Page 1: 140940869 Pltu Di Indonesia

PLTU SELURUH INDONESIA

Page 2: 140940869 Pltu Di Indonesia

KELOMPOK 1

AMALIA SARASWATI L2F008005ARI HASTANTO L2F008011BAYU PRIMASTHA L2F008016GIGIH MAHARTOTO L2F008039

Page 3: 140940869 Pltu Di Indonesia

Fast track – Power Plants in Java

3

Consortium Sinomach CNEEC and PT Penta Adi Samudra

2 x 300 MWPLTU 3 Jawa Timur – Tanjung Awar-Awar

10

1 x 600 MWPLTU 2 Jawa Tengah - Cilacap9

Consortium Harbin Power Engineering and Mitra Selaras Hutama Energi

1 x 600 MWPLTU 2 Jawa Timur - Paiton8

Consortium Dongfang Electric and Dalle Energy

2 x 315 MWPLTU 1 Jawa Timur - Pacitan7

Consortium Zelan, Tronoh and Priamanaya2 x 315 MWPLTU 1 Jawa Tengah - Rembang6

Consortium Shanghai Electric and Maxima Infrastruktur

3 x 350 MWPLTU 2 Jawa Barat – Pelabuhan Ratu5

Consortium Sinomach, CNEEC, PT Penta Adi Samudra

3 x 330 MWPLTU 1 Jawa Barat - Indramayu4

Consortium Dongfang Electric and Dalle Energy

3 x 315 MWPLTU 3 Banten – Lontar,Teluk Naga3

Consortium Truba Jurong Engineering and Chengda Engineering Corp.

2 x 300 MWPLTU 2 Banten - Labuhan2

Consortium of China National Technical Import & Export Corporation (CNTIC), China National Machinery Import & Export Corporation, Zhejiang Electric Power Design Institute and PT Rekayasa Industri

1 x 625 MWPLTU 1 Banten – Suralaya1

StatusEPC ContractorCapacity (MW)Power PlantNo

On hand

On hand

On hand

On hand

On hand

Page 4: 140940869 Pltu Di Indonesia

PLTU Tanjung Jati B Jepara

Pengelola : PT. PLN (Persero) Pembangkitan Tanjung Jati B

LOKASI :Desa Tubanan Kecamatan Kembang

Kabupaten Jepara 59457

KAPASITAS :2 x 661 MWBahan bakar : batu baraDistribusi : Jawa-Bali

Page 5: 140940869 Pltu Di Indonesia

PLTU PT Krakatau Daya Listrik

Pengelola : PT Krakatau Steel (KS) dan PT Truba Alam Manunggal Engineering Tbk (TAME)

LOKASI : Cilegon, Banten

KAPASITAS : 400 MW

JENIS & JUMLAH PEMBANGKIT : 5 PLTU

Bahan bakar : batu bara

Distribusi : Jawa-Bali

Page 6: 140940869 Pltu Di Indonesia

PLTU SURALAYA (BANTEN 1)

Pengelola : PT. Indonesia PowerPLTU Suralaya terletak di desa Suralaya

Merak Kotamadya Cilegon, Jawa Barat 7 Km kearah utara dari Pelabuhan Penyeberangan Merak

PLTU Suralaya pembangunannya dilakukan dalam 3 (tiga) tahap yang seluruhnya berjumlah 7 unit :- Tahap I = 2x400 MW beroperasi tahun 1984- Tahap II = 2x400 MW beroperasi tahun 1989- Tahap III = 3x600 MW beroperasi tahun 1997

BAHAN BAKAR : BATU BARAMemasok energi ke JAMALI

Page 7: 140940869 Pltu Di Indonesia

PLTU I JAWA TIMUR-PACITAN

Pengelola : PT. PLN (Persero) dan Konsorsium dari China National Machenery Industry (SINOMACH ), China National Electric Equipment Corporation (CNEEC ) dan Perusahaan Lokal PT. Penta Adi Samudera

