4,275,000.00

83,790.00

    b Paku 1 s/d 5 cm 0.30 kg 14,700.00

4,410.00

    c Lem Kayu 0.80 Ltr 20,000.00

16,000.00

    d Teakwood 120 x 240 x 0,4 cm 0.50 lbr 85,000.00

42,500.00

    e Vernis 0.50 Ltr 27,500.00

13,750.00

    a Formica 4" x 8" 0.50 lbr 135,000.00

67,500.00

    b Pembantu tukang 0.80 org 27,500.00

22,000.00

    c Tukang kayu 2.50 org 42,000.00

105,000.00

    Jumlah 354,950.00

    Dibulatkan 354,900.00

  15 1 M2 PASANG DINDING PEMISAH DOUBLE TEAKWOOD, RANGKA KAYU KAMPER MEDAN

    a Balok kayu Kamper Medan 0.02 m3 4,100,000.00

79,950.00

Page 74: Analisa Harga Satuan Pekerjaan Semarang

    b Papan kayu Kamper Medan 0.01 m3 4,275,000.00

29,925.00

    c Paku 5 - 12 cm 0.10 kg 14,700.00

1,470.00

    d Lem Kayu 0.56 Ltr 20,000.00

11,200.00

    e Teakwood 120 x 240 x 0,4 cm 1.00 lbr 85,000.00

85,000.00

    f Pembantu tukang 0.15 org 27,500.00

4,125.00

    g Tukang kayu 0.45 org 42,000.00

18,900.00

    Jumlah 230,570.00

    Dibulatkan 230,500.00

  16 1 M2 PASANG DINDING PEMISAH DOUBLE GRC, RANGKA KAYU KAMPER MEDAN

    a Balok kayu kamper medan 0.02 m3 4,100,000.00

79,950.00

    b Papan kayu kamper medan 0.01 m3 4,275,000.00

29,925.00

    c Paku 5 - 12 cm 0.10 kg 14,700.00

1,470.00

    d Lem Kayu 0.56 Ltr 20,000.00

11,200.00

    e Triplek 0,4 cm ukuran pintu 1.00 lbr 36,000.00

36,000.00

    f Pembantu tukang 0.20 org 27,500.00

5,500.00

    g Tukang kayu 0.60 org 42,000.00

25,200.00

    Jumlah 189,245.00

Page 75: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 189,200.00

  17 1 Bh PASANG PINTU ALUMINIUM / PINTU PVC

    a Pintu aluminium/Pintu PVC 1.00 bh 375,000.00

375,000.00

    b Alat bantu 10 % harga material 1.00 ls 37,500.00

37,500.00

    c Tukang kayu 0.02 org 42,000.00

882.00

    Jumlah 413,382.00

    Dibulatkan 413,300.00

  18 1 M2 PASANG KUSEN PARTISI DOUBLE TRIPLEK

    a Balok kayu borneo super 0.11 m3 4,000,000.00

420,000.00

    b Triplek 0,4 cm ukuran pintu 5.00 lbr 36,000.00

180,000.00

    c Paku 1 s/d 3 cm 2.00 kg 14,700.00

29,400.00

    d Ampelas 2.00 lbr 3,200.00

6,400.00

    e Engsel 4.00 bh 22,000.00

88,000.00

    f Grendel/Slot 4.00 bh 31,000.00

124,000.00

    g Pembantu tukang 0.30 org 27,500.00

8,250.00

    h Tukang kayu terampil 1.30 org 42,000.00

54,600.00

    Jumlah 910,650.00

Page 76: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 129,530.00

  19 1 M2 PASANG KUSEN PARTISI DOUBLE GYPSUM + RANGKA KAYU

    a Balok kayu borneo super 0.11 m3 4,000,000.00

420,000.00

    b Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 59,000.00

42,480.00

    c Paku 1 s/d 3 cm 2.00 kg 14,700.00

29,400.00

    d Ampelas 2.00 lbr 3,200.00

6,400.00

    e Engsel 4.00 bh 22,000.00

88,000.00

    f Grendel/Slot 4.00 bh 31,000.00

124,000.00

    g Pembantu tukang 0.30 org 27,500.00

8,250.00

    h Tukang kayu 1.30 org 42,000.00

54,600.00

    Jumlah 773,130.00

    Dibulatkan 129,530.00

  20 1 M2 PASANG DINDING PARTISI GYPSUM BOARD + RANGKA BESI HOLLOW

    a Hollow 4/4 Zincromate 0.42 btg 45,000.00

18,900.00

    b Hollow 2/4 Zincromate 0.15 btg 32,000.00

4,800.00

    c Gypsum board ( 120 x 240 x 9 ) mm 0.72 lbr 59,000.00

42,480.00

    d Paku sekrup 25.00 bh 700.00

17,500.00

Page 77: Analisa Harga Satuan Pekerjaan Semarang

    e Ramset / dina bolt 4.00 bh 2,400.00

9,600.00

    f Cotton plaster 0.10 bh 56,000.00

5,600.00

    g Compoun 0.13 kg 28,500.00

3,705.00

    h Pembantu tukang 0.10 org 27,500.00

2,750.00

    i Tukang kayu 0.05 org 42,000.00

2,100.00

    Jumlah 107,435.00

    Dibulatkan 107,430.00

           X PEKERJAAN RANGKA ATAP DAN PENUTUP ATAPA PEKERJAAN RANGKA ATAP  1 1 M3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU KAMPER MEDAN

