NO JENIS BAHAN SATUAN HARGA BAHAN Rp. BAHAN AGREGAT KASAR, BAHAN PEREKAT DAN BAHAN JADINYA Pasir Urug m3 70,000.00 Sirtu m3 150,000.00 Pasir Pasang m3 240,000.00 Pasir Beton m3 250,000.00 Batu Pecah Mesin 1/2 m3 250,000.00 Batu Pecah Mesin 2/3 m3 250,000.00 Batu Pecah Mesin 3/5 m3 250,000.00 Batu Pecah Mesin 5/7 m3 250,000.00 Batu Belah Pondasi m3 175,000.00 Batu Tempel Hitam m2 80,000.00 Bata merah kelas I bh 500.00 Inter Blok Natural 6 cm m2 25,000.00 Paving Blok natural 8 cm m2 28,000.00 Paving Blok Warna 6 cm m2 30,000.00 Kanstin Paving Blok m1 30,000.00 Glass Block m2 15,000.00 Semen PC Tiga Roda / 50 kg zak 40,000.00 Semen Putih kg 3,500.00 Semen warna kg 3,500.00 Aspal (ESO) 1 Drum 150 kg kg 8,000.00 BAHAN FINISHING : LABURAN , PENGISI DAN ALATNYA Plamir Tembok Ex. Paragon kg 18,000.00 Cat Tembok Sanlex kg 5,100.00 Rool Cat Tembok bh 15,000.00 Kape Tembok bh 5,000.00 Kape Kayu bh 5,000.00 Soligneum 1 Blek 5 ltr 12,000.00 Kwas 3 " bh 7,500.00 Otem (Pewarna Plitur) bks 1,000.00 Spirtus ltr 2,500.00 Bahan Plitur Kripik (Sirlak India) kg 6,000.00 Dempul Halus/ Infra (Wood Filler)/Impra kg 21,500.00 Terpentin ltr 2,000.00 Tiner ltr 18,000.00 Ampelas lbr 2,500.00 Dempul Kayu Cap Kucing kg 9,500.00 Dempul Kayu Avian kg 6,000.00 Meni Kayu/ Besi kg 20,000.00 Sincromat kg 60,000.00 Cat Kayu pinoguar kg 24,000.00 Cat Besi Seiv kg 60,000.00 Cat Kayu Avian kg 45,000.00 Cat Besi Duco Danaglos / ICI kg 130,000.00 Lem Kayu Putih (Fox) kg 8,500.00 Lem Kayu Kuning (AIBON) kg 14,000.00 BAHAN KAYU BERIKUT BAHAN JADINYA Kayu Terentang m3 310,000.00 Kayu Balok Borneo Super m3 1,700,000.00 Kayu papan Borneo Super m3 1,700,000.00 Kayu kaso 5/7 Borneo Super m3 1,700,000.00
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
NO JENIS BAHAN SATUAN HARGA BAHAN
Rp.
BAHAN AGREGAT KASAR, BAHAN
PEREKAT DAN BAHAN JADINYA
Pasir Urug m3 70,000.00 Sirtu m3 150,000.00 Pasir Pasang m3 240,000.00 Pasir Beton m3 250,000.00 Batu Pecah Mesin 1/2 m3 250,000.00 Batu Pecah Mesin 2/3 m3 250,000.00 Batu Pecah Mesin 3/5 m3 250,000.00 Batu Pecah Mesin 5/7 m3 250,000.00 Batu Belah Pondasi m3 175,000.00 Batu Tempel Hitam m2 80,000.00 Bata merah kelas I bh 500.00 Inter Blok Natural 6 cm m2 25,000.00 Paving Blok natural 8 cm m2 28,000.00 Paving Blok Warna 6 cm m2 30,000.00 Kanstin Paving Blok m1 30,000.00 Glass Block m2 15,000.00 Semen PC Tiga Roda / 50 kg zak 40,000.00 Semen Putih kg 3,500.00 Semen warna kg 3,500.00 Aspal (ESO) 1 Drum 150 kg kg 8,000.00
BAHAN FINISHING :
LABURAN , PENGISI DAN ALATNYA