Lokasi proyek berada di Desa Sukorejo,

Kecamatan Sudimoro, Kabupaten Pacitan

PLTU I Jawa Timur – Pacitan dengan kapasitas 2 x 315 MW

Page 8: 140940869 Pltu Di Indonesia

PLTU Asam-Asam

Pengelola : PT Mentawai Surak Wisata (PMA)

LOKASI : Desa Asam-asam, Kecamatan Jorong, Kabupaten Tanah Laut, Kalimantan Selatan

KAPASITAS : 2 x 65 MWJENIS & JUMLAH

PEMBANGKIT : Unit I dan II

Bahan bakar: batu bara

Page 9: 140940869 Pltu Di Indonesia

Bangka Power PlantProject Company PT Bangka Manunggal Power

Location Bangka-Belitung

Fuel Coal

Units 2x12 MW

Minimum fuel requirements 30,000 tons per annum

Off Take PLN

Construction status 14%

EPC contractor PT Truba Jaya Engineering (TJE)

Expected COD September 2009

Off Take status 25 years PPA to PLN

Off Take price Rp.448.15/ Kwh (Coal cost pass through)

Designed delivery per annum 147,269,000 Kwh

Financing status Secured project finance from local bank

Page 10: 140940869 Pltu Di Indonesia

Pontianak Power PlantProject Company PT Equator Manunggal Power

Location Pontianak, West Kalimantan

Fuel Coal

Units 2x30 MW

Minimum fuel requirements 218,000 tons per annum

Off Take PLN

Construction status 10%

EPC contractor PT Truba Jaya Engineering (TJE)

Expected COD December 2010

Off Take status 25 years PPA to PLN

Off Take price Rp.447.05/ Kwh (Coal cost pass through)

Designed delivery per annum 350,640,000 Kwh

Financing status Secured syndicated loan from local banks

Page 11: 140940869 Pltu Di Indonesia

CP Bahari Power PlantProject Company PT Central Daya Energi

Location Tulang Bawang, Lampung

Fuel Coal

Units 4x30 MW

Minimum fuel requirements 590,000 tons per annum

Off Take Central Pertiwi Bahari and Central Protein Prima

Construction status 30%

EPC contractor Shanghai Electric Group Company, TAME Turnkey, PT Manunggal Engineering

Expected COD 1st unit in May 2009, and completion in December 2009

Off Take status 30 years PPA to CPB and CPP

Off Take price Rp.1,165/ Kwh

Designed delivery per annum 781,200,000 Kwh

Financing status In discussion

Page 12: 140940869 Pltu Di Indonesia

Kuala Tanjung Power PlantProject Company PT Ranyza Energi

Location Kuala Tanjung, North Sumatra

Fuel Coal

Units 2x135MW

Minimum fuel requirements 930,000 tons per annum

Off Take PLN

Construction status

EPC contractor PT Manunggal Engineering and Shanghai Machinery

Expected COD July 2010

Off Take status 30 years PPA to PLN

Off Take price USD cents 4.748/ Kwh (Coal cost pass through)

Designed delivery per annum 1,789,315,920 Kwh

Financing status In discussion

Page 13: 140940869 Pltu Di Indonesia

Banyuasin Power PlantProject Company PT Banyuasin Power Energi

Location Banyuasin, South Sumatra

Fuel Coal

Units 2x125MW

Minimum fuel requirements 949,000 tons per annum

Off Take PLN

Construction status

EPC contractor TAME Turnkey Contracting

Expected COD December 2010

Off Take status 30 years PPA to PLN

Off Take price USD cents 4.2568/ Kwh (Coal cost pass through)

Designed delivery per annum 1,758,000,000 Kwh

Financing status In discussion

Page 14: 140940869 Pltu Di Indonesia

Banjarsari Power PlantProject Company PT Bukit Pembangkit Innovative

Location Gunung Kembang, South Sumatra

Fuel Coal

Units 2x100MW

Minimum fuel requirements 870,000 tons per annum

Off Take PLN

Construction status

EPC contractor CNEEC

Expected COD September 2010

Off Take status 30 years PPA to PLN

Off Take price Rp.459.4/ Kwh (Coal cost pass through)

Designed delivery per annum 1,401,600,000 Kwh

Financing status Local bank financing