    a Balok kayu kamper medan 1.10 m3 4,100,000.00

4,510,000.00

    b Besi Strip 15.00 kg 11,000.00

165,000.00

    c Paku Ukuran besar 0.80 kg 14,700.00

11,760.00

    d Meni kayu 0.40 kg 15,000.00

6,000.00

    e Pembantu tukang 4.00 org 27,500.00

110,000.00

    f Tukang kayu 12.00 org

Page 78: Analisa Harga Satuan Pekerjaan Semarang

42,000.00 504,000.00

    Jumlah 5,306,760.00

    Dibulatkan 5,306,700.00

  2 1 M3 PEKERJAAN KONSTRUKSI KUDA - KUDA KAYU BORNEO SUPER

    a Balok kayu borneo super 1.10 m3 1,378,000.00

1,515,800.00

    b Besi Strip 15.00 kg 11,000.00

165,000.00

    c Paku ukuran besar 0.80 kg 14,700.00

11,760.00

    d Meni kayu 0.40 kg 15,000.00

6,000.00

    e Pembantu tukang 4.00 org 27,500.00

110,000.00

    f Tukang kayu 12.00 org 42,000.00

504,000.00

    Jumlah 2,312,560.00

    Dibulatkan 2,312,500.00

  3 1 M2 PASANG KASO + RENG GENTENG PLENTONG KAYU BORNEO SUPER

    a Balok kayu borneo super 0.01 m3 4,000,000.00

48,000.00

    b Paku 7 - 10 cm 0.15 kg 14,700.00

2,205.00

    c Pembantu tukang 0.10 org 27,500.00

2,750.00

    d Tukang kayu 0.10 org 42,000.00

4,200.00

    Jumlah

Page 79: Analisa Harga Satuan Pekerjaan Semarang

57,155.00

    Dibulatkan 57,100.00

  4 1 M2 PASANG KASO + RENG GENTENG BETON KAYU BORNEO SUPER

    a Balok kayu borneo super 0.01 m3 4,000,000.00

56,000.00

    b Paku 7 - 10 cm 0.15 kg 14,700.00

2,205.00

    c Pembantu tukang 0.10 org 27,500.00

2,750.00

    d Tukang kayu 0.10 org 42,000.00

4,200.00

    Jumlah 65,155.00

    Dibulatkan 65,100.00

  5 1 M1 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 20 cm

    a Papan kayu Kamper Medan 0.01 m3 4,275,000.00

30,780.00

    b Paku 7 - 10 cm 0.05 kg 14,700.00

735.00

    c Pembantu tukang 0.10 org 27,500.00

2,750.00

    d Tukang kayu 0.20 org 42,000.00

8,400.00

    Jumlah 42,665.00

    Dibulatkan 42,600.00

  6 1 M2 PASANG LISPLANG KAYU KAMPER MEDAN UKURAN 3 X 30 cm

    a Papan kayu Kamper Medan 0.01 m3 4,275,000.00

47,025.00

Page 80: Analisa Harga Satuan Pekerjaan Semarang

    b Paku 7 - 10 cm 0.05 kg 14,700.00

735.00

    c Pembantu tukang 0.11 org 27,500.00

3,025.00

    d Tukang kayu 0.22 org 42,000.00

9,240.00

    Jumlah 60,025.00

    Dibulatkan 60,000.00

  7 1 M3 PEKERJAAN NOK/GORDING/JURAY KAYU BORNEO SUPER

    a Balok kayu borneo super 1.05 m3 4,000,000.00

4,200,000.00

    b Paku 10 - 15 cm 0.20 kg 14,700.00

2,940.00

    c Pembantu tukang 2.00 org 27,500.00

55,000.00

    d Tukang kayu 2.00 org 42,000.00

84,000.00

    Jumlah 4,341,940.00

    Dibulatkan 4,341,900.00

B PEKERJAAN PENUTUP ATAP  1 1 M2 PASANG ATAP GENTENG PLENTONG

    a Genteng palentong 25.00 bh 800.00

20,000.00

    b Pembantu tukang 0.15 org 27,500.00

4,125.00

    c Tukang kayu 0.08 org 42,000.00

3,150.00

    Jumlah

Page 81: Analisa Harga Satuan Pekerjaan Semarang

27,275.00

    Dibulatkan 27,270.00

  2 1 M2 PASANG NOK/BUBUNGAN GENTENG KERAMIK GLAZUR

    a Genteng nok/bubungan plentong 5.00 bh 16,500.00

82,500.00

    b Semen PC (abu-abu) 0.16 sak 49,500.00

7,920.00

    c Pasir pasang 0.03 m3 125,000.00

4,000.00

    d Pembantu tukang 0.30 org 27,500.00

8,250.00

    e Tukang kayu 0.20 org 42,000.00

8,400.00

    Jumlah 111,070.00

    Dibulatkan 111,070.00

  3 1 M2 PASANG ATAP FIBREGLASS UKURAN 180 X 90 cm

    a Atap fibreglass 0.60 lbr 60,000.00

36,000.00

    b Paku 2 - 5 cm 0.05 kg 14,700.00

735.00

    c Pembantu tukang 0.14 org 27,500.00

3,850.00

    d Tukang kayu 0.07 org 42,000.00

2,814.00

    Jumlah 43,399.00

    Dibulatkan 43,390.00

  4 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,05 m TEBAL 4 mm

Page 82: Analisa Harga Satuan Pekerjaan Semarang

    a Asbes gelombang 0.35 lbr 63,000.00

22,050.00

    b Paku payung 0.12 kg 14,700.00

1,764.00

    c Pembantu tukang 0.14 org 27,500.00

3,850.00

    d Tukang kayu 0.07 org 42,000.00

2,940.00

    Jumlah 30,604.00

    Dibulatkan 30,600.00

  5 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,05 m TEBAL 4 mm

    a Asbes gelombang 0.42 lbr 50,000.00

21,000.00

    b Paku payung 0.12 kg 14,700.00

1,764.00

    c Pembantu tukang 0.14 org 27,500.00

3,850.00

    d Tukang kayu 0.07 org 42,000.00

2,940.00

    Jumlah 29,554.00

    Dibulatkan 29,550.00

  6 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,70 x 1,02 m TEBAL 5 mm

    a Asbes gelombang 0.44 lbr 82,000.00

36,080.00

    b Paku payung 0.12 kg 14,700.00

1,764.00

    c Pembantu tukang 0.14 org 27,500.00

3,850.00

Page 83: Analisa Harga Satuan Pekerjaan Semarang

    d Tukang kayu 0.07 org 42,000.00

2,814.00

    Jumlah 44,508.00

    Dibulatkan 44,500.00

  7 1 M2 PASANG ATAP ASBES GELOMBANG UKURAN 2,40 x 1,02 m TEBAL 5 mm

    a Asbes gelombang 0.51 lbr 82,000.00

41,820.00

    b Paku payung 0.12 kg 14,700.00

1,764.00

    c Pembantu tukang 0.14 org 27,500.00

3,850.00

    d Tukang kayu 0.07 org 42,000.00

2,814.00

    Jumlah 50,248.00

    Dibulatkan 50,240.00

  8 1 M2 PASANG ATAP ASBES GELOMBANG ( 1,50 x 1,02 m ) x 5 mm

    a Asbes gelombang 0.80 lbr 35,000.00

28,000.00

    b Paku payung 0.12 kg 14,700.00

1,764.00

    c Pembantu tukang 0.14 org 27,500.00

3,850.00

    d Tukang kayu 0.07 org 42,000.00

2,940.00

    Jumlah 36,554.00

    Dibulatkan 36,550.00

Page 84: Analisa Harga Satuan Pekerjaan Semarang

  9 1 M¹ PASANG ATAP SIRAP

    a Genteng sirap 80.00 bh 1,450.00

116,000.00

    b Paku 0.20 kg 14,700.00

2,940.00

    c Pembantu tukang 0.10 org 27,500.00

2,750.00

    d Tukang kayu 0.20 org 42,000.00

8,400.00

    Jumlah 130,090.00

    Dibulatkan 130,090.00

  10 1 M2 PASANG ATAP GENTENG BETON

    a Genteng beton 1.10 bh 62,500.00

68,750.00

    b Paku 5 - 12 cm 0.03 kg 14,700.00

441.00

    c Pembantu tukang 0.20 org 27,500.00

5,500.00

    d Tukang kayu 0.10 org 42,000.00

4,200.00

    Jumlah 78,891.00

    Dibulatkan 78,890.00

  11 1 M2 PASANG ATAP GENTENG METAL + C301

    a Genteng metal 1.02 lbr 130,000.00

132,600.00

    b Paku 5 - 12 cm 0.20 kg 14,700.00

2,940.00

    c Pembantu tukang 0.20 org

Page 85: Analisa Harga Satuan Pekerjaan Semarang

27,500.00 5,500.00

    d Tukang kayu 0.10 org 42,000.00

4,200.00

    Jumlah 145,240.00

    Dibulatkan 145,240.00

  12 1 M¹ PASANG NOK GENTENG BETON

    a Nok genteng beton 3.50 bh 16,000.00

56,000.00

    b Paku 5 - 12 cm 0.05 kg 14,700.00

735.00

    c Semen PC (abu-abu) 0.22 sak 49,500.00

10,692.00

    d Pasir pasang 0.03 m3 125,000.00

4,000.00