Plamir Tembok Ex. Paragon kg 18,000.00 Cat Tembok Sanlex kg 5,100.00 Rool Cat Tembok bh 15,000.00 Kape Tembok bh 5,000.00 Kape Kayu bh 5,000.00 Soligneum 1 Blek 5 ltr 12,000.00 Kwas 3 " bh 7,500.00 Otem (Pewarna Plitur) bks 1,000.00 Spirtus ltr 2,500.00 Bahan Plitur Kripik (Sirlak India) kg 6,000.00 Dempul Halus/ Infra (Wood Filler)/Impra kg 21,500.00 Terpentin ltr 2,000.00 Tiner ltr 18,000.00 Ampelas lbr 2,500.00 Dempul Kayu Cap Kucing kg 9,500.00 Dempul Kayu Avian kg 6,000.00 Meni Kayu/ Besi kg 20,000.00 Sincromat kg 60,000.00 Cat Kayu pinoguar kg 24,000.00 Cat Besi Seiv kg 60,000.00 Cat Kayu Avian kg 45,000.00 Cat Besi Duco Danaglos / ICI kg 130,000.00 Lem Kayu Putih (Fox) kg 8,500.00 Lem Kayu Kuning (AIBON) kg 14,000.00
BAHAN KAYU BERIKUT BAHAN JADINYAKayu Terentang m3 310,000.00 Kayu Balok Borneo Super m3 1,700,000.00 Kayu papan Borneo Super m3 1,700,000.00 Kayu kaso 5/7 Borneo Super m3 1,700,000.00
NO JENIS BAHAN SATUAN HARGA BAHAN
Rp.Kayu 5/10 kayu awet kls I m3 1,700,000.00 Kayu Awet Kls I m3 1,250,000.00 Kayu KAMPER m3 3,600,000.00 Kayu Balok Rasamala m3 2,100,000.00 Kayu papan Rasamala m3 2,100,000.00 Kayu Balok Kamper Medan (Kruing) m3 1,600,000.00 Kayu Papan Kamper Medan (Kruing) m3 1,600,000.00 Kayu Balok Kamper Banjar m3 2,100,000.00 Kayu Papan Kamper Banjar m3 2,100,000.00 Kayu Balok Kamper Samarinda m3 5,500,000.00 Kayu Papan Kamper Samarinda m3 5,500,000.00 Kayu Jati jabar m3 7,000,000.00 Dolken 5 s/d 7 bt 7,000.00 Dolken 7 s/d 10 / kaso 4/6 untuk stootwork bt 11,500.00 List Profil kamper 1 cm m1 1,000.00 List Profil kamper 2 cm (45x45) m1 2,750.00 Kayu Reng 2/3 Borneo Super m1 1,500.00 Kayu Reng 3/4 Borneo Super m1 3,000.00 kayu ulin m3 1,650,000.00
BAHAN PENUTUP RANGKA PLAPONBahan Plapon Eternit 4 mm lbr 42,500.00 Kalsiboard lbr 38,000.00 List Kayu 4 / 4 btng 18,000.00 List Kayu 5 / 5 btng 27,000.00 Gypsum 9 mm lbr 75,000.00
BAHAN KAYU LAPISTriplek 3 mm 120 x 240 lbr 33,000.00 Triplek 4 mm 120 x 240 lbr 39,000.00 Triplek 6 mm 120 x 240 lbr 42,000.00 Multiplek 12 mm 120 x 240 lbr 112,500.00 Multiplek 12 mm ukuran pintu lbr 236,250.00 Teak Wood 4 mm 120 x240 lbr 75,000.00 Formika lbr 69,000.00
BAHAN LANTAI DAN PELAPIS DINDINGKeramik lantai 20 x 20 Putih Polos "MULIA" m2 45,000.00 Keramik dinding 20 x 25 Putih Polos "MULIA" m2 48,000.00 Keramik 30X30 Putih Polos "MULIA" m2 46,000.00 Lantai Pear Stone m2 89,000.00 Floor Hardener Ferofax sekualitas Metaltop kg 60,000.00
G. BAHAN SALURAN AIR KOTOR / BERSIHGrafel U 20 cm m' 20,000.00 Grafel U 30 cm m' 30,000.00 Buis Beton dia. 20 cm ( 1 m ) m' 45,000.00 Buis Beton dia.30 cm (1 m ) m' 60,000.00
BAHAN LOGAM DAN BAHAN JADINYABesi Beton U-24 Rata-rata kg 14,000.00 Pagar BRC T.120 Lengkap Tiang m1 132,000.00 Pagar BRC T.175 Lengkap Tiang m1 612,500.00 Besi Canal kg 14,000.00 Besi Siku L kg 14,000.00 Besi IWF DN SII kg 14,000.00 Besi HWF kg 14,000.00 Besi plat kg 14,000.00 Kawat Beton kg 19,500.00
NO JENIS BAHAN SATUAN HARGA BAHAN
Rp.Kawat Duri kg 12,500.00 Seng plat BJLS 28 ( lebar = 90 cm ) m1 35,000.00 Seng Glb BJLS 28 lbr 20,500.00 Ram kawat m2 35,000.00
BAHAN KACAKaca polos 3 mm (ASAHI) m2 57,000.00 Kaca polos 5 mm (ASAHI) m2 65,000.00 Cermin m2 89,000.00
BAHAN PAKU DAN MUR BAUTPaku biasa kg 15,000.00 Paku hak Pj. 15 cm bh 6,000.00
BAHAN PERPIPAAN
Pipa GIP Medium B dia. 1/2" bt 17,000.00
Pipa GIP Medium B dia. 3/4" bt 23,000.00
Pipa GIP Medium B dia. 1" bt 25,000.00
Pipa GIP Medium B dia. 1 1/2" bt 43,000.00
Pipa GIP Medium B dia. 2" bt 60,000.00
Pipa PVC MASPION ABU dia. 2" (AW) bt 75,000.00
Pipa PVC MASPION ABU dia. 3" (AW) bt 140,000.00
Pipa PVC MASPION ABU dia. 4" (AW) bt 230,000.00
Grefel beton 1/2 dia. 30 cm m1 30,000.00
BAHAN SANITAIR DAN PERPIPAAN
Stop Kran 3/4 " KIT bh 75,000.00
Stop Kran 1 1/2 " KIT bh 125,000.00
Kran bebek Sun Ei 1/2 " bh 85,000.00
Floor drain bh 20,000.00
Wastafel Lengkap Toto Type L 34 bh 350,000.00
Closet Jongkok Standard Putih Poslin INA unit 125,000.00
closet duduk ex toto unit 1,050,000.00
kran air 1/2" bh 37,300.00
shower unit 250,000.00
kichensink unit 250,000.00
BAHAN PENUTUP ATAP
Genteng Palentong bh 1,000.00
Wuwung Genteng bh 18,500.00
Atap genteng Morando glazur bh 2,000.00
Wuwung Genteng morando glazur bh 4,000.00
Genteng Ex KIA (11 bh ) m2 58,685.00
BAHAN ELEKTRIKALSaklar Broko Tunggal Standard (1Phase) bh 16,000.00 Saklar Broko Seri Standard (1 Phase) bh 16,000.00 Stop Kontak Broko Standard (1 Phase) bh 9,000.00 Lampu Neon TL Philip 1 X 36 W Type TKI bh 17,500.00 Pentanahan Penangkal Petir lengkap bak kontrol ttk 900,000.00 pipa kabel bt 8,000.00 Kabel NYY 2 X 2,5 mm Prima m1 4,000.00 Kabel NYY 3 X 2,5 mm Prima M1 5,000.00
NO JENIS BAHAN SATUAN HARGA BAHAN
Rp.
BAHAN ALAT PENGGANTUNG DAN KUNCIKunci 2 Slaag bh 75,000.00 Kunci KM Bulat ALPA bh 75,000.00 Espanyolet/Slot Tanam bh 30,000.00 Hak Angin Kait Jendela Biasa ( Kait ) bh 15,000.00 Engsel Pintu Arch Standard bh 6,000.00 Engsel Jendela Arch bh 4,000.00 Pasang roda type 61. K/ N ex Henderson bh 65,000.00
BAHAN PENGHISAP AIR SUMUR DALAMMesin Pompa Air 400 W - Sanyo unit 650,000.00
BAHAN PENAMPUNG AIRTangki Air Fiber Glass 0.5 m3 ( Pinguinl ) bh 1,200,000.00 Tangki Air Fiber Glass 2000 liter ( Pinguinl ) bh 1,900,000.00 Bak km Fiber 50 X 50 bh 125,000.00
DAFTAR HARGA SATUAN
NOJENIS UPAH HARGA UPAH
Rp.
Mandor 63,500 Pekerja 40,000 Pekerja las 45,000 Pelaksana 40,000 Pengawas las 50,000 Tukang 50,000 Tukang cat 45,000 Tukang gerinda 45,000 Tukang las 55,000 Juru ukur 80,000 Teknisi 80,000 Operator mesin 63,500
- - - - - - - - -
NO JENIS BAHANSPESIFIKASI HARGA BAHAN
Rp.