    e Semen warna 1.00 kg 12,700.00

12,700.00

    f Pembantu tukang 0.40 org 27,500.00

11,000.00

    g Tukang kayu 0.20 org 42,000.00

8,400.00

    Jumlah 103,527.00

    Dibulatkan 103,520.00

  13 1 M¹ PASANG NOK GENTENG METAL

    a Nok genteng metal 1.10 bh 54,000.00

59,400.00

    b Paku payung 0.05 kg 14,700.00

735.00

    c Pembantu tukang 0.25 org

Page 86: Analisa Harga Satuan Pekerjaan Semarang

27,500.00 6,875.00

    d Tukang kayu 0.15 org 42,000.00

6,300.00

    Jumlah 73,310.00

    Dibulatkan 73,310.00

  14 1 M2 PASANG ATAP SENG GELOMBANG

    a Seng gelombang 0.70 lbr 67,000.00

46,900.00

    b Paku payung 0.02 kg 14,700.00

294.00

    c Pembantu tukang 0.12 org 27,500.00

3,300.00

    d Tukang kayu 0.06 org 42,000.00

2,520.00

    Jumlah 53,014.00

    Dibulatkan 53,010.00

  15 1 M2 PASANG NOK SENG UNTUK ATAP SENG GELOMBANG

    a Seng plat BJLS 1.05 M1 32,000.00

33,600.00

    b Paku payung 0.04 kg 14,700.00

588.00

    c Pembantu tukang 0.15 org 27,500.00

4,125.00

    d Tukang kayu 0.07 org 42,000.00

2,940.00

    Jumlah 41,253.00

    Dibulatkan

Page 87: Analisa Harga Satuan Pekerjaan Semarang

41,250.00   16 1 M2 PASANG ATAP POLYCARBONATE

    a Polycarbonate 1.05 m2 200,000.00

210,000.00

    b Besi Hollow 1.50 btg 45,000.00

67,500.00

    c Alat bantu 20 % harga material 1.00 ls 42,000.00

42,000.00

    d Pembantu tukang 0.15 org 27,500.00

4,125.00

    e Tukang kayu 0.05 org 42,000.00

2,100.00

    Jumlah 325,725.00

    Dibulatkan 325,720.00

  17 1 M2 PASANG ALUMINIUM FOIL

    a Aluminium foil 1.05 m2 4,300.00

4,515.00

    b Alat bantu 20 % harga material 1.00 ls 903.00

903.00

    c Pembantu tukang 0.15 org 27,500.00

4,125.00

    d Tukang kayu 0.05 org 42,000.00

2,100.00

    Jumlah 11,643.00

    Dibulatkan 11,640.00

XI PEKERJAAN PENUTUP PLAFON

Page 88: Analisa Harga Satuan Pekerjaan Semarang

  1 1 M2 PASANG RANGKA PLAFON ( ukrn 0,50 x 1,00 ) m, KAYU BORNEO SUPER

    a Balok kayu borneo super 4 x 6 cm 0.01 m3 4,000,000.00

48,000.00

    b Paku 5 - 12 cm 0.10 kg 14,700.00

1,470.00

    c Pembantu tukang 0.15 org 27,500.00

4,125.00

    d Tukang kayu 0.25 org 42,000.00

10,500.00

    Jumlah 64,095.00

    Dibulatkan 64,000.00

  2 1 M2 PLAFON GRC ( 60 x 1,20 ) m, TEBAL 4 mm

    a Pelat GRC tebal 4 mm 1.10 lbr 45,600.00

50,160.00

    b Paku 1 cm 0.01 kg 14,700.00

147.00

    c Pembantu tukang 0.03 org 27,500.00

825.00

    d Tukang kayu 0.07 org 42,000.00

2,940.00

    Jumlah 54,072.00

    Dibulatkan 54,070.00

  3 1 M2 PLAFON ASBES ( 1,00 x 1,00 ) m, TEBAL5 mm

    a Pelat asbes tebal 5 mm 1.10 lbr 11,500.00

12,650.00

    b Paku 1 cm 0.01 kg 14,700.00

147.00

    c Pembantu tukang 0.03 org

Page 89: Analisa Harga Satuan Pekerjaan Semarang

27,500.00 825.00

    d Tukang kayu 0.07 org 42,000.00

2,940.00

    Jumlah 16,562.00

    Dibulatkan 16,560.00

  4 1 M2 PLAFON AKUSTIK ( 60 x 120 ) cm

    a Akustik 600 x 1200 x 15 mm 1.50 lbr 78,000.00

117,000.00

    b Paku 2 - 5 cm 0.05 kg 14,700.00

735.00

    c Pembantu tukang 0.06 org 27,500.00

1,650.00

    d Tukang kayu 0.10 org 42,000.00

4,200.00

    Jumlah 123,585.00

    Dibulatkan 123,580.00

  5 1 M2 PLAFON AKUSTIK ( 60 x 120 ) cm + RANGKA ALUMUNIUM

    a Profil alluminium "T" 3.60 M¹ 26,000.00

93,600.00

    b Kawat seng polos 0.15 kg 15,000.00

2,250.00

    c Ramset / dina bolt 1.00 bh 2,400.00

2,400.00

    d Akustik 600 x 1200 x 15 mm 1.50 lbr 78,000.00

117,000.00

    e Pembantu tukang 0.15 org 27,500.00

4,125.00

    f Tukang kayu 0.20 org

Page 90: Analisa Harga Satuan Pekerjaan Semarang

42,000.00 8,400.00

    Jumlah 227,775.00

    Dibulatkan 227,770.00

  6 1 M¹ LIST PLAFON PROFIL KAYU

    a List profil kayu 1.10 M¹ 12,500.00

13,750.00

    b Paku 2 cm 0.01 kg 14,700.00

147.00

    c Pembantu tukang 0.05 org 27,500.00

1,375.00

    d Tukang kayu 0.05 org 42,000.00

2,100.00

    Jumlah 17,372.00

    Dibulatkan 17,370.00

  7 1 M¹ LIST PLAFON KAYU 1/4

    a List kayu 1/4 1.10 M¹ 5,000.00

5,500.00

    b Paku 2 cm 0.01 kg 14,700.00

147.00

    c Pembantu tukang 0.05 org 27,500.00

1,375.00

    d Tukang kayu 0.05 org 42,000.00

2,100.00

    Jumlah 9,122.00

    Dibulatkan 9,120.00

  8 1 M2 PLAFON TRIPLEK 4 mm + RANGKA KAYU BORNEO SUPER

Page 91: Analisa Harga Satuan Pekerjaan Semarang

    a Balok kayu borneo super 0.02 m3 4,000,000.00

92,000.00

    b Paku 1- 12 cm 0.06 kg 14,700.00

882.00

    c Triplek 120 cm x 240 cm x 0,4 cm 0.39 lbr 36,000.00

14,040.00

    d Pembantu tukang 0.27 org 27,500.00

7,425.00

    e Tukang kayu 0.40 org 42,000.00

16,800.00

    Jumlah 131,147.00

    Dibulatkan 131,140.00

  9 1 M2 PLAFON TEAKWOOD 4 mm + RANGKA KAYU BORNEO SUPER

    a Balok kayu borneo super 0.02 m3 4,000,000.00

92,000.00

    b Paku 1 - 12 cm 0.06 kg 14,700.00

882.00

    cTeakwood 120 cm x 240 cm x 0,4 cm

0.39 lbr 85,000.00

33,150.00

    d Pembantu tukang 0.27 org 27,500.00

7,425.00

    e Tukang kayu 0.40 org 42,000.00

16,800.00

    Jumlah 150,257.00

Dibulatkan 150,250.00

  10 1 M2 PLAFON PAPAN 10 cm, TEBAL 1 cm + RANGKA KAYU BORNEO SUPER

    a Balok kayu borneo super 0.02 m3 4,000,000.00

92,000.00

Page 92: Analisa Harga Satuan Pekerjaan Semarang

    b Paku 2 - 12 cm 0.20 kg 14,700.00

2,940.00

    c Papan kayu kamper 0.02 m3 5,350,000.00

107,000.00

    d Pembantu tukang 0.35 org 27,500.00

9,625.00

    e Tukang kayu 0.50 org 42,000.00

21,000.00

    Jumlah 232,565.00

Dibulatkan 232,560.00

  11 1 M2 PLAFON GYPSUM BOARD, TEBAL 9 mm + RANGKA BESI HOLLOW

    a Hollow 4/4 Zincromate 0.42 btg 45,000.00

18,675.00

    b Hollow 2/4 Zincromate 0.15 btg 32,000.00

4,800.00

    c Gypsum board ( 120 x 240 x 9 ) mm 0.36 lbr 59,000.00

21,476.00

    d Paku sekrup 25.00 bh 700.00

17,500.00

    e Ramset / dina bolt 4.00 bh 2,400.00

9,600.00

    f Cotton plaster 0.07 bh 56,000.00

4,032.00

    g Compoun 0.13 kg 28,500.00

3,562.50

    h Pembantu tukang 0.10 org 27,500.00

2,750.00

    i Tukang kayu 0.05 org 42,000.00

2,100.00

    Jumlah 84,495.50

Page 93: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 84,490.00

               XII PEKERJAAN SANITAIR   1 MEMASANG 1 BH KLOSET DUDUK/MONOBLOK

    a Kloset duduk/monoblok 1.00 bh 2,280,000.00

2,280,000.00

    b Perlengkapan (10% hrg kloset)     228,000.00

228,000.00

    c Pembantu tukang 3.30 org 27,500.00

90,750.00

    d Tukang batu 1.10 org 42,000.00

46,200.00

    Jumlah 2,644,950.00

    Dibulatkan 2,644,950.00