1 Acetylin @ 45 kg 175,000 2 Amplas 5,500 3 Apron 73,265 4 Bahan las thermit 847,000 5 Bahan pengisi 110,000 6 Balas batu pecah 2/6 di quarry 140,000 7 Baling-baling 22,700 8 Bambu dia. 8-10 x 400-550 cm 11,500 9 Bantalan beton lengkap dengan penambat 457,000
10 Bantalan kayu biasa ukuran 13x22x200 405,000 11 Bantalan kayu jembatan ukuran 18x22x200 625,000
12 Batu pecah 130,000 13 Batu gerinda MP12 406,875 14 Batu gerinda tangan 52,100 15 Batu gerinda profil 270,000 16 Batu pecah 2/3 140,000 17 Batu pecah kricak 1/2 140,000 18 Baut bantalan dia. 19, p = 270 mm 23,650 19 Baut glugu 25,100 20 Baut IRJ 55,000 21 Baut Isol 55,000 22 Baut kopel dia. 19 mm p = 400 mm 29,700 23 Baut kopel dia. 19 mm p = 700 mm 29,700 24 Baut kopel dia. 19 mm p = 800 mm 29,700 25 Baut lasplaat (fishplate) 55,000 26 Baut/mur 3,000 27 Baut keling diameter 19 - 45 mm 9,600 28 Baut kaki gongsol diameter 21-160 215,000 29 Baut kupingan gongsol diameter 19-55 8,500 30 Baut sindik 24,000 31 Cat Jembatan (Epoxy) - 32 Begel glugu 26,000 33 Begel rel bendel dia. 19 mm 33,000 34 Bensin 4,500 35 Bensin campur 4,750 36 Brander pemanas 1,480,000 37 Bor kayu 60,000 38 Bor rel 200,000 39 Cetok 12,000 40 Cincin glugu 45,000 41 Conector galvanis 4 mm 11,000 42 Cookes 11,500 43 Dempul 20,500 44 Dongkrak alignment beam 4,235,000 45 Elektroda untuk layer 40,250 46 Elektroda untuk pengeras 75,000 47 Ember 7,500 48 Gemuk 21,000 49 Gergaji besi standar 23,500 50 Jeligen air, ember+lap 15,000 51 Kabel las 0,8 mm 75,000 52 Kacamata Gerinda 45,000
53 Kacamata las 45,000 54 Kain bendera 15,000 55 Kain lap 5,750 56 Kawat diameter 5 mm 13,500 57 Kawat las elektroda 27,500 58 Kawat pral 19,500 59 Kek besi cookes 37,000 60 Kikir segi empat 1.5" 22,000 61 Kuas uk. 3" 13,500 62 Kunci baut lasplaat 70,000 63 Kunci inggris 12" 93,500 64 Kunci ring / pas 45,000 65 Kunci tirefon 66,500 66 Lampu semboyan 177,100 67 Lasplaat sambung R.42 146,750 68 Lasplaat sambung R.54 74,500 69 Lasplaat Isol 299,700 70 Linggis 140,000 71 LPG 12 kg 60,000 72 LPG 46 kg 192,500 73 Masker Las 60,000 74 Minyak Tanah 2,500 75 Mistar kusus untuk gurinda 125,000 76 Mistar pelurus rel 1 m 440,000 77 Mold Tembaga 354,200 78 Oksigen 75,000 79 Oli Meditrain 40 9,500 80 Oli SAE 20 25,850 81 Oli SAE 30-40 16,000 82 Oli SAE 40 16,000 83 Oli SAE 90 32,450 84 P3K 125,000 85 Pahat ganjal 7,700 86 Paku 10,000 87 Paku maskrum 11,500 88 Paku seng 11,500 89 Palu 4 kg 70,000 90 Palu Ketrek 22,000 91 Palu konde 1 kg 33,000 92 Palu/ martil 4 kg 49,500 93 Pandpuller 99,000 94 Pandrol R.42 26,000 95 Pandrol R.54 26,600
96 Pasak 6 mm 35,500 97 Pasir 90,000 98 Pasir sirtu 87,500 99 Pasir urug darat 130,000
100 Paslin 15,000 101 Pelat tembaga penghalang 125,000 102 Pemegang elektroda 150,000 103 Penetran cleaner 400 ml 124,450 104 Penetran developer 400 ml 73,200 105 Penetran revolfer 400 ml 124,450 106 Plat landas 219,000 107 Ram kawat 29,000 108 Regulator acetylin 480,000 109 Regulator LPG 75,000 110 Regulator oksigen 120,000 111 Residu 15,000 112 Sarung tangan panjang 35,000 113 Sarung tangan pendek 25,000 114 Sekop 10,000 115 Senteleng bambu 54,000 116 Sepatu glugu 27,500 117 Sepatu las 105,000 118 Sikat baja 10,000 119 Solar 4,200 120 Stopwatch 240,000 121 Tabung pemanas elektroda 175,000 122 Tambang manila dia 19 mm 27,500 123 Tangkai martil 7,500 124 Tenda plastik 4x4 m 89,000 125 Ter 11,500 126 Thermometer 145,000 127 Tirefon 45,000 128 Vaselin 5,500 129 Zat asam 110,000
NO SEWA ALAT/TEST SEWA ALAT
Rp.
1 Alat bantu 75,750 2 Generator set 1,478,750 3 Mesin gerinda MP12 144,500 4 Mesin gerinda tangan 31,125 5 Mesin weldshear manual 72,600 6 Wheel loader 288,000 7 Mesin las 400 Amp 150,000 8 Test ultrasonic termasuk akomodasi petugas 25,000 9 Transportasi untuk pekerjaan las 50,000
10 Pengaman operasional untuk pekerjaan las 5,000 11 Biaya operasi MTT 09-16 CAT 9,511 12 Biaya operasi MTT 07-16 G, MTT 08-16 GS plain track 7,018
34 11 46.13.100 Angkat lestreng pada jalan rel yang baru diganti balasnya pada BANTALAN KAYU
(Dikerjakan setelah dilalui minimum oleh 2 KA pada kecepatan sebelumnya)
34 11 46.13.110 1 m'sp Angkat lestreng untuk kecepatan KA 20 km/jam dari kec 5 km/jam dengan manual 0.00 11,587.50 0.00 11,587.50
Upah
Mandor 0.0250 0.025 OH 63,500.00 1,588
Pekerja 0.2500 0.250 OH 40,000.00 10,000
34 11 46.13.120 1 m'sp Angkat lestreng untuk kecepatan KA 40 km/jam dari kec 20 km/jam 0.00 21,175.00 0.00 21,175.00
Upah
Halaman 27
NO U R A I A N KOEF SAT HARGA SAT JUMLAH TOTAL
bahan upah alat/angkut bahan upah alat/angkut
A B D D' E F G H I=D'xF J=D'xG K=D'xH L=I+J+K
KOEF RAP
Mandor 0.0500 0.050 OH 63,500.00 3,175
Pekerja 0.4500 0.450 OH 40,000.00 18,000
34 11 46.13.130 1 m'sp Angkat lestreng untuk kecepatan KA 60 km/jam dari kec 40 km/jam 0.00 23,175.00 0.00 23,175.00
Upah
Mandor 0.0500 0.050 OH 63,500.00 3,175
Pekerja 0.5000 0.500 OH 40,000.00 20,000
34 11 46.13.200 Angkat lestreng pada jalan rel yang baru diganti balasnya pada BANTALAN BESI
(Dikerjakan setelah dilalui minimum oleh 2 KA pada kecepatan sebelumnya)
34 11 46.13.210 1 m'sp Angkat lestreng untuk kecepatan KA 20 km/jam dari kec 5 km/jam dengan manual 0.00 12,978.00 0.00 12,978.00
Upah
Mandor 0.0280 0.028 OH 63,500.00 1,778
Pekerja 0.2800 0.280 OH 40,000.00 11,200
34 11 46.13.220 1 m'sp Angkat lestreng untuk kecepatan KA 40 km/jam dari kec 20 km/jam 0.00 23,292.50 0.00 23,292.50
Upah
Mandor 0.0550 0.055 OH 63,500.00 3,493
Pekerja 0.4950 0.495 OH 40,000.00 19,800
34 11 46.13.230 1 m'sp Angkat lestreng untuk kecepatan KA 60 km/jam dari kec 40 km/jam 0.00 25,492.50 0.00 25,492.50
Upah
Mandor 0.0550 0.055 OH 63,500.00 3,493
Pekerja 0.5500 0.550 OH 40,000.00 22,000
34 11 46.13.300 Angkat lestreng pada jalan rel yang baru diganti balasnya pada BANTALAN BETON
(Dikerjakan setelah dilalui minimum oleh 2 KA pada kecepatan sebelumnya)
34 11 46.13.310 1 m'sp Angkat lestreng untuk kecepatan KA 20 km/jam dari kec 5 km/jam dengan manual 0.00 17,613.00 0.00 17,613.00
Upah
Mandor 0.0380 0.038 OH 63,500.00 2,413
Pekerja 0.3800 0.380 OH 40,000.00 15,200
34 11 46.13.320 1 m'sp Angkat lestreng untuk kecepatan KA 40 km/jam dari kec 20 km/jam 0.00 31,962.50 0.00 31,962.50
Upah
Mandor 0.0750 0.075 OH 63,500.00 4,763
Pekerja 0.6800 0.680 OH 40,000.00 27,200
34 11 46.13.330 1 m'sp Angkat lestreng untuk kecepatan KA 60 km/jam dari kec 40 km/jam 0.00 34,762.50 0.00 34,762.50
Upah
Mandor 0.0750 0.075 OH 63,500.00 4,763
Pekerja 0.7500 0.750 OH 40,000.00 30,000
34 11 46.16 Pada Jalan Rel Baru atau Direhabilitasi