  2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN

    a Kloset jongkok porselen 1.00 bh 140,000.00

140,000.00

    b Semen PC (abu-abu) 0.12 sak 49,500.00

5,940.00

    c Pasir pasang 0.01 m3 125,000.00

1,250.00

    d Pembantu tukang 1.00 org 27,500.00

27,500.00

    e Tukang batu 1.50 org 42,000.00

63,000.00

    Jumlah 237,690.00

    Dibulatkan 237,690.00

Page 94: Analisa Harga Satuan Pekerjaan Semarang

  3 MEMASANG 1 BUAH URINOIR

    a Urinoir 1.00 bh 375,000.00

375,000.00

    b Perlengkapan ( 30% hrg urinoir )     112,500.00

112,500.00

    c Semen PC (abu-abu) 0.12 sak 49,500.00

5,940.00

    d Pasir pasang 0.01 m3 125,000.00

1,250.00

    e Pembantu tukang 1.00 org 27,500.00

27,500.00

    f Tukang batu 1.00 org 42,000.00

42,000.00

    Jumlah 564,190.00

    Dibulatkan 564,190.00

  4 MEMASANG 1 BUAH WASTAFEL DINDING

    a Wastafel 1.00 bh 230,000.00

230,000.00

    b Perlengkapan ( 12% hrg kloset )     27,600.00

27,600.00

    c Semen PC ( abu-abu ) 0.12 sak 49,500.00

5,940.00

    d Pasir pasang 0.01 m3 125,000.00

1,250.00

    e Pembantu tukang 1.20 org 27,500.00

33,000.00

    f Tukang batu 1.45 org 42,000.00

60,900.00

    Jumlah 358,690.00

Page 95: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 358,690.00

  5 MEMASANG 1 BUAH WASTAFEL KAKI

    a Wastafel 1.00 bh 248,000.00

248,000.00

    b Perlengkapan ( 12% hrg kloset )     29,760.00

29,760.00

    c Semen PC ( abu-abu ) 0.12 sak 49,500.00

5,940.00

    d Pasir pasang 0.01 m3 125,000.00

1,250.00

    e Pembantu tukang 1.20 org 27,500.00

33,000.00

    f Tukang batu 1.45 org 42,000.00

60,900.00

    Jumlah 378,850.00

    Dibulatkan 378,850.00

  6 MEMASANG 1 BH SHOWER DINDING

    a Shower dinding 1.00 bh 130,000.00

130,000.00

    b Pembantu tukang 0.01 org 27,500.00

275.00

    c Tukang batu 0.10 org 42,000.00

4,200.00

    Jumlah 134,475.00

    Dibulatkan 134,470.00

  7 MEMASANG BAK MANDI FIBERGLASS UKURAN SEDANG    a Bak fibreglass 1.00 bh

Page 96: Analisa Harga Satuan Pekerjaan Semarang

150,000.00 150,000.00

    b Perlengkapan ( 20% hrg bak )     27,000.00

27,000.00

    c Pembantu tukang 1.80 org 27,500.00

49,500.00

    d Tukang batu 2.70 org 42,000.00

113,400.00

    Jumlah 339,900.00

    Dibulatkan 339,900.00

  8 MEMASANG BAK KONTROL PASANGAN BATU BATA UKURAN 30 X 30 CM, TINGGI 35 CM

    a Batu bata 0.15 m3 325.00

48.75

    b Semen PC (abu-abu) 0.88 sak 49,500.00

43,560.00

    c Pasir pasang 0.07 m3 125,000.00

8,750.00

    d Batu kerikil 0.07 m3 78,000.00

5,460.00

    e Besi beton 1.60 kg 10,000.00

16,000.00

    f Pasir beton 0.06 m3 140,000.00

8,400.00

    g Pembantu tukang 3.20 org 27,500.00

88,000.00

    h Tukang batu 1.02 org 42,000.00

42,840.00

    Jumlah 213,058.75

    Dibulatkan 213,050.00

Page 97: Analisa Harga Satuan Pekerjaan Semarang

  9 MEMASANG KITCHEN ZINK/BAK CUCI PIRING STAINLESS STEEL

    a Bak cuci stainless steel 1.00 bh 173,000.00

173,000.00

    b Water Drain + Asesories 1.00 Set 70,000.00

70,000.00

    c Pembantu tukang 0.03 org 27,500.00

825.00

    d Tukang batu 0.30 org 42,000.00

12,600.00

    Jumlah 256,425.00

    Dibulatkan 256,420.00

  10 MEMASANG 1 BH KRAN DIAMETER 3/4 " ATAU 1/2 "

    a Kran air 1.00 bh 55,000.00

55,000.00

    b Perlengkapan ( 2% hrg kran ) 1.00 ls 1,100.00

1,100.00

    c Pembantu tukang 0.01 org 27,500.00

275.00

    d Tukang batu 0.10 org 42,000.00

4,200.00

    Jumlah 60,575.00

    Dibulatkan 60,570.00

  11 MEMASANG 1 BH KRAN AIR ANGSA

    a Kran air angsa 1.00 bh 155,000.00

155,000.00

    b Perlengkapan ( 2% hrg kran ) 1.00 ls 3,100.00

3,100.00

    c Pembantu tukang 0.01 org

Page 98: Analisa Harga Satuan Pekerjaan Semarang

27,500.00 275.00

    d Tukang batu 0.10 org 42,000.00

4,200.00

    Jumlah 162,575.00

    Dibulatkan 162,570.00

  12 MEMASANG 1 BH FLOOR DRAIN

    a Floor drain 1.00 bh 59,500.00

59,500.00

    b Pembantu tukang 0.01 org 27,500.00

275.00

    c Tukang batu 0.10 org 42,000.00

4,200.00

    Jumlah 63,975.00

    Dibulatkan 63,970.00

  13 MEMASANG 1 BH TEMPAT SABUN

    a Tempat Sabun 1.00 bh 30,000.00

30,000.00

    b Pembantu tukang 0.01 org 27,500.00

275.00

    c Tukang batu 0.10 org 42,000.00

4,200.00

    Jumlah 34,475.00

    Dibulatkan 34,470.00

                 XIIIPEKERJAAN PERPIPAAN DAN POMPA

Page 99: Analisa Harga Satuan Pekerjaan Semarang

  1 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ½"

    a Pipa galvanis dia 1/2" 1.10 M¹ 13,400.00

14,740.00

    b Perlengkapan ( 30% harga pipa )     4,020.00

4,020.00

    c Pembantu tukang 0.05 org 27,500.00

1,485.00

    d Tukang pipa 0.09 org 42,000.00

3,780.00

    Jumlah 24,025.00

    Dibulatkan 24,020.00

  2 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER ¾"

    a Pipa galvanis 1.10 M¹ 19,500.00

21,450.00

    b Perlengkapan ( 30% harga pipa )     5,850.00

5,850.00

    c Pembantu tukang 0.05 org 27,500.00

1,485.00

    d Tukang pipa 0.09 org 42,000.00

3,780.00

    Jumlah 32,565.00

    Dibulatkan 32,560.00

  3 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1"

    a Pipa galvanis 1.10 M¹ 21,250.00

23,375.00

    b Perlengkapan ( 30% harga pipa )     6,375.00

6,375.00

    c Pembantu tukang 0.05 org

Page 100: Analisa Harga Satuan Pekerjaan Semarang

27,500.00 1,485.00

    d Tukang pipa 0.09 org 42,000.00

3,780.00

    Jumlah 35,015.00

    Dibulatkan 35,010.00

  4 MEMASANG 1 M¹ PIPA GALVANIS DIAMETER 1½"

    a Pipa galvanis 1.10 M¹ 31,700.00

34,870.00

    b Perlengkapan ( 30% harga pipa )     9,510.00

9,510.00

    c Pembantu tukang 0.11 org 27,500.00

2,970.00

    d Tukang pipa 0.18 org 42,000.00

7,560.00

    Jumlah 54,910.00

    Dibulatkan 54,910.00

  5 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 3"

    a Pipa PVC type D 1.10 M¹ 6,400,000.00

7,040,000.00

    b Perlengkapan ( 30% harga pipa )     1,920,000.00

1,920,000.00

    c Pembantu tukang 0.10 org 27,500.00

2,750.00

    d Tukang pipa 0.18 org 42,000.00

7,560.00

    Jumlah 8,970,310.00

    Dibulatkan

Page 101: Analisa Harga Satuan Pekerjaan Semarang

8,970,310.00   6 MEMASANG 1 M¹ PIPA PVC TYPE D DIAMETER 4"

    a Pipa PVC type D 1.10 M¹ 8,500.00

9,350.00

    b Perlengkapan ( 30% harga pipa )     2,550.00

2,550.00

    c Pembantu tukang 0.13 org 27,500.00

3,575.00

    d Tukang pipa 0.22 org 42,000.00

9,240.00

    Jumlah 24,715.00

    Dibulatkan 24,710.00

  7 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ½"