34 11 46.16.100 Angkat lestreng pada jalan rel BANTALAN KAYU
(Dikerjakan setelah dilalui minimum oleh 2 KA pada kecepatan sebelumnya)
34 11 46.16.110 1 m'sp Angkat lestreng untuk kecepatan KA 20 km/jam 0.00 7,670.00 0.00 7,670.00
Upah
Mandor 0.0200 0.020 OH 63,500.00 1,270
Pekerja 0.1600 0.160 OH 40,000.00 6,400
34 11 46.16.120 1 m'sp Angkat lestreng untuk kecepatan KA 40 km/jam 0.00 15,340.00 0.00 15,340.00
Upah
Mandor 0.0400 0.040 OH 63,500.00 2,540
Pekerja 0.3200 0.320 OH 40,000.00 12,800
34 11 46.16.130 1 m'sp Angkat lestreng untuk kecepatan KA 60 km/jam 0.00 19,340.00 0.00 19,340.00
Upah
Mandor 0.0400 0.040 OH 63,500.00 2,540
Pekerja 0.4200 0.420 OH 40,000.00 16,800
34 11 46.16.200 Angkat lestreng pada jalan rel yang baru diganti balasnya pada BANTALAN BESI
(Dikerjakan setelah dilalui minimum oleh 2 KA pada kecepatan sebelumnya)
34 11 46.16.210 1 m'sp Angkat lestreng untuk kecepatan KA 20 km/jam dari kec 5 km/jam dengan manual 0.00 8,437.00 0.00 8,437.00
Upah
Mandor 0.0220 0.022 OH 63,500.00 1,397
Halaman 28
NO U R A I A N KOEF SAT HARGA SAT JUMLAH TOTAL
bahan upah alat/angkut bahan upah alat/angkut
A B D D' E F G H I=D'xF J=D'xG K=D'xH L=I+J+K
KOEF RAP
Pekerja 0.1760 0.176 OH 40,000.00 7,040
34 11 46.16.220 1 m'sp Angkat lestreng untuk kecepatan KA 40 km/jam dari kec 20 km/jam 0.00 16,874.00 0.00 16,874.00
Upah
Mandor 0.0440 0.044 OH 63,500.00 2,794
Pekerja 0.3520 0.352 OH 40,000.00 14,080
34 11 46.16.230 1 m'sp Angkat lestreng untuk kecepatan KA 60 km/jam dari kec 40 km/jam 0.00 21,274.00 0.00 21,274.00
Upah
Mandor 0.0440 0.044 OH 63,500.00 2,794
Pekerja 0.4620 0.462 OH 40,000.00 18,480
34 11 46.16.300 Angkat lestreng pada jalan rel yang baru diganti balasnya pada BANTALAN BETON
(Dikerjakan setelah dilalui minimum oleh 2 KA pada kecepatan sebelumnya)
34 11 46.16.310 1 m'sp Angkat lestreng untuk kecepatan KA 20 km/jam dari kec 5 km/jam dengan manual 0.00 17,613.00 0.00 17,613.00
Upah
Mandor 0.0380 0.038 OH 63,500.00 2,413
Pekerja 0.3800 0.380 OH 40,000.00 15,200
34 11 46.16.320 1 m'sp Angkat lestreng untuk kecepatan KA 40 km/jam dari kec 20 km/jam 0.00 31,962.50 0.00 31,962.50
Upah
Mandor 0.0750 0.075 OH 63,500.00 4,763
Pekerja 0.6800 0.680 OH 40,000.00 27,200
34 11 46.16.330 1 m'sp Angkat lestreng untuk kecepatan KA 60 km/jam dari kec 40 km/jam 0.00 34,762.50 0.00 34,762.50
Upah
Mandor 0.0750 0.075 OH 63,500.00 4,763
Pekerja 0.7500 0.750 OH 40,000.00 30,000
34 11 46.19 Final Tamping
(Dikerjakan setelah dilalui minimum oleh 2 KA pada kec 20 km/jam)
34 11 46.19.100 1 m'sp Angkat lestreng untuk kecepatan > KA 60 km/jam dengan MTT, PBR dan VDM (Final Tamping) 0.00 16,800.00 47,286.80 64,086.80
Upah
Juru ukur 0.0350 0.035 OH 80,000.00 2,800
Pekerja 0.3500 0.350 OH 40,000.00 14,000
Alat
Biaya operasi MTT 09-16 CAT 3.0000 3.000 kali 9,510.60 28,532
Biaya operasi PBR 200-400 1.0000 1.000 kali 13,975.50 13,976
Biaya operasi VDM 800-800 GS 1.0000 1.000 kali 4,779.50 4,780
Page 29 of 36
Total Harga #REF!RENCANA ANGGARAN PELAKSANAAN Harga /m2 #REF!PEKERJAAN TRACK LUAS BANGUNAN 18 PROYEK MATERIAL /M2 : #REF!
Total MATERIAL : #REF!
NO ITEM PEKERJAAN VOL
SATanalisa HARSAT JUMLAH HARGA
Real MATERIAL MATERIAL 61.67
I PEKERJAAN PERSIAPAN1 PEMBERSIHAN LAHAN 12.00 m2 #REF! #REF! #REF!2 PENGUKURAN DAN PASANG BOUWPLANK 9.00 m #REF! #REF! #REF!
SUB TOTAL 1
II PEKERJAAN PEMBONGKARAN1 Bongkar plat jalan setapak untuk dipakai kembali 18.00 bh2 Bongkar plesteran dibawah plat jalan setapak 3.00 m23 Bongkar kongliong 0.90 m3 #REF! #REF! #REF!4 Bongkar dinding partisi 9.00 m25 Bongkar kusen aluminium untuk dipakai kembali 1.00 bh6 Bongkar daun pintu aluminium untuk dipakai kembali 1.00 bh
SUB TOTAL 1
III PEKERJAAN TANAH DAN PONDASI1 GALIAN PONDASI 12.40 M3 #REF! #REF! #REF!2 PONDASI CAKAR AYAM (4d8,d6-200)
IV PEKERJAAN PASANGAN DAN PLESTERAN1 PASANGAN BATA MERAH 1/2 BT 1:5 216.00 M2 #REF! #REF! #REF!2 PLESTER 1:5 + ACI 432.00 M2 #REF! #REF! #REF!
SUB TOTAL 4
V
1 KUSEN PINTU DAN JENDELA 44.50 M Rp 40,000 Rp 1,780,000 2 PINTU JATI PANEL SOLID 3.00 UNIT Rp 400,000 Rp 1,200,000 3 PINTU KACA BINGKAI JATI 2.00 UNIT Rp 350,000 Rp 700,000 4 DAUN JENDELA BESAR 2.00 UNIT Rp 200,000 Rp 400,000 5 DAUN JENDELA KECIL 2.00 UNIT Rp 150,000 Rp 300,000 6 HANDLE PINTU 5.00 UNIT Rp 120,000 Rp 600,000 7 SLOT DAUN JENDELA 8.00 UNIT Rp 15,000 Rp 120,000 8 HAK ANGIN 4.00 UNIT Rp 20,000 Rp 80,000 9 ENGSEL DAUN PINTU 15.00 BH Rp 9,000 Rp 135,000
10 ENGSEL DAUN JENDELA 8.00 BH Rp 8,000 Rp 64,000 11 KACA POLOS 5 MM M2
SUB TOTAL 5
VI PEKERJAAN ATAP1 RANGKA ATAP BAJA RINGAN 50.00 M2 Rp 135,000 Rp 6,750,000 2 LISPLANK PAPAN 16.00 M' Rp 30,000 Rp 480,000 3 PENUTUP ATAP GENTENG 50.00 M2 Rp 58,000 Rp 2,900,000
PEKERJAAN KUSEN, PINTU, JENDELA , KACA DAN ACCESSORIES
Page 31 of 36
NO ITEM PEKERJAAN VOL
SATanalisa HARSAT JUMLAH HARGA
Real MATERIAL MATERIAL4 NOK ATAP GENTENG 8.00 M' Rp 45,000 Rp 360,000
SUB TOTAL 6
VII PEKERJAAN PLAFOND1 RANGKA PLAFOND METAL FOORING 50.00 M2 Rp 26,000 Rp 1,300,000 2 PLAFOND GYPSUM 50.00 M2 Rp 21,000 Rp 1,050,000
SUB TOTAL 7
VIII PEKERJAAN PELAPIS LANTAI DAN DINDING
Page 32 of 36
NO ITEM PEKERJAAN VOL
SATanalisa HARSAT JUMLAH HARGA