    a Pipa PVC 1.10 M¹ 5,000.00

5,500.00

    b Perlengkapan ( 30% harga pipa )     1,500.00

1,500.00

    c Pembantu tukang 0.04 org 27,500.00

990.00

    d Tukang pipa 0.06 org 42,000.00

2,520.00

    Jumlah 10,510.00

    Dibulatkan 10,510.00

  8 MEMASANG 1 M¹ PVC TIPE AW DIAMETER ¾"

    a Pipa PVC 1.10 M¹ 5,625.00

6,187.50

    b Perlengkapan ( 30% harga pipa )     1,687.50

1,687.50

Page 102: Analisa Harga Satuan Pekerjaan Semarang

    c Pembantu tukang 0.03 org 27,500.00

825.00

    d Tukang pipa 0.06 org 42,000.00

2,520.00

    Jumlah 11,220.00

Dibulatkan 11,220.00

  9 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 1"

    a Pipa PVC 1.10 M¹ 7,000.00

7,700.00

    b Perlengkapan ( 30% harga pipa )     2,100.00

2,100.00

    c Pembantu tukang 0.04 org 27,500.00

990.00

    d Tukang pipa 0.06 org 42,000.00

2,520.00

    Jumlah 13,310.00

    Dibulatkan 13,310.00

  10 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 2"

    a Pipa PVC 1.10 M¹ 9,500.00

10,450.00

    b Perlengkapan ( 30% harga pipa )     2,850.00

2,850.00

    c Pembantu tukang 0.05 org 27,500.00

1,485.00

    d Tukang pipa 0.09 org 42,000.00

3,780.00

    Jumlah 18,565.00

Page 103: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 18,560.00

  11 MEMASANG 1 M¹ PVC TIPE AW DIAMETER 4"

    a Pipa PVC 1.10 M¹ 28,000.00

30,800.00

    b Perlengkapan ( 30% harga pipa )     8,400.00

8,400.00

    c Pembantu tukang 0.08 org 27,500.00

2,227.50

    d Tukang pipa 0.14 org 42,000.00

5,670.00

      Jumlah       47,097.50

    Dibulatkan   47,090.00

  12 MEMBUAT 1 BH SEPTICTANK PASANGAN BATU BATA DAN REMBESAN

  a Galian tanah Septictank & rembesan 7.5m3 20,950.00

157,125.00

  b Pasir urug 0.21m3 70,000.00

14,700.00

  c Lantai kerja 2.25 m3 480,100.00

1,080,225.00

  d Pasang bata 1 Pc : 2 Psr 15.00 m2 55,100.00

826,500.00

  e Pelat beton penutup dan balok 0.30 m3 4,071,500.00

1,221,450.00

  fPipa PVC 4 inci AW & perlengkapannya

5.40 M1 28,000.00

151,200.00

  g Plesteran 1 Pc : 3 Psr 30.00 m2 20,700.00

621,000.00

  h Pasangan ijuk 5.00 IKAT 7,000.00

35,000.00

Page 104: Analisa Harga Satuan Pekerjaan Semarang

  i Urugan kerikil 3,5 cm 1.05 m3 103,400.00

108,570.00

  J Pipa PVC 4 inci AW dilobang 9.00 M1 28,000.00

252,000.00

  q Urugan kembali 1.13 m3 5,800.00

6,554.00

  r Pembantu tukang 4.00 org 27,500.00

110,000.00

  s Tukang batu 3.00 org 42,000.00

126,000.00

  Jumlah 4,710,324.00

  Dibulatkan 4,710,320.00

  13 MEMASANG 1 BH POMPA AIR

    a Pompa Air 100 Watt 1.00 bh 780,000.00

780,000.00

    b Perlengkapan ( 25% harga pompa )     195,000.00

195,000.00

    c Pembantu tukang 0.08 org 27,500.00

2,227.50

    d Tukang Pipa 0.14 org 42,000.00

5,670.00

    Jumlah 982,897.50

    Dibulatkan 982,890.00

XIV PEKERJAAN PENUTUP BESI DAN BAJA   1 1 KG PASANG RANGKA ATAP BAJA            a Besi profil WF 1.10 kg

Page 105: Analisa Harga Satuan Pekerjaan Semarang

11,500.00 12,650.00

    b Meni besi 0.08 kg 22,000.00

1,760.00

    c Peralatan las ( 5 % material ) 1.00 ls 632.50

632.50

    d Elektroda 0.20 ls 12,000.00

2,400.00

    e Tukang besi 0.04 org 42,000.00

1,680.00

    f Pembantu tukang 0.06 org 27,500.00

1,650.00

    Jumlah 20,772.50

    Dibulatkan 20,770.00

  2 1 KG PASANG RANGKA ATAP BESI SIKU

    a Besi siku 1.10 kg 11,500.00

12,650.00

    b Meni besi 0.10 kg 22,000.00

2,200.00

    c Peralatan las ( 5 % material ) 1.00 ls 632.50

632.50

    d Elektroda 0.15 ls 12,000.00

1,800.00

    e Baud 0.20 kg 10,000.00

2,000.00

    f Tukang besi 0.04 org 42,000.00

1,680.00

    g Pembantu tukang 0.06 org 27,500.00

1,650.00

    Jumlah 22,612.50

Page 106: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 22,610.00

  3 1 KG PASANG GORDING BESI C

    a Besi C 1.10 kg 11,000.00

12,100.00

    b Meni besi 0.10 kg 15,000.00

1,500.00

    c Peralatan las ( 5 % material ) 1.00 ls 605.00

605.00

    d Elektroda 0.15 ls 12,000.00

1,800.00

    e Baud 0.20 kg 10,000.00

2,000.00

    f Tukang besi 0.04 org 42,000.00

1,680.00

    g Pembantu tukang 0.06 org 27,500.00

1,650.00

    Jumlah 21,335.00

    Dibulatkan 21,330.00

  4 1 m2 Pasang Pintu Rolling Door besi

    a Rolling door besi 1.00 m2 230,000.00

230,000.00

    b Tukang besi 1.50 org 42,000.00

63,000.00

    c Pembantu tukang 1.05 org 27,500.00

28,875.00

    Jumlah 321,875.00

    Dibulatkan 321,870.00

Page 107: Analisa Harga Satuan Pekerjaan Semarang

  5 1 bh Pasang Pintu besi ukuran 0,8 x 2 m

    a Pintu besi jadi 1.00 bh 375,000.00

375,000.00

    b Tukang besi 1.05 org 42,000.00

44,100.00

    c Pembantu tukang 1.05 org 27,500.00

28,875.00

    Jumlah 447,975.00

    Dibulatkan 447,970.00

  6 1 M2 PASANG TERALIS BESI

    a Besi strip 2 mm x 3 cm 11.50 M¹ 11,000.00

126,500.00

    b Tukang las 1.20 org 42,000.00

50,400.00

    c Pembantu tukang 1.20 org 27,500.00

33,000.00

    Jumlah 209,900.00

    Dibulatkan 209,900.00

  7 1 M2 PASANG KAWAT HARMONIKA

    a Kawat harmonika 1.10 m2 12,000.00

13,200.00

    b Paku 2 - 5 cm 0.02 kg 14,700.00

294.00

    c Papan kayu kamper medan 0.00 m3 4,275,000.00

7,695.00

    d Pembantu tukang 0.10 org 27,500.00

2,750.00

    e Tukang kayu 0.10 org

Page 108: Analisa Harga Satuan Pekerjaan Semarang

42,000.00 4,200.00

    Jumlah 28,139.00

    Dibulatkan 28,130.00

  8 1 M1 PASANG TALANG DATAR, SENG PLAT BJLS

    a Seng plat BJLS 1.00 M1 32,000.00

32,000.00

    b Paku 2 - 5 cm 0.02 kg 14,700.00

220.50

    c Papan kayu borneo super 0.01 m3 4,800,000.00

46,080.00

    d Flincote / meni besi 0.25 kg 18,000.00

4,500.00

    e Pembantu tukang 0.15 org 27,500.00

4,125.00

    f Tukang kayu 0.40 org 42,000.00

16,800.00

    Jumlah 103,725.50

    Dibulatkan 103,720.00

  9 1 M1 PASANG TALANG MIRING, SENG PLAT BJLS

    a Seng plat BJLS 0.50 M1 32,000.00

16,000.00

    b Paku 2 - 5 cm 0.02 kg 14,700.00

220.50

    c Papan kayu borneo super 0.02 m3 4,800,000.00

91,200.00

    d Flincote / meni besi 0.30 kg 18,000.00

5,400.00

    e Pembantu tukang 0.04 org

Page 109: Analisa Harga Satuan Pekerjaan Semarang

27,500.00 1,100.00

    f Tukang kayu 0.40 org 42,000.00

16,800.00

    Jumlah 130,720.50

    Dibulatkan 130,720.00

XV PEKERJAAN ALUMINIUM  1 1 M2PASANG PINTU ROLLING DOOR ALUMINIUM

    a Rolling door aluminium 1.00 m2 230,000.00

230,000.00

    b Tukang besi konstruksi 1.50 org 42,000.00

63,000.00

    c Pembantu tukang 1.05 org 27,500.00

28,875.00

    Jumlah 321,875.00

    Dibulatkan 321,870.00

  2 1 M2 PASANG PINTU ALUMINIUM PABRIKAN

    a Pintu alluminium 1.00 bh 375,000.00

375,000.00

    b Tukang batu 1.05 org 42,000.00

44,100.00

    c Pembantu tukang 1.05 org 27,500.00

28,875.00

    Jumlah 447,975.00

    Dibulatkan 447,970.00

Page 110: Analisa Harga Satuan Pekerjaan Semarang

  3 1 UNIT KUSEN JENDELA ALUMINIUM 2 LUBANG DGN 2 DAUN JENDELA (UKURAN 1,6 X 1,5 M)

    aProfil aluminium 4" natural (+ spare 20 %)

9.24 M1 80,000.00

739,200.00

    bProfil daun jendela alm.( + spare 20%)

11.04 M1 80,000.00

883,200.00

    c Kaca polos 3 mm 2.40 m2 52,000.00

124,800.00

    d Engsel jendela 4.00 ps 20,000.00

80,000.00

    e Grendel jendela 2.00 bh 19,100.00

38,200.00

    f Kait angin 2.00 bh 15,000.00

30,000.00

    g Aksesoris ( 6 % harga bahan) 1.00 ls 104,832.00

104,832.00

    hUpah pembuatan profil ( 20 % bahan )

1.00 ls 147,840.00

147,840.00

    iUpah pembuatan daun jendela (20 % bahan)

1.00 ls 176,640.00

176,640.00

    Jumlah 2,324,712.00

    Dibulatkan 2,324,710.00

  41 UNIT KUSEN JENDELA ALUMINIUM 3 LUBANG DGN 2 DAUN JENDELA DAN 1 KACA MATI (UKURAN 2 X 1,5 M)

    aProfil aluminium 4" natural (+ spare 20 %)

12.00 M1 80,000.00

960,000.00

    bProfil daun jendela alm.( + spare 20%)

11.04 M1 80,000.00

883,200.00

    c Kaca polos 3 mm 3.00 m2 52,000.00

156,000.00

    d Engsel jendela 4.00 ps

Page 111: Analisa Harga Satuan Pekerjaan Semarang

20,000.00 80,000.00

    e Grendel jendela 2.00 bh 19,100.00

38,200.00

    f Kait angin 2.00 bh 15,000.00

30,000.00

    g Aksesoris ( 6 % harga bahan ) 1.00 ls 119,952.00

119,952.00

    hUpah pembuatan profil ( 20 % bahan )

1.00 ls 192,000.00

192,000.00

    iUpah pembuatan daun jendela (20 % bahan)

1.00 ls 176,640.00

176,640.00

    Jumlah 2,267,352.00

    Dibulatkan 2,267,350.00

  51 UNIT KUSEN PINTU JENDELA GENDONG ALUMINIUM DGN 2 JNDL DAN 1 PNT TEAKWOOD (UKR 2,2 X 2,7 M)

    aProfil aluminium 4" natural (+ spare 20 %)

17.04 M1 80,000.00

1,363,200.00

    bProfil daun jendela alm.( + spare 20%)

14.88 M1 80,000.00

1,190,400.00

    c Kaca polos 3 mm 3.96 m2 52,000.00

205,920.00

    d Daun pintu teakwood 1.80 m2 279,700.00

503,460.00

    e Engsel jendela 4.00 ps 20,000.00

80,000.00

    f Grendel jendela 2.00 bh 19,100.00

38,200.00

    g Kait angin 4.00 bh 15,000.00

60,000.00

    h Engsel pintu 3.00 ps

Page 112: Analisa Harga Satuan Pekerjaan Semarang

22,000.00 66,000.00

    i Grendel pintu 1.00 bh 31,000.00

31,000.00

    j Kunci tanam 1.00 bh 13,000.00

13,000.00

    k Aksesoris ( 6 % harga bahan ) 1.00 ls 137,976.00

137,976.00

    lUpah pembuatan profil ( 20 % bahan )

1.00 ls 16,000.00

16,000.00

    mUpah pembuatan daun jendela (20 % bahan)

1.00 ls 7,640.00

7,640.00

    Jumlah 3,712,796.00

    Dibulatkan 3,712,790.00

  6 1 UNIT KUSEN PINTU ALUMINIUM UKR 0.9 X 2,7 M

    aProfil aluminium 4" natural (+ spare 20 %)

7.56 M1 80,000.00

604,800.00

    b Kaca polos 3 mm untuk bovenlight 0.45 m2 52,000.00

23,400.00

    c Daun pintu tekwood 1.68 m2 279,700.00

469,896.00

    d Engsel pintu 3.00 ps 22,000.00

66,000.00

    e Grendel pintu 1.00 bh 31,000.00

31,000.00

    f Kunci tanam 1.00 bh 13,000.00

13,000.00

    g Aksesoris ( 6 % ) 1.00 ls 37,692.00

37,692.00

    hUpah pembuatan profil ( 20 % bahan )

1.00 ls 120,960.00

120,960.00

Page 113: Analisa Harga Satuan Pekerjaan Semarang

    Jumlah 1,366,748.00

    Dibulatkan 1,366,740.00

  7 1 BH BOVENLIGHT ALMUNIUM DENGAN KISI-KISI ALMUNIUM PLAT (UKURAN 0,5 X 1 M)

    aProfil Aluminium 4" natural + upah 20%

3.60 M1 52,000.00

187,200.00

    b Plat Aluminium untuk Jalusi 5.00 M1 17,000.00

85,000.00

    c Aksesoris ( 6 % ) 1.00 ls 11,232.00

11,232.00

    dUpah pembuatan profil ( 20 % bahan )

1.00 ls 24,192.00

24,192.00

    Jumlah 307,624.00

    Dibulatkan 307,620.00

  8 1 BH BOVENLIGHT ALMUNIUM UKURAN 0,5 X 1 M DENGAN BAGIAN DALAM KACA

    aProfil Aluminium 4" natural + upah 20%

3.60 M1 52,000.00

187,200.00

    b Kaca Polos 3 mm 0.50 m2 52,000.00

26,000.00

    c Aksesoris ( 6 % ) 1.00 ls 11,232.00

11,232.00

    dUpah pembuatan profil ( 20 % bahan )

1.00 ls 4,838.40

4,838.40

    Jumlah 229,270.40

    Dibulatkan 229,270.00

 