Real MATERIAL MATERIAL1 PLUR LANTAI 50.00 M2 #REF! Rp 21,000 Rp 1,050,000 2 KERAMIK LANTAI UBUD CREAM 40X40 38.30 M2 Rp 32,000 Rp 1,225,600 3 KERAMIK LANTAI KAMAR MANDI 20X20 2.70 M2 Rp 28,000 Rp 75,600 4 KERAMIK LANTAI DAPUR 40x40 9.00 M2 Rp 32,000 Rp 288,000 5 KERAMIK DINDING KAMAR MANDI 20x20 ( T = 1.6 M ) 6.10 M2 Rp 32,500 Rp 198,250
SUB TOTAL 8
IX PEKERJAAN PENGECATAN1 CAT DINDING INTERIOR 368.00 M2 Rp 6,000 Rp 2,208,000 1 CAT DINDING EXTERIOR 64.00 M2 Rp 9,000 Rp 576,000 2 CAT KUSEN 44.50 M' Rp 15,000 Rp 667,500 3 CAT DAUN PINTU 3.00 UNIT Rp 60,000 Rp 180,000 4 CAT DAUN JENDELA 4.00 UNIT Rp 15,000 Rp 60,000 5 CAT PLAFOND 50.00 M2 Rp 6,000 Rp 300,000 6 CAT LISPLANK PAPAN 16.00 M' Rp 12,000 Rp 192,000
SUB TOTAL 9
X PEKERJAAN INSTALASI LISTRIK1 INSTALASI TITIK LAMPU 10.00 TTK Rp 70,000 Rp 700,000 2 INSTALASI STOP KONTAK 4.00 TTK Rp 90,000 Rp 360,000 3 SAKLAR 10.00 BH Rp 8,000 Rp 80,000 4 STOP KONTAK EX. BROCO 4.00 BH Rp 11,000 Rp 44,000 5 FITING LAMPU 10.00 BH Rp 8,000 Rp 80,000
SUB TOTAL 10
REAL COSTDIBULATKANTERBILANG :
Page 33 of 36
UPAH /M2: #REF! Total UPAH : #REF!
HARSAT JUMLAH HARGA UPAH UPAH
#REF! #REF!#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!#REF! #REF!
#REF! #REF!
#REF! #REF!#REF! #REF!
#REF! #REF!#REF! #REF!
#REF! #REF!#REF! #REF!
#REF! #REF!
#REF! #REF!
Page 34 of 36
HARSAT JUMLAH HARGA UPAH UPAH
#REF! #REF!
#REF! #REF!
#REF! #REF!#REF! #REF!
#REF! #REF!
#REF! #REF!#REF! #REF!
#REF! #REF!
#REF! #REF!#REF! #REF!
#REF! #REF!
#REF! #REF!#REF! #REF!
Rp 5,000 Rp 222,500 Rp 40,000 Rp 120,000 Rp 40,000 Rp 80,000 Rp 15,000 Rp 30,000 Rp 15,000 Rp 30,000
Rp - Rp 3,000 Rp 48,000 Rp 6,500 Rp 325,000
Page 35 of 36
HARSAT JUMLAH HARGA UPAH UPAH
Rp 10,000 Rp 80,000
Rp 6,000 Rp 300,000 Rp 4,000 Rp 200,000
Page 36 of 36
HARSAT JUMLAH HARGA UPAH UPAH
Rp 4,000 Rp 200,000 Rp 6,000 Rp 229,800 Rp 6,000 Rp 16,200 Rp 6,000 Rp 54,000 Rp 6,000 Rp 36,600
Rp 1,500 Rp 552,000 Rp 1,500 Rp 96,000 Rp 3,500 Rp 155,750 Rp 17,000 Rp 51,000 Rp 8,000 Rp 32,000 Rp 2,500 Rp 125,000 Rp 2,500 Rp 40,000