Page 114: Analisa Harga Satuan Pekerjaan Semarang

XVI PEKERJAAN KACA & PENGGANTUNG  1 1 BUAH PASANG KUNCI TANAM BESAR

    a Kunci tanam besar 1.00 bh 125,000.00

125,000.00

    b Pembantu tukang 0.06 org 27,500.00

1,650.00

    c Tukang kayu 0.60 org 42,000.00

25,200.00

    Jumlah 151,850.00

    Dibulatkan 151,850.00

  2 1 BUAH PASANG KUNCI TANAM SEDANG

    a Kunci tanam sedang 1.00 bh 55,000.00

55,000.00

    b Pembantu tukang 0.01 org 27,500.00

275.00

    c Tukang kayu 0.50 org 42,000.00

21,000.00

    Jumlah 76,275.00

    Dibulatkan 76,270.00

  3 1 BUAH PASANG KUNCI BULAT PUTAR KAMAR MANDI

    a Kunci bulat putar kamar mandi 1.00 bh 50,000.00

50,000.00

    b Pembantu tukang 0.01 org 27,500.00

137.50

    c Tukang kayu 0.50 org 42,000.00

21,000.00

    Jumlah 71,137.50

Page 115: Analisa Harga Satuan Pekerjaan Semarang

    Dibulatkan 71,130.00

  4 1 BUAH PASANG ENGSEL PINTU

    a Engsel pintu 1.00 bh 22,000.00

22,000.00

    b Pembantu tukang 0.02 org 27,500.00

412.50

    c Tukang kayu 0.15 org 42,000.00

6,300.00

    Jumlah 28,712.50

    Dibulatkan 28,710.00

  5 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU

    a Engsel jendela 1.00 bh 20,000.00

20,000.00

    b Pembantu tukang 0.01 org 27,500.00

275.00

    c Tukang kayu 0.10 org 42,000.00

4,200.00

    Jumlah 24,475.00

    Dibulatkan 24,470.00

  6 1 BUAH PASANG KAIT ANGIN

    a Kait angin 1.00 bh 15,000.00

15,000.00

    b Pembantu tukang 0.02 org 27,500.00

412.50

    c Tukang kayu 0.15 org 42,000.00

6,300.00

    Jumlah

Page 116: Analisa Harga Satuan Pekerjaan Semarang

21,712.50

    Dibulatkan 21,710.00

  7 1 BUAH PASANG DOOR CLOSER

    a Door closer 1.00 bh 350,000.00

350,000.00

    b Pembantu tukang 0.05 org 27,500.00

1,375.00

    c Tukang kayu 0.50 org 42,000.00

21,000.00

    Jumlah 372,375.00

    Dibulatkan 372,370.00

  8 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER

    a Door holder 1.00 bh 50,000.00

50,000.00

    b Pembantu tukang 0.05 org 27,500.00

1,375.00

    c Tukang kayu 0.50 org 42,000.00

21,000.00

    Jumlah 72,375.00

    Dibulatkan 72,370.00

  9 1 BUAH PASANG PENAHAN PINTU / DOOR STOPER

    a Door stoper 1.00 bh 60,000.00

60,000.00

    b Pembantu tukang 0.05 org 27,500.00

1,375.00

    c Tukang kayu 0.50 org 42,000.00

21,000.00

Page 117: Analisa Harga Satuan Pekerjaan Semarang

    Jumlah 82,375.00

    Dibulatkan 82,370.00

  10 1 BUAH PASANG GRENDEL/SLOOT PINTU

    a Grendel / sloot pintu 1.00 bh 31,000.00

31,000.00

    b Pembantu tukang 0.05 org 27,500.00

1,375.00

    c Tukang kayu 0.50 org 42,000.00

21,000.00

    Jumlah 53,375.00

    Dibulatkan 53,370.00

  11 1 BUAH PASANG GRENDEL/SLOOT JENDELA

    a Grendel / sloot jendela 1.00 bh 19,100.00

19,100.00

    b Pembantu tukang 0.05 org 27,500.00

1,375.00

    c Tukang kayu 0.50 org 42,000.00

21,000.00

    Jumlah 41,475.00

    Dibulatkan 41,470.00

  12 1 BUAH PASANG TARIKAN JENDELA

    a Tarikan jendela 1.00 bh 15,000.00

15,000.00

    b Pembantu tukang 0.05 org 27,500.00

1,375.00

    c Tukang kayu 0.50 org

Page 118: Analisa Harga Satuan Pekerjaan Semarang

42,000.00 21,000.00

    Jumlah 37,375.00

    Dibulatkan 37,370.00

  13 1 M2 PASANG KACA POLOS, TEBAL 3 MM

    a Kaca polos 1.10 m2 52,000.00

57,200.00

    b Pembantu tukang 0.02 org 27,500.00

412.50

    c Tukang kayu 0.15 org 42,000.00

6,300.00

    Jumlah 63,912.50

    Dibulatkan 63,910.00

  14 1 M2 PASANG KACA POLOS, TEBAL 5 MM

    a Kaca polos 1.10 m2 63,000.00

69,300.00

    b Pembantu tukang 0.02 org 27,500.00

412.50

    c Tukang kayu 0.15 org 42,000.00

6,300.00

    Jumlah 76,012.50

    Dibulatkan 76,010.00

  15 1 M2 PASANG KACA RAY BAND, TEBAL 5 MM

    a Kaca 1.10 m2 125,000.00

137,500.00

    b Pembantu tukang 0.02 org 27,500.00

412.50

Page 119: Analisa Harga Satuan Pekerjaan Semarang

    c Tukang kayu 0.15 org 42,000.00

6,300.00

    Jumlah 144,212.50

    Dibulatkan 144,210.00

XVII PEKERJAAN PENGECATAN  1 1 M2 MENGIKIS / MENGEROK / MENGELUPAS PERMUKAAN CAT TEMBOK LAMA

    a Soda api 0.05 kg 42,000.00

2,100.00

    b Pembantu tukang 0.05 org 27,500.00

1,375.00

    c Tukang cat 0.02 org 42,000.00

840.00

    Jumlah 4,315.00     Dibulatkan 4,310.00   2 1 M2 MENDEMPUL DAN MENGGOSOK KAYU

    a Dempul jadi 0.10 kg 22,000.00

2,200.00

    b Minyak cat 0.03 kg 17,500.00

525.00

    c Ampelas kasar 0.30 lbr 32,000.00

9,600.00

    d Pembantu tukang 0.04 org 27,500.00

1,100.00

  e Tukang cat 0.05 org 42,000.00

2,100.00

  Jumlah 15,525.00     Dibulatkan 15,520.00

Page 120: Analisa Harga Satuan Pekerjaan Semarang

  3 1 M2 PENGECATAN KAYU LAMA

    a Cat meni 0.25 kg 15,000.00

3,750.00

    b Plamir 0.15 kg 12,000.00

1,800.00

    c Ampelas 1.00 lbr 3,200.00

3,200.00

    d Cat dasar 0.15 kg 36,000.00

5,400.00

    e Cat penutup kwalitas baik 0.60 kg 37,000.00

22,200.00

    f Pembantu tukang 0.05 org 27,500.00

1,375.00

    g Tukang cat 0.15 org 42,000.00

6,300.00

    Jumlah 44,025.00     Dibulatkan 44,020.00   4 1 M2 PENGECATAN KAYU BARU

    a Cat meni 0.50 kg 15,000.00

7,500.00

    b Plamir 0.15 kg 12,000.00

1,800.00

    c Ampelas 1.00 lbr 3,200.00

3,200.00

    d Cat dasar 0.15 kg 36,000.00

5,400.00

    e Cat penutup kwalitas baik 0.35 kg 37,000.00

12,950.00

    f Pembantu tukang 0.05 org 27,500.00

1,375.00

    g Tukang cat 0.15 org 42,000.00

6,300.00

Page 121: Analisa Harga Satuan Pekerjaan Semarang

    Jumlah 38,525.00     Dibulatkan 38,520.00   5 1 M2 PENGECATAN KAYU DENGAN POLITUR

    a Politur 0.15 Ltr 29,000.00

4,350.00

    b Dempul jadi 0.25 kg 22,000.00

5,500.00

    c Ampelas 2.00 lbr 3,200.00

6,400.00

    d Pembantu tukang 0.05 org 27,500.00

1,375.00

    e Tukang cat 0.15 org 42,000.00

6,300.00

    Jumlah 23,925.00     Dibulatkan 23,920.00   6 1 M2 PENGECATAN KAYU DENGAN MELAMIK

    a Melamik 0.15 Ltr 30,000.00

4,500.00

    b Dempul jadi 0.25 kg 22,000.00

5,500.00

    c Ampelas 2.00 lbr 3,200.00

6,400.00

    d Pembantu tukang 0.05 org 27,500.00

1,375.00

    e Tukang cat 0.15 org 42,000.00

6,300.00

    Jumlah 24,075.00     Dibulatkan 24,070.00   7 1 M2 PENGECATAN KAYU DENGAN CAT RESIDU/TER

    a Residu atau ter 0.35 Ltr 3,000.00

1,050.00

    b Pembantu tukang 0.15 org 4,125.00

Page 122: Analisa Harga Satuan Pekerjaan Semarang

27,500.00

    c Tukang cat 0.02 org 42,000.00

840.00

    Jumlah 6,015.00     Dibulatkan 6,010.00   8 1 M2 PENGECATAN TEMBOK/PLAFON BARU KWALITAS SEDANG

    a Plamir 0.10 kg 9,000.00

900.00

    b Rol cat 0.01 bh 26,000.00

260.00

    c Cat penutup kwalitas sedang 0.45 kg 16,000.00

7,200.00

    d Steger (perancah kerja) 0.01 Ls 60,000.00

600.00

    e Ampelas 0.50 lbr 3,200.00

1,600.00

    f Pembantu tukang 0.06 org 27,500.00

1,650.00

    g Tukang cat 0.20 org 42,000.00

8,400.00

    Jumlah 20,610.00     Dibulatkan 20,610.00   9 1 M2 PENGECATAN TEMBOK/PLAFON BARU KWALITAS BAIK

    a Plamir 0.10 kg 9,000.00

900.00

    b Rol cat 0.01 bh 26,000.00

260.00

    c Cat penutup kwalitas baik 0.50 kg 16,000.00

8,000.00

    d Steger (perancah kerja) 0.01 Ls 60,000.00

600.00

    e Ampelas 0.50 lbr 1,600.00

Page 123: Analisa Harga Satuan Pekerjaan Semarang

3,200.00

    f Pembantu tukang 0.06 org 27,500.00

1,650.00

    g Tukang cat 0.20 org 42,000.00

8,400.00

    Jumlah 21,410.00     Dibulatkan 21,410.00   10 1 M2 PENGECATAN TEMBOK LAMA

    a Cat penutup kwalitas baik 0.40 kg 27,000.00

10,800.00

    b Rol cat 0.01 bh 26,000.00

260.00

    c Steger (perancah kerja) 0.01 Ls 60,000.00

600.00

    d Ampelas 0.50 lbr 3,200.00

1,600.00

    e Pembantu tukang 0.06 org 27,500.00

1,650.00

    f Tukang cat 0.20 org 42,000.00

8,400.00

    Jumlah 23,310.00     Dibulatkan 23,310.00   11 1 M2 PENGECATAN EXTERIOR

    a Cat tembok 0.36 kg 72,000.00

25,920.00

    b Plamir tembok 0.16 kg 9,000.00

1,440.00

    c Rol cat 0.01 bh 26,000.00

260.00

    d Steger (perancah kerja) 0.01 Ls 60,000.00

600.00

    e Ampelas 0.50 lbr 1,600.00

Page 124: Analisa Harga Satuan Pekerjaan Semarang

3,200.00

    f Pembantu tukang 0.20 org 27,500.00

5,500.00

    g Tukang cat 0.30 org 42,000.00

12,600.00

    Jumlah 47,920.00     Dibulatkan 47,920.00   12 1 M2 MEMASANG WALLPAPER

    a Wallpaper 1.20 m2 15,700.00

18,840.00

    b Lem perekat 0.20 kg 30,800.00

6,160.00

    c Pembantu tukang 0.02 org 27,500.00

550.00

    d Tukang cat 0.15 org 42,000.00

6,300.00

    Jumlah 31,850.00     Dibulatkan 31,850.00   13 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI

    a Meni besi 0.10 kg 15,000.00

1,500.00

    b Kuas 0.01 bh 13,500.00

135.00

    c Pembantu tukang 0.02 org 27,500.00

550.00

    d Tukang cat 0.20 org 42,000.00

8,400.00

    Jumlah 10,585.00     Dibulatkan 10,580.00   14 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN CAT

    a Meni besi 0.10 kg 15,000.00

1,500.00

Page 125: Analisa Harga Satuan Pekerjaan Semarang

    b Cat besi 0.13 kg 37,000.00

4,810.00

    c Kuas 0.01 bh 13,500.00

135.00

    d Ampelas 0.50 lbr 3,200.00

1,600.00

    e Perancah kayu 0.01 m3 60,000.00

600.00

    f Pembantu tukang 0.20 org 27,500.00

5,500.00

    g Tukang cat 0.20 org 42,000.00

8,400.00

    Jumlah 22,545.00     Dibulatkan 22,540.00

 

XVIII PEKERJAAN LISTRIK  1 PASANG 1 TITIK STOP KONTAK

    a Stop kontak 1.00 bh 12,500.00

12,500.00

    b Kabel listrik NYM 3 x 2,5 mm 0.25 rol 625,000.00

156,250.00

    c Aksesoris ( 20 % material ) 1.00 ls 31,250.00

31,250.00

    d Pembantu tukang 0.20 org 27,500.00

5,500.00

    e Tukang listrik 0.60 org 42,000.00

25,200.00

    Jumlah 230,700.00

    Dibulatkan 230,700.00

Page 126: Analisa Harga Satuan Pekerjaan Semarang

  2 PASANG 1 TITIK LAMPU

    a Saklar 1.00 bh 12,500.00

12,500.00

    b Kabel listrik NYM 2 x 2,5 mm 0.25 rol 375,000.00

93,750.00

    c Aksesoris ( 20 % material ) 1.00 ls 18,750.00

18,750.00

    d Pembantu tukang 0.20 org 27,500.00

5,500.00

    e Tukang listrik 0.60 org 42,000.00

25,200.00

    Jumlah 155,700.00

    Dibulatkan 155,700.00

  3 PASANG 1 BUAH LAMPU SL

    a Lampu SL 1.00 bh 56,000.00

56,000.00

    b Aksesoris (1 % alat) 1.00 ls 560.00

560.00

    c Tukang listrik 0.10 org 42,000.00

4,200.00

    Jumlah 60,760.00

    Dibulatkan 60,760.00

  4 PASANG 1 BUAH LAMPU TL

    a Lampu TL 1.00 bh 56,000.00

56,000.00

    b Aksesoris ( 1 % alat ) 1.00 ls 560.00

560.00

    c Tukang listrik 0.12 org

Page 127: Analisa Harga Satuan Pekerjaan Semarang

42,000.00 5,040.00

    Jumlah 61,600.00

    Dibulatkan 61,600.00

  5 PASANG 1 BUAH LAMPU BARET

    a Lampu baret 1.00 bh 87,000.00

87,000.00

    b Aksesoris ( 1 % alat ) 1.00 ls 870.00

870.00

    c Tukang listrik 0.15 org 42,000.00

6,300.00

    Jumlah 94,170.00

    Dibulatkan 94,170.00

  6 PASANG 1 BUAH LAMPU PIJAR

    a Lampu pijar 1.00 bh 5,000.00

5,000.00

    b Aksesoris (1 % alat) 1.00 ls 50.00

50.00

    c Tukang listrik 0.10 org 42,000.00

4,200.00

    Jumlah 9,250.00

    Dibulatkan 9,250.00

  7 PASANG 1 BUAH LAMPU TAMAN

    a Lampu taman 1.00 bh 152,500.00

152,500.00

    b Aksesoris (1 % alat) 1.00 ls 1,525.00

1,525.00

Page 128: Analisa Harga Satuan Pekerjaan Semarang

    c Tukang listrik 0.35 org 42,000.00

14,700.00

    Jumlah 168,725.00

    Dibulatkan 168,720.00

  8 PASANG 1 BUAH PANEL

    a Panel listrik standar untuk rumah 1.00 bh 250,000.00

250,000.00

    b Aksesoris (10 % alat) 1.00 ls 25,000.00

25,000.00

    c Tukang listrik 1.00 org 42,000.00

42,000.00

  Jumlah 317,000.00

    Dibulatkan 317,000.00

XIX PEKERJAAN WATERPROOFING  1 PASANG 1 M2 WATERPROOFING MEMBRAN

    a Material primer 2.50 kg 2,450.00

6,125.00

    b Waterproofing membrane 1.10 m2 60,000.00

66,000.00

    c Pengetesan ( 10 % material ) 1.00 ls 6,600.00

6,600.00

    d Pembantu tukang 0.20 org 27,500.00

5,500.00

    e Tukang batu 0.60 org 42,000.00

25,200.00

    Jumlah

Page 129: Analisa Harga Satuan Pekerjaan Semarang

109,425.00

    Dibulatkan 109,420.00

  2 PASANG 1 M2 WATERPROOFING COATING

    aPre treatment/cleaning ( 10 % material )

1.00 m2 4,200.00

4,200.00

    b Bahan waterproofing coating 1.00 kg 42,000.00

42,000.00

    c Kuas 3 " 0.25 bh 13,500.00

3,375.00

    d Pembantu tukang 0.20 org 27,500.00

5,500.00

    e Tukang batu 0.60 org 42,000.00

25,200.00

    Jumlah 80,275.00

    Dibulatkan 80,270.00

  3 PASANG 1 M2 FLOOR HARDERNER

    a Material natural non metalic 1.10 kg 42,000.00

46,200.00

    b Aksesori ( 10 % alat ) 1.00 ls 462.00

462.00

    c Pembantu tukang 0.20 org 27,500.00

5,500.00

    d Tukang batu 0.60 org 42,000.00

25,200.00

    Jumlah 77,362.00

    Dibulatkan 77,360.00

Page 130: Analisa Harga Satuan Pekerjaan Semarang